Data Date: February 1, 2022

To create the print version set the font-size:0.5em on both tables. Save as PDF in Chrome; More Settings - Margins:None and Scale:85. Also change link on https://www.sandiego.gov/cip/reports to match the year if starting with quarter 1.

This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City's Adopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects were already awarded to a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. See Construction Contract Types for more information about delivery methods. Also, visit Bid and Contract Opportunities for projects currently in the bid and award phase For more information about this report, call 619-533-4207 or email engineering@sandiego.gov.

PDF icon PRINT -  Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)

File DOWNLOAD -  Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)

summary by asset-managing departments is listed at the bottom of this page.

* To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.

Line    
Number    
Project    
Name    
Project    
Number    
Asset Managing    
Department    
Contract    
Type    
Estimated    
Contract    
Cost ($)    
Estimated    
Total Project    
Cost ($)    
Fiscal Year    
Advertising    
Quarter    
Advertising    
Fiscal Year    
Awarding    
Quarter    
Awarding    
1 Organics Processing Facility L17000.2 Environmental Services Design Build $77,233,000 $85,000,000 FY22 Q3 FY23 Q2
2 Morena Conveyance Southern B15141.4 Public Utilities Design Bid Build $66,174,486 $83,048,725 FY22 Q2 FY23 Q1
3 Morena Conveyance Middle B15141.3 Public Utilities Design Bid Build $63,579,409 $80,281,702 FY22 Q2 FY23 Q1
4 Montezuma PPL/Mid City Pipeline Ph 2 S11026 Public Utilities Design Bid Build $45,173,935 $63,092,200 FY23 Q2 FY23 Q4
5 PWP Central Facility B21151 Public Utilities Design Bid Build $44,200,000 $56,120,000 FY23 Q2 FY23 Q4
6 La Media Road Improvements S15018 Transportation Design Bid Build $42,884,422 $60,635,000 FY23 Q1 FY23 Q2
7 Harbor Drive Trunk Sewer S18006 Public Utilities Design Bid Build $30,987,399 $42,700,000 FY22 Q4 FY23 Q1
8 Murphy Canyon Trunk Sewer Repair/Rehab B17005 Public Utilities Design Bid Build $29,600,000 $38,458,407 FY23 Q3 FY23 Q4
9 AC Water Group 1038 B17153 Public Utilities Design Bid Build $24,725,358 $29,738,676 FY23 Q3 FY23 Q4
10 Clairemont Mesa East Improv 2 (W) B20005 Public Utilities Design Bid Build $16,034,612 $19,243,281 FY23 Q3 FY23 Q4
11 Water Group Job 952 B11048 Public Utilities Design Bid Build $13,163,696 $17,067,714 FY22 Q4 FY23 Q1
12 Corridor Improv 2 (W) B20044 Public Utilities Design Build $13,075,682 $15,472,480 FY23 Q1 FY23 Q2
13 Beyer Park Development S00752 Parks & Recreation Design Bid Build $12,250,000 $16,319,036 FY23 Q3 FY23 Q4
14 Street Reconstruction Group 1801 B17188 Transportation Design Bid Build $10,435,367 $15,218,386 FY23 Q1 FY23 Q2
15 Lake Murray Improv 2 (W) B19135 Public Utilities Design Bid Build $10,200,000 $13,228,375 FY23 Q2 FY23 Q4
16 Maple Canyon Restoration - Phases 1 & 2 B12040 Stormwater Design Bid Build $10,080,553 $17,595,749 FY23 Q2 FY23 Q4
17 Sewer & AC Water Group 765A (S) B18073 Public Utilities Design Bid Build $9,410,549 $11,943,918 FY22 Q4 FY23 Q2
18 Asphalt Overlay Group 2110 B21089 Transportation Design Bid Build $9,280,145 $12,060,000 FY22 Q4 FY23 Q1
19 Asphalt Resurfacing Group 1901 B18134 Transportation Design Bid Build $9,053,597 $13,106,596 FY22 Q3 FY23 Q1
20 College Areas Swr & AC Wtr Main Repl (S) B16025 Public Utilities Design Bid Build $8,962,380 $10,830,212 FY22 Q3 FY23 Q1
21 Asphalt Overlay Group 2110 (SS) B22116 Transportation Design Bid Build $8,587,520 $9,600,000 FY22 Q4 FY23 Q1
22 La Jolla Improv 2 (W) B19117 Public Utilities Design Bid Build $8,002,730 $10,713,727 FY23 Q3 FY23 Q4
23 University Avenue Complete Street Phase1 S18001 Transportation Design Bid Build $7,881,066 $12,379,850 FY22 Q4 FY23 Q1
24 Egger Highland Improvements 1 (S) B20071 Public Utilities Design Build $7,530,000 $11,051,800 FY23 Q3 FY23 Q4
25 Miramar PS Improvement B17190 Public Utilities Design Bid Build $7,376,684 $12,718,399 FY22 Q3 FY23 Q1
26 Salk Neighborhood Park & Joint Use Devel S14007 Parks & Recreation Design Bid Build $7,240,888 $11,287,278 FY22 Q4 FY23 Q1
27 Sewer & AC Water Group 765A (W) B18071 Public Utilities Design Bid Build $7,002,016 $9,524,275 FY22 Q4 FY23 Q2
28 Asphalt Overlay Group 2111 B21090 Transportation Design Bid Build $6,969,420 $9,031,500 FY22 Q3 FY23 Q1
29 Encanto Improv 1 (W) B18209 Public Utilities Design Bid Build $6,968,700 $10,416,500 FY23 Q3 FY23 Q4
30 Sewer & AC Water Group 794 (S) B00395 Public Utilities Design Bid Build $6,461,953 $9,154,285 FY22 Q3 FY23 Q1
31 STORM DRAIN DIVERSION AT THE MBC B19197 Public Utilities Design Bid Build $6,399,933 $9,140,043 FY22 Q4 FY23 Q2
32 College East Improv 1 (S) B21028 Public Utilities Design Build $6,260,580 $10,251,000 FY23 Q3 FY23 Q4
33 Jerabek Park Improvements S20007 Parks & Recreation Design Bid Build $5,719,851 $7,676,400 FY23 Q3 FY23 Q4
34 Corridor Improv 2 (S) B20042 Public Utilities Design Build $5,372,147 $6,948,618 FY23 Q1 FY23 Q2
35 Miramar Reservoir PS New Generator & Upg B19099 Public Utilities Design Bid Build $5,315,316 $7,100,789 FY22 Q3 FY23 Q1
36 Logan Heights LID (South) B15051 Stormwater Design Bid Build $5,248,863 $8,107,200 FY23 Q2 FY23 Q4
37 Sewer Group 836 B13232 Public Utilities Design Bid Build $5,000,000 $9,136,485 FY23 Q2 FY23 Q4
38 Encanto Improv 1 (S) B18206 Public Utilities Design Bid Build $4,905,200 $7,112,700 FY23 Q3 FY23 Q4
39 Bay Terraces Improv 1 (W) B20029 Public Utilities Design Bid Build $4,857,800 $6,549,300 FY23 Q3 FY23 Q4
40 Asphalt Overlay Group 2111 (SS) B22117 Transportation Design Bid Build $4,645,129 $5,746,000 FY22 Q3 FY23 Q1
41 AC Water & Sewer Group 1048 (S) B18095 Public Utilities Design Bid Build $4,537,800 $6,655,500 FY23 Q2 FY23 Q4
42 PQPS Oxygenation Sys B21001 Public Utilities Design Bid Build $4,391,767 $6,525,085 FY23 Q1 FY23 Q2
43 Asphalt Resurfacing Group 1901 (SS) B22115 Transportation Design Bid Build $4,328,403 $6,020,000 FY22 Q3 FY23 Q1
44 SCRIPPS MIRAMAR RANCH LIB S00811 Library Design Bid Build $4,209,105 $6,754,384 FY23 Q3 FY23 Q4
45 AC Water & Sewer Group 1042 (SS) B22128 Transportation Job Order Contract $4,000,000 $4,525,000 FY23 Q3 FY23 Q3
46 University City Improv 1 (W) B19086 Public Utilities Design Bid Build $3,982,800 $5,005,400 FY23 Q3 FY23 Q4
47 Witch Creek Fire Street Improv B22155 Transportation Job Order Contract $3,949,063 $5,260,001 FY23 Q1 FY23 Q2
48 Egger/South Bay Comm Pk ADA Improvements S15031 Parks & Recreation Design Bid Build $3,800,000 $5,580,145 FY23 Q4 FY23 Q4
49 University City Improv 1 (S) B19087 Public Utilities Design Bid Build $3,793,900 $5,242,100 FY23 Q4 FY23 Q4
50 Scripps Ranch Improv 1 (W) B18208 Public Utilities Design Bid Build $3,608,000 $5,307,650 FY22 Q4 FY23 Q2
51 Old Town Improv 1 (w) B20129 Public Utilities Design Bid Build $3,537,265 $6,149,559 FY23 Q3 FY23 Q4
52 Downtown Complete St Impl Phase 3A1 B19144 Transportation Design Bid Build $3,530,000 $5,500,000 FY22 Q4 FY23 Q2
53 Water & Sewer Group 965 (W) B12057 Public Utilities Design Bid Build $3,418,666 $5,471,487 FY23 Q3 FY23 Q4
54 Jamacha Lomita Improv 1 (S) B22011 Public Utilities Design Bid Build $3,315,000 $5,069,700 FY23 Q3 FY23 Q4
55 Miramar Place CNG Facility Upgrades B22041 Environmental Services Design Build $3,300,114 $4,248,000 FY23 Q1 FY23 Q3
56 La Jolla Improv 2 (S) B19105 Public Utilities Design Bid Build $3,161,793 $4,565,693 FY23 Q3 FY23 Q4
57 Water & Sewer Group 965 (S) B12048 Public Utilities Design Bid Build $3,109,200 $4,797,085 FY23 Q3 FY23 Q4
58 Paradise Hills Improv 1 (S) B20024 Public Utilities Design Bid Build $2,986,536 $4,403,200 FY23 Q3 FY23 Q4
59 STORM WATER DIVERSION AT THE SBWRP B20002 Public Utilities Design Bid Build $2,840,650 $4,714,773 FY23 Q1 FY23 Q2
60 Bay Ho Improv 3 (W) B19134 Public Utilities Design Build $2,820,200 $3,869,500 FY23 Q1 FY23 Q4
61 College East Improv 1 (W) B21029 Public Utilities Design Build $2,817,990 $4,662,100 FY23 Q3 FY23 Q4
62 2870 Mobley St SD Replacement B22153 Stormwater Job Order Contract $2,489,928 $3,395,928 FY23 Q1 FY23 Q3
63 Bannock Ave Streetscape Enhancements B10027 Stormwater Design Bid Build $2,441,627 $4,664,294 FY23 Q2 FY23 Q4
64 Mission Bay Athletic Comfort Station Mod B17179 Parks & Recreation Design Bid Build $2,316,000 $3,342,000 FY23 Q4 FY23 Q4
65 Olive St Park Acquisition and Develpment S10051 Parks & Recreation Design Bid Build $2,305,500 $5,704,482 FY23 Q1 FY23 Q3
66 AC Water Group 1027A B21055 Public Utilities Design Bid Build $2,255,790 $3,427,333 FY22 Q4 FY23 Q2
67 John F Kennedy Neighborhood Park Improve B18005 Parks & Recreation Design Bid Build $2,235,951 $3,802,774 FY23 Q3 FY23 Q4
68 AC Water and Sewer Group 1023B (W) B19205 Public Utilities Design Bid Build $2,184,871 $3,145,724 FY23 Q2 FY23 Q4
69 Bermuda Ave Coastal Access Replacement B17110 Parks & Recreation Design Bid Build $2,132,000 $3,650,528 FY23 Q1 FY23 Q2
70 Bay Ho Improv 3 (S) B19136 Public Utilities Design Build $2,010,000 $2,910,000 FY23 Q1 FY23 Q4
71 MBC Gas Detect Syst Replace B20121 Public Utilities Design Bid Build $1,980,000 $3,049,000 FY23 Q3 FY23 Q4
72 North Park Mini Park Ped Improvements B17102 Transportation Design Bid Build $1,897,373 $2,995,600 FY23 Q3 FY23 Q4
73 Hospitality Point Parking Lot Improvemt B19156 Parks & Recreation Design Bid Build $1,893,619 $2,750,000 FY23 Q3 FY23 Q4
74 Citywide Street Lights 1950 B19125 Transportation Job Order Contract $1,862,486 $2,257,481 FY22 Q4 FY23 Q2
75 Highland & Monroe Aves Storm Drain Repl B12096 Stormwater Design Bid Build $1,788,816 $3,382,798 FY23 Q1 FY23 Q2
76 Foothill Blvd & Loring St Roundabout B18008 Transportation Design Bid Build $1,784,505 $2,859,699 FY23 Q1 FY23 Q3
77 Scripps Ranch Improv 1 (S) B18204 Public Utilities Design Bid Build $1,756,934 $2,546,781 FY22 Q4 FY23 Q2
78 Redwood Village/Rolando Park Imp 1A (W) B23047 Public Utilities Job Order Contract $1,740,000 $2,224,000 FY23 Q3 FY23 Q4
79 Bay Terraces Improv 1 (S) B20027 Public Utilities Design Bid Build $1,659,200 $2,350,631 FY23 Q3 FY23 Q4
80 AC Water & Sewer Group 1024 (P) B22108 Transportation Design Bid Build $1,653,581 $1,653,581 FY22 Q3 FY23 Q2
81 Miramar Landfill Storm Water Basin Improvements L18002.3 Environmental Services Design Bid Build $1,649,649 $2,193,000 FY22 Q4 FY23 Q1
82 Police HQ Elevator Modernization B22081 General Services Design Build $1,626,400 $2,450,000 FY23 Q2 FY23 Q4
83 Sewer & AC Water Group 794 (W) B16041 Public Utilities Design Bid Build $1,567,701 $3,041,698 FY22 Q3 FY23 Q1
84 CMP Storm Drain Lining II B20086 Stormwater Job Order Contract $1,500,675 $2,102,320 FY23 Q3 FY23 Q4
85 Kensington Hts #2 Series Circuit Upgrade B17146 Transportation Design Bid Build $1,500,000 $2,700,000 FY22 Q4 FY23 Q1
86 Hospitality Point Comfort Station Imp B19179 Parks & Recreation Design Bid Build $1,490,500 $2,480,000 FY23 Q4 FY23 Q4
87 Redland Improv (W) B23015 Public Utilities Job Order Contract $1,438,974 $2,351,396 FY23 Q2 FY23 Q3
88 North Cove Comfort Station Imp B18234 Parks & Recreation Design Bid Build $1,378,334 $2,300,000 FY23 Q2 FY23 Q3
89 Paradise Hills Improv 1 (W) B20025 Public Utilities Design Bid Build $1,341,364 $1,880,900 FY23 Q3 FY23 Q4
90 College Areas Swr & AC Wtr Main Repl (W) B16022 Public Utilities Design Bid Build $1,340,894 $2,333,741 FY22 Q3 FY23 Q1
91 MLK Rec Center Moisture Intrusion B19001 Parks & Recreation Design Bid Build $1,317,320 $2,815,168 FY22 Q4 FY23 Q2
92 AC Water & Sewer Group 1048 (W) B18088 Public Utilities Design Bid Build $1,231,700 $1,806,500 FY23 Q2 FY23 Q4
93 Clay Ave Mini Park L16000.5 Parks & Recreation Design Bid Build $1,159,100 $2,213,339 FY23 Q1 FY23 Q2
94 Redland Improv (P) B23016 Transportation Job Order Contract $1,096,943 $1,156,288 FY23 Q2 FY23 Q3
95 Mountain View Sports Courts B18192 Parks & Recreation Job Order Contract $974,837 $2,015,085 FY21 Q1 FY23 Q3
96 Chollas Lake Electrical Upgrade L18001.1 Parks & Recreation Design Bid Build $966,035 $1,392,034 FY22 Q3 FY23 Q1
97 Castle Neighborhood New Streetlights B19080 Transportation Design Bid Build $943,717 $1,374,966 FY23 Q1 FY23 Q4
98 Miramar Landfill Office Trailers L17000.7 Environmental Services Multiple $900,000 $1,000,000 FY23 Q3 FY23 Q3
99 MYF Electrical System Upgrade B18034 Airports Design Bid Build $876,846 $1,270,062 FY23 Q1 FY23 Q4
100 Chollas Paint Booth L14002.5 Fleet Services Design Bid Build $849,271 $1,376,000 FY22 Q4 FY23 Q3
101 Clairemont Mesa East Improv 2 (S) B20004 Public Utilities Design Bid Build $843,931 $1,291,628 FY23 Q3 FY23 Q4
102 DeAnza North Parking Lot Improvements B18220 Parks & Recreation Design Bid Build $842,728 $1,378,920 FY23 Q1 FY23 Q2
103 Asphalt Overlay 2201 (SS) B23018 Transportation Job Order Contract $832,600 $1,018,000 FY23 Q3 FY23 Q3
104 Miramar Valves Replacement B20015 Public Utilities Job Order Contract $721,267 $1,398,500 FY23 Q3 FY23 Q3
105 Mira Mesa South Storm Drain Replacement B16175 Stormwater Design Bid Build $655,542 $2,364,903 FY22 Q4 FY23 Q2
106 Mid-City & Eastern Area Signal Mods B17128 Transportation Design Bid Build $620,000 $1,784,593 FY23 Q1 FY23 Q4
107 Citywide Street Lights Group 1701 B17050 Transportation Design Bid Build $529,325 $795,600 FY22 Q4 FY23 Q2
108 Paradise Mesa Crosstie PL CP Improv B21110 Public Utilities Job Order Contract $528,400 $700,000 FY23 Q3 FY23 Q4
109 Howard Ave-Village Pine to Iris Sidewalk B18019 Transportation Design Bid Build $492,382 $1,247,442 FY22 Q3 FY23 Q1
110 AC Water and Sewer Group 1023B (S) B19204 Public Utilities Design Bid Build $489,405 $726,960 FY23 Q2 FY23 Q4
111 Mountain View Improv 1 B20149 Public Utilities Design Bid Build $453,800 $720,799 FY23 Q3 FY23 Q4
112 Lake Murray Improv 2 (S) B19140 Public Utilities Design Bid Build $400,000 $743,738 FY23 Q2 FY23 Q4
113 Citywide Street Lights Group 1702 B17051 Transportation Design Bid Build $374,233 $659,144 FY22 Q4 FY23 Q2
114 Orange Ave RD Imp UU24 B23053 Transportation Job Order Contract $300,000 $100,000 FY23 Q3 FY23 Q2
115 Morena Improv 3A (W) B22152 Public Utilities Design Bid Build $270,000 $400,000 FY23 Q3 FY23 Q4
116 Water & Sewer Group Job 954 (W) B10187 Public Utilities Design Bid Build $200,000 $4,253,026 FY16 Q3 FY23 Q3
117 Orange Ave RD Imp UU24 (SS) B23020 Transportation Job Order Contract $200,000 $200,000 FY23 Q3 FY23 Q4
118 AC Water & Sewer Group 1029 (P) B22062 Transportation Job Order Contract $161,241 $161,241 FY23 Q2 FY23 Q3
119 ADA Torrey Pines APS PROW-S25 B18061 Transportation Design Bid Build $122,094 $359,600 FY22 Q4 FY23 Q1
120 Torrey Pines Gf-Repr Storm Drain Outfall B17152 Parks & Recreation Job Order Contract $117,300 $3,360,000 FY22 Q3 FY23 Q2
121 Alvarado WTP Basins Baffle Wall Doors B21054 Public Utilities Job Order Contract $102,881 $245,800 FY22 Q2 FY23 Q2
122 Kellogg Comfort Station Improvements B20120 General Services Job Order Contract $89,500 $237,855 FY22 Q4 FY23 Q1

Summary By Asset-Managing Departments

Asset-Managing Department Estimated Construction Contract Award Estimated Total Project Cost
Library $4,209,105 $6,754,384
Public Utilities $529,125,443 $714,309,799
Fleet Services $849,271 $1,376,000
Environmental Services $83,082,763 $92,441,000
Public Utilities $453,800 $720,799
Parks & Recreation $48,139,962 $78,067,188
Airports $876,846 $1,270,062
Stormwater $24,206,003 $41,613,191
Transportation $129,914,612 $180,405,570
General Services $1,715,900 $2,687,855
FY 2023 Total $822,573,706 $1,119,645,849

*Estimated Advertise and Award Dates for Pure Water projects are to be determined

Archive of Anticipated CIP Projects