Data Date: Feb 1, 2022
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | Crest Canyon Park Emergency SD Replace | B20019 | Stormwater | Emergency (As-needed) | $439,000 | $9,635,495 | FY20 | Q3 | FY22 | Q2 |
2 | 5604 Campanile Way SD Repair Emergency | B21126 | Stormwater | Emergency (As-needed) | $1,500,000 | $1,765,770 | FY21 | Q4 | FY22 | Q2 |
3 | 4617 Antioch Pl CMP SD Emergency | B21127 | Stormwater | Emergency (As-needed) | $1,200,000 | $1,750,000 | FY21 | Q3 | FY22 | Q2 |
4 | Mississippi St CMP SD Emergency | B21137 | Stormwater | Emergency (As-needed) | $526,000 | $626,000 | FY21 | Q4 | FY22 | Q2 |
5 | 3505 Udall St (CMP) SD Emergency | B21138 | Stormwater | Emergency (As-needed) | $500,000 | $1,250,000 | FY21 | Q4 | FY22 | Q2 |
6 | 3405 Kite Street SD Emergency | B21153 | Stormwater | Emergency (As-needed) | $1,500,000 | $2,000,000 | FY22 | Q1 | FY22 | Q1 |
7 | 3984 Pacific Hwy Pump StationL Emergency | B22013 | Stormwater | Emergency (As-needed) | $425,000 | $650,000 | FY21 | Q4 | FY22 | Q2 |
8 | 4182 60th St & 5973 Alta Mesa Wy Emer | B22052 | Stormwater | Emergency (As-needed) | $2,700,000 | $3,500,000 | FY22 | Q1 | FY22 | Q1 |
9 | Ocean Beach Pier Improvements | S20011 | Parks & Recreation | Design Build | $450,000 | $2,500,000 | FY22 | Q2 | FY22 | Q2 |
10 | Signal Mods in Barrio Logan | B13010 | Transportation | Design Bid Build | $509,000 | $648,400 | FY22 | Q3 | FY22 | Q4 |
11 | Pacific Beach TS Interconnect Upgrade | B15065 | Transportation | Job Order Contract | $933,030 | $1,841,619 | FY22 | Q3 | FY22 | Q4 |
12 | Paradise Mesa Crosstie PL CP Improv | B21110 | Public Utilities | Job Order Contract | $237,200 | $375,100 | FY22 | Q4 | FY22 | Q4 |
13 | Fire Station 48 | S15015 | Fire-Rescue | Design Build | $11,137,500 | $15,091,000 | FY22 | Q3 | FY22 | Q4 |
14 | CMP Storm Drain Lining III | B20087 | Stormwater | Job Order Contract | $665,000 | $980,600 | FY22 | Q3 | FY22 | Q4 |
15 | El Cajon Blvd (Mid-City) Street Lights | B21065 | Transportation | Design Bid Build | $311,658 | $361,658 | FY21 | Q4 | FY22 | Q2 |
16 | Talmadge Traffic Calming Infrastructure | S17001 | Parks & Recreation | Design Bid Build | $177,100 | $337,964 | FY21 | Q3 | FY22 | Q1 |
17 | AC Water & Sewer Group 1056 (W) | B18181 | Public Utilities | Design Bid Build | $8,466,401 | $10,976,801 | FY21 | Q3 | FY22 | Q1 |
18 | AC Water & Sewer Group 1056 (S) | B18182 | Public Utilities | Design Bid Build | $368,705 | $428,605 | FY21 | Q3 | FY22 | Q1 |
19 | Talmadge AC Water Main Replacement | B18197 | Public Utilities | Design Bid Build | $1,317,345 | $2,001,660 | FY21 | Q3 | FY22 | Q1 |
20 | Cajon Way CMP Storm Drain Emergency | B21115 | Stormwater | Emergency (As-needed) | $1,100,000 | $1,750,000 | FY21 | Q3 | FY22 | Q1 |
21 | El Cajon Bl-Highland-58th Improv | B17003 | Transportation | Design Bid Build | $573,647 | $1,316,448 | FY21 | Q4 | FY22 | Q2 |
22 | Santa Clara Playground Improvements | B19029 | Parks & Recreation | Design Bid Build | $819,242 | $2,109,500 | FY21 | Q4 | FY22 | Q2 |
23 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation | Design Bid Build | $561,646 | $1,409,500 | FY21 | Q4 | FY22 | Q2 |
24 | Balboa Park Botanical Bldg Improvements | S20005 | Parks & Recreation | Design Build | $14,261,647 | $21,452,999 | FY21 | Q2 | FY22 | Q1 |
25 | San Diego NC-MBC Improvements | B17006 | Public Utilities | Design Bid Build | $2,899,148 | $10,038,088 | FY21 | Q3 | FY22 | Q1 |
26 | PWP NCWRP Flow Equalization Basin | B21059 | Public Utilities | Design Bid Build | $11,886,000 | $18,350,051 | FY21 | Q4 | FY22 | Q2 |
27 | MBC Equipment Upgrades | S17013 | Public Utilities | Design Bid Build | $37,187,542 | $47,645,194 | FY21 | Q3 | FY22 | Q1 |
28 | MBGC Clubhouse Demo/Prtbl Building Instl | S01090 | Parks & Recreation | Design Bid Build | $5,161,700 | $7,685,084 | FY21 | Q4 | FY22 | Q2 |
29 | MBGC Irrigation & Electrical Upgrades | S11010 | Parks & Recreation | Design Bid Build | $9,199,700 | $10,661,700 | FY21 | Q4 | FY22 | Q2 |
30 | Wangenheim Joint Use Facility | S15007 | Parks & Recreation | Design Bid Build | $6,834,000 | $9,645,952 | FY21 | Q2 | FY22 | Q2 |
31 | Accelerated MH Referral Group 1 | B19097 | Public Utilities | Design Bid Build | $1,026,647 | $2,047,033 | FY21 | Q4 | FY22 | Q2 |
32 | RIVIERA DEL SOL NEIGHBORHOOD PARK | S00999 | Parks & Recreation | Design Bid Build | $5,524,537 | $9,570,838 | FY22 | Q1 | FY22 | Q2 |
33 | Governor Dr @ Lakewood St Traffic Signal | B17016 | Transportation | Design Bid Build | $306,925 | $558,784 | FY21 | Q4 | FY22 | Q2 |
34 | Adams Ave (1620) Storm Drain Replacement | B13102 | Stormwater | Design Bid Build | $493,555 | $1,901,933 | FY22 | Q2 | FY22 | Q4 |
35 | SCRIPPS MIRAMAR RANCH LIB | S00811 | Library Department | Design Bid Build | $4,208,097 | $6,253,376 | FY22 | Q3 | FY22 | Q4 |
36 | Otay WTP-Basin #1 Concrete Restoration | B17092 | Public Utilities | Design Bid Build | $1,245,625 | $4,747,270 | FY22 | Q2 | FY22 | Q4 |
37 | Clairemont Mesa E Improv 1 (W) | B18200 | Public Utilities | Design Bid Build | $5,142,770 | $6,993,986 | FY22 | Q1 | FY22 | Q4 |
38 | Clairemont Mesa E Improv 1 (S) | B18202 | Public Utilities | Design Bid Build | $2,777,959 | $3,960,932 | FY22 | Q1 | FY22 | Q4 |
39 | MYF Electrical System Upgrade | B18034 | Airports Department | Design Bid Build | $864,846 | $1,270,062 | FY22 | Q2 | FY22 | Q4 |
40 | Chollas Paint Booth | L14002.5 | Fleet Services | Design Bid Build | $303,000 | $666,000 | FY21 | Q2 | FY22 | Q3 |
41 | Sidewalk Replacement Group 1903-SE & CH | B19014 | Transportation | Design Bid Build | $1,240,000 | $1,809,007 | FY22 | Q3 | FY22 | Q3 |
42 | Damon Ave Water Main Extension & AC Repl | B18215 | Public Utilities | Design Bid Build | $791,789 | $1,590,707 | FY22 | Q4 | FY22 | Q4 |
43 | Asphalt Resurfacing Group 1901 | B18134 | Transportation | Design Bid Build | $9,571,046 | $10,486,046 | FY22 | Q3 | FY22 | Q3 |
44 | Chollas Lake Electrical Upgrade | L18001.1 | Parks & Recreation Department | Design Bid Build | $424,000 | $850,000 | FY22 | Q3 | FY22 | Q3 |
45 | Kearny Mesa Facility Improvements | S20009 | Citywide | Design Bid Build | $14,864,176 | $16,421,600 | FY22 | Q3 | FY22 | Q4 |
46 | Morena Improv 3 (W) | B21056 | Public Utilities | Design Build | $1,202,657 | $1,754,175 | FY21 | Q4 | FY22 | Q3 |
47 | Morena Improv 3 (S) | B21064 | Public Utilities | Design Build | $426,684 | $648,862 | FY21 | Q4 | FY22 | Q3 |
48 | Pacific Highlands Ranch Branch Library | S14023 | Library Department | Design Bid Build | $17,902,982 | $26,164,178 | FY22 | Q2 | FY22 | Q3 |
49 | Hickman Fields Athletic Area | S00751 | Parks & Recreation | Design Bid Build | $8,037,928 | $11,066,319 | FY22 | Q2 | FY22 | Q4 |
50 | Salk Neighborhood Park & Joint Use Devel | S14007 | Parks & Recreation | Design Bid Build | $5,577,278 | $7,237,278 | FY22 | Q2 | FY22 | Q3 |
51 | AC Water & Sewer Group 1036 (W) | B18121 | Public Utilities | Design Bid Build | $4,730,600 | $6,311,527 | FY21 | Q3 | FY22 | Q3 |
52 | AC Water & Sewer Group 1036 (S) | B18123 | Public Utilities | Design Bid Build | $1,456,393 | $2,237,673 | FY21 | Q3 | FY22 | Q3 |
53 | Tecolote Canyon Trunk Sewer Improvement | S15020 | Public Utilities | Design Bid Build | $38,944,050 | $45,550,000 | FY22 | Q3 | FY22 | Q4 |
54 | Bermuda Ave Coastal Access Replacement | B17110 | Parks & Recreation | Design Bid Build | $1,792,528 | $3,050,528 | FY22 | Q2 | FY22 | Q3 |
1 | Balboa Park Federal Bldg Improvements | B20066 | Parks & Recreation | Design Bid Build | $1,741,000 | $2,793,000 | FY22 | Q2 | FY22 | Q4 |
2 | Miramar Valves Replacement | B20015 | Public Utilities | Design Bid Build | $525,000 | $859,000 | FY22 | Q3 | FY22 | Q4 |
3 | Harbor Drive Trunk Sewer | S18006 | Public Utilities | Design Bid Build | $19,400,000 | $26,500,000 | FY22 | Q1 | FY22 | Q3 |
4 | Mountain View Sports Courts | B18192 | Parks & Recreation | Job Order Contract | $546,000 | $1,555,000 | FY21 | Q1 | FY22 | Q4 |
5 | MLK Rec Center Moisture Intrusion | B19001 | Parks & Recreation | Design Bid Build | $1,020,093 | $2,515,168 | FY22 | Q2 | FY22 | Q4 |
6 | Citywide Street Lights 1950 | B19125 | Transportation & Storm Water | Job Order Contract | $2,540,231 | $3,044,731 | FY21 | Q4 | FY22 | Q4 |
7 | AC Water & Sewer Group 1056 (BL) | B21136 | Transportation | Design Bid Build | $64,000 | $64,000 | FY21 | Q3 | FY22 | Q1 |
8 | Linda Vista Skate Park Phase 2 | B19062 | Parks & Recreation | Job Order Contract | $145,000 | $429,769 | FY21 | Q4 | FY22 | Q2 |
9 | Organics Processing Facility | L17000.2 | Environmental Services | Design-Build | $49,000,000 | $51,000,000 | FY22 | Q2 | FY22 | Q2 |
10 | Palm Avenue Storm Drain Replacement | B17163 | Stormwater | Job Order Contract | $190,869 | $564,208 | FY22 | Q1 | FY22 | Q2 |
11 | Point Loma Library Chiller Replacement | B19203 | Library Department | Job Order Contract | $252,756 | $560,000 | FY21 | Q3 | FY22 | Q2 |
12 | Torrey Highlands Neighborhood Park Upgra | S16036 | Parks & Recreation | Design Bid Build | $1,020,696 | $1,717,937 | FY20 | Q2 | FY22 | Q3 |
13 | Torrey Pines Gf-Repr Storm Drain Outfall | B17152 | Stormwater | Design Bid Build | $1,540,000 | $3,360,000 | FY22 | Q3 | FY22 | Q3 |
14 | Kearny Mesa Pipeline Manway | B20072 | Public Utilities | Job Order Contract | $492,786 | $1,027,425 | FY22 | Q3 | FY22 | Q3 |
15 | Marlesta/Beagle (Gen-B/M-Ashf) SL UU465 | B18127 | Transportation | Design Bid Build | $211,000 | $350,000 | FY22 | Q2 | FY22 | Q3 |
16 | Cchavez Pkwy (I5-Comml) UU27 | B21092 | Transportation | Design Bid Build | $60,000 | $150,000 | FY21 | Q4 | FY22 | Q3 |
17 | Miramar Place Repair Shop Upgrades | TBD4 | Environmental Services | Design Bid Build | $1,286,000 | $1,500,000 | FY22 | Q3 | FY22 | Q3 |
18 | Miramar Landfill Fee Booth Truck Scale #3 Replacement | TBD5 | Environmental Services | Sole Source | $190,000 | $220,000 | FY22 | Q3 | FY22 | Q3 |
19 | Miramar Landfill Outbound Scale #5 Replacement | TBD6 | Environmental Services | Sole Source | $190,000 | $220,000 | FY22 | Q3 | FY22 | Q3 |
20 | Howard Ave-Village Pine to Iris Sidewalk | B18019 | Transportation | Design Bid Build | $380,000 | $1,050,060 | FY22 | Q3 | FY22 | Q4 |
21 | Miramar Reservoir Pump Station Improveme | B17190 | Public Utilities | Design Bid Build | $9,024,353 | $14,621,623 | FY22 | Q3 | FY22 | Q4 |
22 | Miramar Reservoir PS New Generator & Upg | B19099 | Public Utilities | Design Bid Build | $2,660,874 | $4,235,874 | FY22 | Q3 | FY22 | Q4 |
23 | Penasquitos Pump Stn Oxygenation System | B21001 | Public Utilities | Design Bid Build | $2,458,357 | $3,482,591 | FY22 | Q3 | FY22 | Q4 |
24 | STORM WATER DIVERSION AT THE PLWTP | B20001 | Public Utilities | Design Bid Build | $3,410,400 | $5,208,600 | FY22 | Q3 | FY22 | Q4 |
25 | Citywide Street Lights Group 1801 | B18012 | Transportation | Design Bid Build | $162,762 | $250,000 | FY22 | Q3 | FY22 | Q4 |
26 | Sewer & AC Water Group 765A (W) | B18071 | Public Utilities | Design Bid Build | $7,018,230 | $9,260,223 | FY22 | Q3 | FY22 | Q4 |
27 | Sewer & AC Water Group 765A (S) | B18073 | Public Utilities | Design Bid Build | $7,018,230 | $9,232,230 | FY22 | Q3 | FY22 | Q4 |
28 | ADA Torrey Pines APS PROW-S25 | B18061 | Transportation | Design Bid Build | $25,900 | $359,600 | FY22 | Q3 | FY22 | Q4 |
29 | Asphalt Overlay Group 2110 | B21089 | Transportation | Design Bid Build | $7,384,901 | $9,060,525 | FY22 | Q3 | FY22 | Q4 |
30 | AC Water & Sewer Group 1052 (W) | B18092 | Public Utilities | Design Bid Build | $10,985,000 | $13,218,000 | FY22 | Q2 | FY22 | Q4 |
31 | AC Water & Sewer Group 1052 (S) | B18096 | Public Utilities | Design Bid Build | $3,547,000 | $4,965,800 | FY22 | Q2 | FY22 | Q4 |
32 | Alvarado Trunk Sewer Phase IV | S15019 | Public Utilities | Design Bid Build | $54,300,000 | $66,874,811 | FY22 | Q3 | FY22 | Q4 |
33 | Maple Canyon Restoration - Phases 1 & 2 | B12040 | Stormwater | Design Bid Build | $9,504,293 | $16,876,996 | FY22 | Q3 | FY22 | Q4 |
34 | Tierrasanta Improv 1 (s) | B21003 | Public Utilities | Design Bid Build | $2,830,000 | $3,590,000 | FY22 | Q2 | FY22 | Q4 |
35 | Ocean Air CP Comfort Station & Park Impr | S16031 | Parks & Recreation | Design Bid Build | $1,223,021 | $2,181,793 | FY22 | Q3 | FY22 | Q4 |
36 | Morena Conveyance Middle | B15141.3 | Public Utilities | Design Bid Build | $56,719,052 | $71,351,280 | FY22 | Q2 | FY22 | Q4 |
37 | Morena Conveyance Southern | B15141.4 | Public Utilities | Design Bid Build | $60,077,352 | $73,727,679 | FY22 | Q2 | FY22 | Q4 |
38 | Morena Pipeline | S16027 | Public Utilities | Design Bid Build | $33,444,875 | $39,609,023 | FY22 | Q3 | FY22 | Q4 |
39 | Dusty Rhodes Playground | B19181 | Parks & Recreation | Design Bid Build | $1,015,640 | $1,944,000 | FY22 | Q4 | FY22 | Q4 |
40 | Tecolote Cyn GC Water Conn | B15203 | Public Utilities | Design Bid Build | $450,000 | $525,500 | FY22 | Q2 | FY22 | Q4 |
41 | Accelerated Sewer Referral Group 851 | B19063 | Public Utilities | Design Bid Build | $4,900,773 | $6,217,408 | FY22 | Q3 | FY22 | Q4 |
42 | Mountain View Improv 1 (S) | B20149 | Public Utilities | Job Order Contract | $453,800 | $720,799 | FY22 | Q3 | FY22 | Q4 |
43 | Citywide Street Lights Group 1701 | B17050 | Transportation | Design Bid Build | $419,500 | $705,600 | FY21 | Q4 | FY22 | Q4 |
44 | Citywide Street Lights Group 1702 | B17051 | Transportation | Design Bid Build | $458,844 | $749,144 | FY21 | Q4 | FY22 | Q4 |
45 | Regional Arterial Guardrail Group 2a | B18201 | Transportation | Design Bid Build | $142,000 | $311,500 | FY22 | Q3 | FY22 | Q4 |
46 | Miramar Trailer for new office space needs LF Ops | L17000.6 | Environmental Services | Design Build | $900,000 | $1,000,000 | FY22 | Q3 | FY22 | Q4 |
47 | University Avenue Complete Street Phase1 | S18001 | Transportation | Design Bid Build | $6,921,000 | $10,874,460 | FY21 | Q3 | FY22 | Q4 |
48 | Soledad Pressure Reducing Stn Hatch (w) | B21040 | Public Utilities | Design Bid Build | $325,000 | $500,000 | FY22 | Q3 | FY22 | Q3 |
49 | Alvarado WTP Basins Baffle Wall Doors | B21054 | Public Utilities | Job Order Contract | $114,041 | $205,800 | FY22 | Q3 | FY22 | Q3 |
50 | Reo Drive New Streetlights | B19079 | Transportation | Job Order Contract | $287,500 | $428,300 | FY22 | Q3 | FY22 | Q3 |
51 | Miramar Place CNG Facility Upgrades | B22041 | Environmental Services | Sole Source | $3,100,000 | $3,700,000 | FY22 | Q3 | FY22 | Q3 |
52 | Hard Court Improvements | B22045 | Parks & Recreation | To Be Determined | $1,070,000 | $1,070,000 | FY22 | Q2 | FY22 | Q3 |
53 | Highland & Monroe Aves Storm Drain Repl | B12096 | Stormwater | Design Bid Build | $1,586,000 | $3,276,516 | FY22 | Q3 | FY22 | Q4 |
54 | Storm Drain Group 968 | B15028 | Stormwater | Design Bid Build | $156,810 | $296,757 | FY20 | Q3 | FY22 | Q4 |
55 | Mt Acadia (Mt Alifan-Mt Burnham)SL UU621 | B17012 | Transportation | Job Order Contract | $205,200 | $298,000 | FY21 | Q4 | FY22 | Q1 |
56 | Redwood (Pershing-Boundary) SL UU611 | B20095 | Transportation | Job Order Contract | $23,119 | $152,319 | FY21 | Q4 | FY22 | Q2 |
57 | Balboa Park Golf Course - Bathroom Remod | B20064 | Parks & Recreation | City Forces | $109,600 | $217,600 | FY22 | Q2 | FY22 | Q2 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Airports Department | $864,846 | $1,270,062 |
Library Department | $22,363,835 | $32,977,554 |
Parks & Recreation Department | $424,000 | $850,000 |
Transportation & Storm Water | $2,540,231 | $3,044,731 |
Fleet Services | $303,000 | $666,000 |
Parks & Recreation | $66,288,356 | $101,151,930 |
Public Utilities | $400,262,638 | $521,591,330 |
Fire-Rescue | $11,137,500 | $15,091,000 |
Citywide | $14,864,176 | $16,421,600 |
Environmental Services | $54,666,000 | $57,640,000 |
Stormwater | $24,026,527 | $50,184,275 |
Transportation | $30,191,032 | $41,825,470 |
FY 2022 Total | $627,932,141 | $842,713,953 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015