Data Date: Feb 1, 2021
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | Fire-Rescue Air Ops Facility - PH II | S18007 | Fire-Rescue | Design Build | $1,000,000 | $22,481,000 | FY20 | Q2 | FY21 | Q1 |
2 | J Street Mini Park Improvement | L16000.6 | Parks & Recreation | Design Bid Build | $847,913 | $1,536,095 | FY20 | Q1 | FY21 | Q1 |
3 | Mingei Museum Dome Waterproofing | B19067 | Parks & Recreation | Minor Contract | $445,066 | $630,066 | FY20 | Q1 | FY21 | Q1 |
4 | FAIRBROOK NEIGHBORHOOD PARK - DEVELOPMEN | S01083 | Parks & Recreation | Design Bid Build | $3,535,354 | $6,011,280 | FY20 | Q4 | FY21 | Q1 |
5 | PHR Pump Track Fence | B20031 | Parks & Recreation | Emergency (As-needed) | $274,903 | $274,903 | FY21 | Q1 | FY21 | Q1 |
6 | Market Street Water Pipe Replacement | B17052 | Public Utilities | Job Order Contract | $1,528,878 | $1,926,448 | FY20 | Q1 | FY21 | Q1 |
7 | Market Street Sewer Pipe Replacement | B17054 | Public Utilities | Job Order Contract | $342,555 | $486,973 | FY20 | Q1 | FY21 | Q1 |
8 | Otay WTP Raw Wtr PS Rpr/Repl Emergency | B21025 | Public Utilities | Emergency (As-needed) | $100,000 | $200,000 | FY21 | Q1 | FY21 | Q1 |
9 | Miramar Ranch North Paving G1 | B19007 | Transportation & Storm Water | Design Bid Build | $3,925,870 | $5,080,555 | FY20 | Q3 | FY21 | Q1 |
10 | Market St-47th St to Euclid Complete St | S16061 | Transportation & Storm Water | Design Bid Build | $6,110,157 | $9,719,909 | FY19 | Q4 | FY21 | Q1 |
11 | Cardinal Road Emergency SD Replacement | B19090 | Transportation & Storm Water | Sole Source Emergency | $106,700 | $5,407,954 | FY19 | Q2 | FY21 | Q1 |
12 | Nimitz Bridge at NTC Rehabilitation | B15198 | Transportation & Storm Water | Job Order Contract | $344,666 | $930,000 | FY20 | Q4 | FY21 | Q1 |
13 | Center City - New Traffic Signals | B18083 | Transportation & Storm Water | Design Bid Build | $1,345,317 | $2,152,767 | FY20 | Q3 | FY21 | Q1 |
14 | 7649 Shorewood Dr SD Repl Emergency | B20143 | Transportation & Storm Water | Emergency (As-needed) | $450,000 | $750,000 | FY20 | Q4 | FY21 | Q1 |
15 | Downtown Complete St Impl Phase 2 | B19143 | Transportation & Storm Water | Design Bid Build | $1,792,937 | $3,941,565 | FY20 | Q2 | FY21 | Q1 |
16 | 5865 Cozzens Street SD Emergency | B20068 | Transportation & Storm Water | Emergency (As-needed) | $40,629 | $750,000 | FY20 | Q2 | FY21 | Q1 |
17 | ADA S/W Group 4E College | B16107 | Transportation & Storm Water | Job Order Contract | $360,000 | $751,607 | FY20 | Q3 | FY21 | Q1 |
18 | 836 Gage Drive SD Replacement Emergency | B20109 | Transportation & Storm Water | Emergency (As-needed) | $600,000 | $750,000 | FY20 | Q3 | FY21 | Q1 |
19 | La Jolla Village/I-805 Landscape Maint | S15017 | Transportation & Storm Water | Design Bid Build | $438,069 | $610,000 | FY20 | Q4 | FY21 | Q1 |
20 | Fanuel St PI Archer to Tourmaline UUD | B00721 | Transportation & Storm Water | Job Order Contract | $90,344 | $142,047 | FY20 | Q3 | FY21 | Q1 |
21 | Seminole PH2 (El Cajon-Stanley) SL UU630 | B17013 | Transportation & Storm Water | Job Order Contract | $83,264 | $120,000 | FY21 | Q1 | FY21 | Q1 |
22 | Ingulf St (Morena Bl-Erie St) SL UU123 | B18126 | Transportation & Storm Water | To Be Determined | $96,673 | $144,473 | FY20 | Q3 | FY21 | Q1 |
23 | OB Dog Beach Accessibility Improvements | B19000 | Parks & Recreation | Job Order Contract | $442,526 | $1,143,306 | FY20 | Q4 | FY21 | Q2 |
24 | Island Ave Mini Park Improvements | L16000.2 | Parks & Recreation | Design Bid Build | $189,720 | $2,688,163 | FY20 | Q2 | FY21 | Q2 |
25 | TP South Golf Course Improvements | B17063 | Parks & Recreation | Multiple Award Construction Contract | $1,630,240 | $18,680,240 | FY21 | Q1 | FY21 | Q2 |
26 | Buchanan Canyon SM Rpr/Repl Emergency | B21080 | Public Utilities | Emergency (As-needed) | $300,000 | $500,000 | FY21 | Q2 | FY21 | Q2 |
27 | SEWER GJ 798C | B00409 | Public Utilities | Design Bid Build | $1,275,193 | $590,885 | FY20 | Q4 | FY21 | Q2 |
28 | Accelerated Pipeline Rehab Ref Group 846 | B18185 | Public Utilities | Design Bid Build | $1,275,193 | $1,177,588 | FY20 | Q4 | FY21 | Q2 |
29 | Rolando Improv 1 (W) | B20126 | Public Utilities | Job Order Contract | $3,765,110 | $5,506,477 | FY21 | Q2 | FY21 | Q2 |
30 | Sewer and AC Water Group 1032 (S) | B17104 | Public Utilities | Design Bid Build | $6,389,000 | $8,518,000 | FY20 | Q3 | FY21 | Q2 |
31 | Sewer and AC Water Group 1032 (W) | B17105 | Public Utilities | Design Bid Build | $7,071,000 | $10,348,685 | FY20 | Q3 | FY21 | Q2 |
32 | Mission Beach Water & Sewer Repl (W) | B17169 | Public Utilities | Design Bid Build | $13,035,280 | $14,317,814 | FY20 | Q3 | FY21 | Q2 |
33 | Mission Beach Water & Sewer Repl (S) | B17170 | Public Utilities | Design Bid Build | $2,194,515 | $3,124,042 | FY20 | Q3 | FY21 | Q2 |
34 | Orange Av PH3 Central-Fairmount SL UU24 | B18130 | Transportation & Storm Water | To Be Determined | $234,878 | $266,856 | FY20 | Q3 | FY21 | Q2 |
35 | San Diego Av (Old Town-McKee) SL UU598 | B20045 | Transportation & Storm Water | To Be Determined | $234,878 | $337,022 | FY20 | Q3 | FY21 | Q2 |
36 | Rancho Mission Canyon Emergency | B20124 | Transportation & Storm Water | Emergency (As-needed) | $120,000 | $1,500,000 | FY20 | Q3 | FY21 | Q2 |
37 | Worden St Storm Drain Emergency | B20144 | Transportation & Storm Water | Emergency (As-needed) | $927,500 | $1,103,070 | FY20 | Q4 | FY21 | Q2 |
38 | 1st Ave CMP Storm Drain Emergency | B21005 | Transportation & Storm Water | Design Bid Build | $200,000 | $290,000 | FY21 | Q1 | FY21 | Q2 |
39 | Rancho Penasquitos Paving Group 1 | B20138 | Transportation & Storm Water | Job Order Contract | $2,025,496 | $3,779,352 | FY20 | Q4 | FY21 | Q2 |
40 | Miramar Landfill Trailer Replacements | L17000.6 | Environmental Services | Design Build | $300,000 | $400,000 | FY21 | Q2 | FY21 | Q3 |
41 | Miramar Landfill Storm Water Basin Improvements | L18002.3 | Environmental Services | Design Bid Build | $6,000,000 | $8,000,000 | FY21 | Q2 | FY21 | Q3 |
42 | City Heights Pool Reconstruction | B19068 | Parks & Recreation | Design Bid Build | $4,352,130 | $5,768,807 | FY20 | Q1 | FY21 | Q3 |
43 | Olive St Park Acquisition and Develpment | S10051 | Parks & Recreation | Design Bid Build | $1,983,000 | $5,671,585 | FY21 | Q1 | FY21 | Q3 |
44 | MLK Rec Center Moisture Intrusion | B19001 | Parks & Recreation | Design Bid Build | $1,020,093 | $2,515,168 | FY21 | Q1 | FY21 | Q3 |
45 | Adult Fitness Course East Shore | B18223 | Parks & Recreation | Design Bid Build | $1,060,000 | $1,954,000 | FY21 | Q2 | FY21 | Q3 |
46 | Torrey Highlands Neighborhood Park Upgra | S16036 | Parks & Recreation | Design Bid Build | $660,000 | $1,057,937 | FY20 | Q2 | FY21 | Q3 |
47 | Tecolote South Parking Lot Improvements | B19017 | Parks & Recreation | Design Bid Build | $419,282 | $528,000 | FY21 | Q2 | FY21 | Q3 |
48 | Sewer Group 776A | B16034 | Public Utilities | Design Bid Build | $3,348,013 | $4,566,148 | FY20 | Q3 | FY21 | Q3 |
49 | SBWRP Variable Frequency Drive Repl | B19066 | Public Utilities | Design Bid Build | $508,292 | $1,359,792 | FY20 | Q4 | FY21 | Q3 |
50 | AC Water Group 1038 | B17153 | Public Utilities | Design Bid Build | $22,286,634 | $29,568,478 | FY21 | Q2 | FY21 | Q3 |
51 | Pipeline Rehabilitation AY-1 | B18212 | Public Utilities | Design Bid Build | $3,680,000 | $7,841,500 | FY21 | Q2 | FY21 | Q3 |
52 | University of SD FH/FS Reconnection | B20136 | Public Utilities | Job Order Contract | $183,116 | $208,116 | FY21 | Q1 | FY21 | Q3 |
53 | Water Group 968 | B14099 | Public Utilities | Design Bid Build | $2,152,300 | $5,064,806 | FY21 | Q1 | FY21 | Q3 |
54 | Morena Conveyance Northern | B15141.2 | Public Utilities | Design Bid Build | $86,344,658 | $103,626,360 | FY21 | Q2 | FY21 | Q3 |
55 | North City Pure Water Pump Station | B15140 | Public Utilities | Design Bid Build | $13,350,922 | $17,617,145 | FY19 | Q3 | FY21 | Q3 |
56 | Balboa Park Pipeline Repl Ph III (W) | B17141 | Public Utilities | Design Bid Build | $3,010,000 | $5,004,135 | FY20 | Q3 | FY21 | Q3 |
57 | Sewer and AC Water Group 812 (S) | B00426 | Public Utilities | Design Bid Build | $3,047,000 | $10,953,041 | FY21 | Q1 | FY21 | Q3 |
58 | Sewer and AC Water Group 812 (W) | B17115 | Public Utilities | Design Bid Build | $1,916,000 | $5,724,222 | FY21 | Q1 | FY21 | Q3 |
59 | PWP North City Pure Water Facility Pkg 2 | B21058 | Public Utilities | Design Bid Build | $356,681,930 | $456,900,000 | FY21 | Q1 | FY21 | Q3 |
60 | PWP Morena Wastewater Pump Station | B21061 | Public Utilities | Design Bid Build | $95,974,999 | $126,441,656 | FY21 | Q2 | FY21 | Q3 |
61 | Tierrasanta Pool Stairway Replacement | B20115 | Real Estate Assets | Job Order Contract | $222,271 | $327,000 | FY20 | Q3 | FY21 | Q3 |
62 | Wellborn Street Storm Drain Emergency | B19101 | Transportation & Storm Water | Sole Source Emergency | $47,161 | $1,857,535 | FY19 | Q2 | FY21 | Q3 |
63 | Concrete Street Panel Repl - Coast Bl | B20046 | Transportation & Storm Water | Design Bid Build | $829,591 | $1,723,480 | FY21 | Q1 | FY21 | Q3 |
64 | Coast Cave SD Accelerated Replacement | B20076 | Transportation & Storm Water | Design Bid Build | $223,095 | $389,200 | FY21 | Q1 | FY21 | Q3 |
65 | Palm Avenue Storm Drain Replacement | B17163 | Transportation & Storm Water | Design Bid Build | $288,700 | $477,380 | FY20 | Q4 | FY21 | Q3 |
66 | ADA Curb Ramp Winder & McKee | B16108 | Transportation & Storm Water | Design Bid Build | $310,567 | $961,800 | FY20 | Q4 | FY21 | Q3 |
67 | Mt Albertine Ave CMP SD Emergency | B21006 | Transportation & Storm Water | Emergency (As-needed) | $360,000 | $550,000 | FY21 | Q2 | FY21 | Q3 |
68 | Hillside Dr (SD Install/Resurf) Improv | B20151 | Transportation & Storm Water | Design Build | $640,000 | $850,000 | FY21 | Q1 | FY21 | Q3 |
69 | Torrey Pines Fire Station | S19003 | Fire-Rescue | Design Build | $16,010,775 | $20,555,999 | FY21 | Q2 | FY21 | Q4 |
70 | Chollas Crane Replacement | L14002.4 | Fleet Operations | Design Bid Build | $300,000 | $555,000 | FY21 | Q2 | FY21 | Q4 |
71 | Chollas Paint Booth | L14002.5 | Fleet Operations | Design Bid Build | $303,000 | $666,000 | FY21 | Q2 | FY21 | Q4 |
72 | Pacific Highlands Ranch Branch Library | S14023 | Library | Design Bid Build | $17,443,915 | $26,164,178 | FY21 | Q3 | FY21 | Q4 |
73 | Point Loma Library Chiller Replacement | B19203 | Library | Job Order Contract | $175,172 | $430,000 | FY21 | Q3 | FY21 | Q4 |
74 | SCRIPPS MIRAMAR RANCH LIB | S00811 | Library | Design Bid Build | $4,270,000 | $6,076,377 | FY21 | Q3 | FY21 | Q4 |
75 | Tecolote North Parking Lot Improvements | B18231 | Parks & Recreation | Design Bid Build | $706,160 | $869,000 | FY21 | Q2 | FY21 | Q4 |
76 | Tecolote North Comfort Station Imp | B18233 | Parks & Recreation | Design Bid Build | $1,639,422 | $1,963,000 | FY21 | Q2 | FY21 | Q4 |
77 | Tecolote South Playground Improvements | B19016 | Parks & Recreation | Design Bid Build | $2,537,976 | $3,027,000 | FY21 | Q2 | FY21 | Q4 |
78 | Tecolote North Playground Improvements | B18232 | Parks & Recreation | Design Bid Build | $1,469,984 | $2,964,000 | FY21 | Q2 | FY21 | Q4 |
79 | Tecolote South Comfort Station Imp | B19015 | Parks & Recreation | Design Bid Build | $1,608,085 | $1,931,000 | FY21 | Q2 | FY21 | Q4 |
80 | Sherman Heights Com Center Playground | B18006 | Parks & Recreation | Design Bid Build | $350,000 | $697,471 | FY20 | Q1 | FY21 | Q4 |
81 | Dennery Ranch Neighborhood Park | S00636 | Parks & Recreation | Agency/ Developer Managed Built - City Paid | $5,070,000 | $15,099,999 | FY19 | Q2 | FY21 | Q4 |
82 | Salk Neighborhood Park & Joint Use Devel | S14007 | Parks & Recreation | Design Bid Build | $5,576,686 | $7,237,278 | FY21 | Q3 | FY21 | Q4 |
83 | Chollas Lake Electrical Upgrade | L18001.1 | Parks & Recreation | Design Bid Build | $424,000 | $850,000 | FY21 | Q4 | FY21 | Q4 |
84 | Mountain View Sports Courts | B18192 | Parks & Recreation | Job Order Contract | $546,000 | $1,080,000 | FY21 | Q3 | FY21 | Q4 |
85 | La Paz Mini Park | S11103 | Parks & Recreation | Design Bid Build | $1,502,338 | $2,602,840 | FY21 | Q2 | FY21 | Q4 |
86 | Talmadge Traffic Calming Infrastructure | S17001 | Parks & Recreation | Design Bid Build | $173,938 | $310,000 | FY21 | Q3 | FY21 | Q4 |
87 | Santa Clara Playground Improvements | B19029 | Parks & Recreation | Design Bid Build | $1,377,009 | $1,960,000 | FY21 | Q3 | FY21 | Q4 |
88 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation | Design Bid Build | $506,137 | $750,000 | FY21 | Q3 | FY21 | Q4 |
89 | Wangenheim Joint Use Facility | S15007 | Parks & Recreation | Design Bid Build | $6,386,396 | $9,517,667 | FY21 | Q2 | FY21 | Q4 |
90 | North City Pure Water Pipeline | B16035 | Public Utilities | Design Bid Build | $87,680,000 | $102,239,039 | FY21 | Q2 | FY21 | Q4 |
91 | Bay Ho Improv 1 (S) | B19088 | Public Utilities | Design Bid Build | $5,208,400 | $7,024,800 | FY21 | Q2 | FY21 | Q4 |
92 | Balboa Park Pipeline Repl Ph III (S) | B17134 | Public Utilities | Design Bid Build | $1,213,000 | $2,093,500 | FY20 | Q3 | FY21 | Q4 |
93 | Morena Improv 3 (W) | B21056 | Public Utilities | Design Build | $550,000 | $797,500 | FY21 | Q4 | FY21 | Q4 |
94 | Morena Improv 3 (S) | B21064 | Public Utilities | Design Build | $550,000 | $797,500 | FY21 | Q4 | FY21 | Q4 |
95 | Water & Sewer Group 965 (S) | B12048 | Public Utilities | Design Bid Build | $1,855,400 | $2,932,600 | FY21 | Q3 | FY21 | Q4 |
96 | Water & Sewer Group 965 (W) | B12057 | Public Utilities | Design Bid Build | $1,769,500 | $2,934,600 | FY21 | Q3 | FY21 | Q4 |
97 | Sewer Group 843 | B17189 | Public Utilities | Design Bid Build | $6,127,389 | $8,889,924 | FY21 | Q3 | FY21 | Q4 |
98 | NCPWF Influent Pump Station and Pipeline | B16140 | Public Utilities | Design Bid Build | $29,218,851 | $38,413,734 | FY21 | Q2 | FY21 | Q4 |
99 | NCWRP Improvements to 30 MGD | S17012 | Public Utilities | Design Bid Build | $26,449,499 | $32,998,711 | FY21 | Q2 | FY21 | Q4 |
100 | PWP North City Water Rec Plant Expansion | B21060 | Public Utilities | Design Bid Build | $148,291,500 | $192,778,950 | FY21 | Q2 | FY21 | Q4 |
101 | AC Water & Sewer Group 1051 (W) | B18091 | Public Utilities | Design Bid Build | $776,300 | $1,004,600 | FY21 | Q2 | FY21 | Q4 |
102 | AC Water & Sewer Group 1051 (S) | B18098 | Public Utilities | Design Bid Build | $3,136,600 | $4,059,100 | FY21 | Q2 | FY21 | Q4 |
103 | Sewer Rehab 1051A | B19145 | Public Utilities | Design Bid Build | $126,200 | $178,200 | FY21 | Q2 | FY21 | Q4 |
104 | Sewer & AC Water Group 763 (S) | B00374 | Public Utilities | Design Bid Build | $8,986,036 | $10,611,813 | FY21 | Q1 | FY21 | Q4 |
105 | Sewer and AC Water Group 763 (W) | B17116 | Public Utilities | Design Bid Build | $1,972,545 | $2,305,318 | FY21 | Q1 | FY21 | Q4 |
106 | Talmadge AC Water Main Replacement | B18197 | Public Utilities | Design Bid Build | $814,100 | $2,138,081 | FY21 | Q3 | FY21 | Q4 |
107 | AC Water & Sewer Group 1036 (S) | B18123 | Public Utilities | Design Bid Build | $525,900 | $652,800 | FY21 | Q3 | FY21 | Q4 |
108 | Balboa Park Pipeline Repl Ph II (S) | B17133 | Public Utilities | Design Bid Build | $1,852,000 | $1,730,069 | FY21 | Q3 | FY21 | Q4 |
109 | Balboa Park Pipeline Repl Phase II (W) | B17140 | Public Utilities | Design Bid Build | $3,790,000 | $8,582,380 | FY21 | Q3 | FY21 | Q4 |
110 | Alvarado TS Water Main Relocations | B18104 | Public Utilities | Design Bid Build | $10,000,000 | $10,438,400 | FY20 | Q3 | FY21 | Q4 |
111 | Alvarado Trunk Sewer Phase IV | S15019 | Public Utilities | Design Bid Build | $55,000,000 | $67,000,000 | FY20 | Q3 | FY21 | Q4 |
112 | MBC Equipment Upgrades | S17013 | Public Utilities | Design Bid Build | $35,400,000 | $45,503,972 | FY21 | Q3 | FY21 | Q4 |
113 | San Diego NC-MBC Improvements | B17006 | Public Utilities | Design Bid Build | $2,484,300 | $3,854,178 | FY21 | Q3 | FY21 | Q4 |
114 | Alvarado 2nd Extension Pipeline | S12013 | Public Utilities | Design Bid Build | $65,210,000 | $125,000,000 | FY21 | Q3 | FY21 | Q4 |
115 | Accelerated MH Referral Group 1 | B19097 | Public Utilities | Design Bid Build | $515,000 | $741,980 | FY21 | Q3 | FY21 | Q4 |
116 | AC Water and Sewer Group 1052A (W) | B19166 | Public Utilities | Multiple Award Construction Contract | $3,502,400 | $5,182,900 | FY21 | Q3 | FY21 | Q4 |
117 | AC Water & Sewer Group 1052A (S) | B19169 | Public Utilities | Multiple Award Construction Contract | $1,923,000 | $2,814,100 | FY21 | Q3 | FY21 | Q4 |
118 | North City Pure Water Subaqueous Pipeline | B16035.1 | Public Utilities | Design Bid Build | $5,270,000 | $7,000,000 | FY21 | Q2 | FY21 | Q4 |
119 | ADA S/W Group 3E W Point Loma | B16100 | Transportation & Storm Water | Design Bid Build | $538,000 | $1,339,502 | FY21 | Q1 | FY21 | Q4 |
120 | Block 1M1 UUP (La Jolla) | B15084 | Transportation & Storm Water | Job Order Contract | $252,450 | $397,000 | FY21 | Q3 | FY21 | Q4 |
121 | District 1 Block 1-J UUD | B00836 | Transportation & Storm Water | Job Order Contract | $695,618 | $1,044,618 | FY20 | Q3 | FY21 | Q4 |
122 | University Avenue Mobility | S00915 | Transportation & Storm Water | Design Bid Build | $5,974,533 | $9,557,310 | FY21 | Q2 | FY21 | Q4 |
123 | Citywide Street Lights Group 1801 | B18012 | Transportation & Storm Water | Design Bid Build | $120,000 | $207,238 | FY21 | Q3 | FY21 | Q4 |
124 | Asphalt Resurfacing Group 1901 | B18134 | Transportation & Storm Water | Design Bid Build | $9,746,100 | $10,486,046 | FY21 | Q3 | FY21 | Q4 |
125 | Governor Dr @ Lakewood St Traffic Signal | B17016 | Transportation & Storm Water | Design Bid Build | $275,700 | $460,000 | FY21 | Q3 | FY21 | Q4 |
126 | Adams Ave (1620) Storm Drain Replacement | B13102 | Transportation & Storm Water | Design Bid Build | $500,000 | $1,148,933 | FY21 | Q3 | FY21 | Q4 |
127 | Highland & Monroe Aves Storm Drain Repl | B12096 | Transportation & Storm Water | Design Bid Build | $1,586,000 | $2,662,516 | FY21 | Q3 | FY21 | Q4 |
128 | Block 3DD (Adams North) SL UU908 | B20050 | Transportation & Storm Water | To Be Determined | $294,813 | $859,413 | FY21 | Q4 | FY21 | Q4 |
129 | Thermal Ave-Donax Av to Palm Ave Sidwlk | B18157 | Transportation & Storm Water | Design Bid Build | $1,270,300 | $1,609,100 | FY21 | Q4 | FY21 | Q4 |
130 | Asphalt Resurfacing Group 1902 | B18135 | Transportation & Storm Water | Design Bid Build | $2,552,801 | $3,003,295 | FY21 | Q3 | FY21 | Q4 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Environmental Services | $6,300,000 | $8,400,000 |
Fire-Rescue | $17,010,775 | $43,036,999 |
Fleet Operations | $603,000 | $1,221,000 |
Library | $21,889,087 | $32,670,555 |
Parks & Recreation | $46,734,357 | $99,318,804 |
Public Utilities | $1,139,958,508 | $1,512,271,059 |
Real Estate Assets | $222,271 | $327,000 |
Transportation & Storm Water | $46,032,806 | $78,111,543 |
FY 2021 Total | $1,278,750,803 | $1,775,356,961 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015