Data Date: April 1, 2022
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | MBC Equipment Upgrades | S17013 | Public Utilities | Design Bid Build | $37,187,542 | $47,645,194 | FY21 | Q3 | FY22 | Q1 |
2 | Balboa Park Botanical Bldg Improvements | S20005 | Parks & Recreation | Design Build | $14,261,647 | $21,453,000 | FY21 | Q2 | FY22 | Q1 |
3 | PWP NCWRP Flow Equalization Basin | B21059 | Public Utilities | Design Bid Build | $11,886,000 | $18,350,052 | FY21 | Q4 | FY22 | Q2 |
4 | MBGC Irrigation & Electrical Upgrades | S11010 | Parks & Recreation | Design Bid Build | $9,199,700 | $10,661,700 | FY21 | Q4 | FY22 | Q2 |
5 | AC Water & Sewer Group 1056 (W) | B18181 | Public Utilities | Design Bid Build | $8,466,401 | $10,976,801 | FY21 | Q3 | FY22 | Q1 |
6 | RIVIERA DEL SOL NEIGHBORHOOD PARK | S00999 | Parks & Recreation | Design Bid Build | $5,524,537 | $9,570,838 | FY22 | Q1 | FY22 | Q2 |
7 | Clairemont Mesa E Improv 1 (W) | B18200 | Public Utilities | Design Bid Build | $5,222,770 | $7,083,977 | FY22 | Q1 | FY22 | Q3 |
8 | MBGC Clubhouse Demo/Prtbl Building Instl | S01090 | Parks & Recreation | Design Bid Build | $5,161,700 | $7,685,084 | FY21 | Q4 | FY22 | Q2 |
9 | San Diego NC-MBC Improvements | B17006 | Public Utilities | Design Bid Build | $2,899,148 | $10,038,088 | FY21 | Q3 | FY22 | Q1 |
10 | Clairemont Mesa E Improv 1 (S) | B18202 | Public Utilities | Design Bid Build | $2,777,959 | $3,971,060 | FY22 | Q1 | FY22 | Q3 |
11 | Tierrasanta Improv 1 (s) | B21003 | Public Utilities | Design Bid Build | $1,567,000 | $2,977,429 | FY22 | Q2 | FY22 | Q4 |
12 | Santa Clara Playground Improvements | B19029 | Parks & Recreation | Design Bid Build | $819,242 | $1,989,500 | FY21 | Q4 | FY22 | Q2 |
13 | Damon Ave Water Main Extension & AC Repl | B18215 | Public Utilities | Job Order Contract | $818,438 | $1,590,707 | FY22 | Q3 | FY22 | Q3 |
14 | El Cajon Bl-Highland-58th Improv | B17003 | Transportation | Design Bid Build | $573,647 | $1,316,448 | FY21 | Q4 | FY22 | Q2 |
15 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation | Design Bid Build | $561,646 | $1,289,500 | FY21 | Q4 | FY22 | Q2 |
16 | Kearny Mesa Pipeline Manway | B20072 | Public Utilities | Job Order Contract | $492,786 | $1,027,425 | FY22 | Q2 | FY22 | Q3 |
17 | AC Water & Sewer Group 1056 (S) | B18182 | Public Utilities | Design Bid Build | $368,705 | $428,605 | FY21 | Q3 | FY22 | Q1 |
18 | El Cajon Blvd (Highland Ave - Chamoune Ave) streetlights | B21065 | Transportation | Design Bid Build | $311,658 | $361,658 | FY21 | Q4 | FY22 | Q2 |
19 | Governor Dr @ Lakewood St Traffic Signal | B17016 | Transportation | Design Bid Build | $306,925 | $558,784 | FY21 | Q4 | FY22 | Q2 |
20 | Reo Drive New Streetlights | B19079 | Transportation | Job Order Contract | $272,223 | $413,023 | FY22 | Q2 | FY22 | Q3 |
21 | Marlesta/Beagle (Gen-B/M-Ashf) SL UU465 | B18127 | Transportation | Job Order Contract | $217,666 | $350,000 | FY22 | Q2 | FY22 | Q3 |
22 | Mt Acadia (Mt Alifan-Mt Burnham)SL UU621 | B17012 | Transportation | Job Order Contract | $205,200 | $298,000 | FY21 | Q4 | FY22 | Q1 |
23 | Talmadge Traffic Calming Infrastructure | S17001 | Parks & Recreation | Design Bid Build | $167,100 | $355,000 | FY21 | Q3 | FY22 | Q1 |
24 | Linda Vista Skate Park Phase 2 | B19062 | Parks & Recreation | Job Order Contract | $145,000 | $429,769 | FY21 | Q4 | FY22 | Q2 |
25 | Balboa Park Golf Course - Bathroom Remod | B20064 | Parks & Recreation | City Forces | $109,600 | $217,600 | FY22 | Q2 | FY22 | Q2 |
26 | Cchavez Pkwy (I5-Comml) UU27 | B21092 | Transportation | Design Bid Build | $103,000 | $148,000 | FY21 | Q4 | FY22 | Q3 |
27 | Redwood St (Pershing-Boundary) SL UU611 | B20095 | Transportation | Job Order Contract | $23,119 | $152,319 | FY21 | Q4 | FY22 | Q2 |
28 | Wangenheim Joint Use Facility | S15007 | Parks & Recreation | Design Bid Build | $6,834,000 | $9,517,667 | FY21 | Q2 | FY22 | Q2 |
29 | AC Water & Sewer Group 1036 (W) | B18121 | Public Utilities | Design Bid Build | $4,617,986 | $6,198,913 | FY21 | Q3 | FY22 | Q3 |
30 | 4182 60th St & 5973 Alta Mesa Wy Emer | B22052 | Stormwater | Emergency (As-needed) | $2,700,000 | $3,500,000 | FY22 | Q1 | FY22 | Q3 |
31 | 5604 Campanile Way SD Repair Emergency | B21126 | Stormwater | Emergency (As-needed) | $1,500,000 | $1,765,770 | FY21 | Q4 | FY22 | Q2 |
32 | 3405 Kite Street SD Emergency | B21153 | Stormwater | Emergency (As-needed) | $1,500,000 | $2,000,000 | FY22 | Q1 | FY22 | Q3 |
33 | AC Water & Sewer Group 1036 (S) | B18123 | Public Utilities | Design Bid Build | $1,411,352 | $2,192,632 | FY21 | Q3 | FY22 | Q3 |
34 | Talmadge AC Water Main Replacement | B18197 | Public Utilities | Design Bid Build | $1,317,345 | $2,001,660 | FY21 | Q3 | FY22 | Q1 |
35 | 4617 Antioch Pl CMP SD Emergency | B21127 | Stormwater | Emergency (As-needed) | $1,200,000 | $1,750,000 | FY21 | Q3 | FY22 | Q2 |
36 | Cajon Way CMP Storm Drain Emergency | B21115 | Stormwater | Emergency (As-needed) | $1,100,000 | $1,950,000 | FY21 | Q3 | FY22 | Q1 |
37 | Accelerated MH Referral Group 1 | B19097 | Public Utilities | Design Bid Build | $1,026,647 | $2,047,033 | FY21 | Q4 | FY22 | Q2 |
38 | Mississippi St CMP SD Emergency | B21137 | Stormwater | Emergency (As-needed) | $526,000 | $506,316 | FY21 | Q4 | FY22 | Q2 |
39 | 3505 Udall St (CMP) SD Emergency | B21138 | Stormwater | Emergency (As-needed) | $500,000 | $1,250,000 | FY21 | Q4 | FY22 | Q2 |
40 | Ocean Beach Pier Improvements | S20011 | Parks & Recreation | Design Build | $450,000 | $1,132,907 | FY22 | Q2 | FY22 | Q2 |
41 | Crest Canyon Park Emergency SD Replace | B20019 | Stormwater | Emergency (As-needed) | $439,000 | $9,615,495 | FY20 | Q3 | FY22 | Q2 |
42 | 3984 Pacific Hwy Pump StationL Emergency | B22013 | Stormwater | Emergency (As-needed) | $425,000 | $650,000 | FY21 | Q4 | FY22 | Q2 |
43 | Palm Avenue Storm Drain Replacement | B17163 | Stormwater | Job Order Contract | $185,476 | $564,208 | FY22 | Q2 | FY22 | Q2 |
44 | Morena Conveyance Southern | B15141.4 | Public Utilities | Design Bid Build | $60,077,353 | $73,727,680 | FY22 | Q2 | FY22 | Q4 |
45 | Morena Conveyance Middle | B15141.3 | Public Utilities | Design Bid Build | $56,719,052 | $71,351,280 | FY22 | Q2 | FY22 | Q4 |
46 | Kearny Mesa Facility Improvements | S20009 | Citywide | Design Bid Build | $14,864,176 | $16,421,600 | FY22 | Q3 | FY22 | Q4 |
47 | AC Water & Sewer Group 1052 (W) | B18092 | Public Utilities | Design Bid Build | $7,106,852 | $10,022,594 | FY22 | Q2 | FY22 | Q4 |
48 | Sewer & AC Water Group 794 (S) | B00395 | Public Utilities | Design Bid Build | $6,263,573 | $7,001,267 | FY22 | Q3 | FY22 | Q4 |
49 | AC Water & Sewer Group 1050 (W) | B18090 | Public Utilities | Design Bid Build | $5,121,200 | $7,511,200 | FY22 | Q3 | FY22 | Q4 |
50 | AC Water & Sewer Group 1052 (S) | B18096 | Public Utilities | Design Bid Build | $2,796,599 | $4,062,797 | FY22 | Q2 | FY22 | Q4 |
51 | AC Water & Sewer Group 1050 (S) | B18094 | Public Utilities | Design Bid Build | $2,346,300 | $3,441,200 | FY22 | Q3 | FY22 | Q4 |
52 | MISSION CTR CNYN A SMR | B00431 | Public Utilities | Design Bid Build | $2,075,492 | $3,197,185 | FY22 | Q3 | FY22 | Q4 |
53 | Otay WTP-Basin #1 Concrete Restoration | B17092 | Public Utilities | Design Bid Build | $1,979,470 | $4,747,270 | FY20 | Q4 | FY22 | Q4 |
54 | Curb Ramp Improvement Group 1701 | B17114 | Transportation | Design Bid Build | $1,500,000 | $3,426,585 | FY22 | Q2 | FY22 | Q4 |
55 | Sewer & AC Water Group 794 (W) | B16041 | Public Utilities | Design Bid Build | $1,147,000 | $1,428,000 | FY22 | Q3 | FY22 | Q4 |
56 | Torrey Pines Gf-Repr Storm Drain Outfall | B17152 | Stormwater | Job Order Contract | $1,082,035 | $3,360,000 | FY22 | Q3 | FY22 | Q4 |
57 | Miramar Valves Replacement | B20015 | Public Utilities | Job Order Contract | $721,267 | $1,398,500 | FY22 | Q3 | FY22 | Q4 |
58 | Adams Avenue (1620) Storm Drain Replacement | B13102 | Stormwater | Design Bid Build | $547,890 | $1,695,934 | FY22 | Q3 | FY22 | Q4 |
59 | Howard Avenue- Village Pine to iris Avenue Sidewalk | B18019 | Transportation | Design Bid Build | $435,000 | $1,130,060 | FY22 | Q3 | FY22 | Q4 |
60 | Miramar Landfill Fee Booth Truck Scale #3 Replacement & Miramar Landfill Outbound Scale #5 Replacement | B22086 | Environmental Services | Sole Source | $380,000 | $440,000 | FY22 | Q4 | FY22 | Q4 |
61 | Morena Improv 3 (W) | B21056 | Public Utilities | Job Order Contract | $1,109,622 | $1,637,238 | FY21 | Q4 | FY22 | Q4 |
62 | Balboa Park Federal Bldg Improvements | B20066 | Parks & Recreation | Design Bid Build | $1,079,850 | $2,293,000 | FY22 | Q1 | FY22 | Q4 |
63 | Ocean Beach Improv 1A (W) | B21152 | Public Utilities | Job Order Contract | $1,019,252 | $1,688,819 | FY22 | Q3 | FY22 | Q4 |
64 | Oak Park Improvements 1 (W) | B21024 | Public Utilities | Job Order Contract | $892,772 | $1,434,555 | FY22 | Q2 | FY22 | Q4 |
65 | Storm Drain CMP Lining III | B20087 | Stormwater | Job Order Contract | $482,663 | $604,263 | FY22 | Q3 | FY22 | Q4 |
66 | Chollas Lake Electrical Upgrade | L18001.1 | Parks & Recreation Department | Design Bid Build | $424,000 | $850,000 | FY22 | Q4 | FY22 | Q4 |
67 | Regional Arterial Guardrail Group 2a | B18201 | Transportation | Job Order Contract | $240,032 | $457,850 | FY22 | Q4 | FY22 | Q4 |
68 | Soledad Pressure Reducing Stn Hatch (w) | B21040 | Public Utilities | Job Order Contract | $227,865 | $472,931 | FY22 | Q3 | FY22 | Q3 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Parks & Recreation Department | $424,000 | $850,000 |
Parks & Recreation | $44,314,022 | $66,595,565 |
Public Utilities | $229,663,750 | $309,652,094 |
Citywide | $14,864,176 | $16,421,600 |
Environmental Services | $380,000 | $440,000 |
Stormwater | $12,188,064 | $29,211,987 |
Transportation | $4,188,469 | $8,612,727 |
FY 2022 Total | $306,022,481 | $431,783,973 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015