Data Date: July 1, 2021
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | Morena Conveyance Southern | B15141.4 | Public Utilities | Design Bid Build | $59,235,777 | $73,727,680 | FY22 | Q1 | FY22 | Q3 |
2 | Morena Conveyance Middle | B15141.3 | Public Utilities | Design Bid Build | $56,719,052 | $71,351,280 | FY22 | Q1 | FY22 | Q3 |
3 | PWP Central Area Small-Scale Facility | B21151 | Public Utilities | Design Bid Build | $44,200,000 | $55,692,000 | FY22 | Q4 | FY22 | Q4 |
4 | MBC Equipment Upgrades | S17013 | Public Utilities | Design Bid Build | $37,187,541 | $50,487,060 | FY21 | Q3 | FY22 | Q1 |
5 | Morena Pipeline | S16027 | Public Utilities | Design Bid Build | $33,443,875 | $39,609,023 | FY22 | Q1 | FY22 | Q3 |
6 | La Media Road Improvements | S15018 | Transportation & Storm Water | Developer Build | $30,400,000 | $42,699,999 | FY22 | Q3 | FY22 | Q4 |
7 | Lakeside Valve Station Replacement | B17082 | Public Utilities | Design Bid Build | $23,001,485 | $36,208,000 | FY22 | Q3 | FY22 | Q4 |
8 | Harbor Drive Trunk Sewer | S18006 | Public Utilities | Design Bid Build | $19,400,000 | $26,500,000 | FY21 | Q3 | FY22 | Q1 |
9 | Fairmount Avenue Fire Station | S14018 | Fire-Rescue | Design Bid Build | $18,214,765 | $22,327,794 | FY22 | Q1 | FY22 | Q2 |
10 | South Mission Beach SD Replacement | B18117 | Transportation & Storm Water | Design Bid Build | $16,081,030 | $17,143,393 | FY22 | Q2 | FY22 | Q4 |
11 | Balboa Park Botanical Bldg Improvements | S20005 | Parks & Recreation | Design Build | $14,261,647 | $21,500,000 | FY21 | Q4 | FY22 | Q1 |
12 | Kearny Mesa Facility Improvements | S20009 | Citywide | Design Bid Build | $13,214,699 | $14,772,123 | FY22 | Q2 | FY22 | Q3 |
13 | Mira Mesa Pool & Skate Plaza Ph2 | L16002.1 | Parks & Recreation | Design Bid Build | $13,010,044 | $21,790,707 | FY22 | Q1 | FY22 | Q3 |
14 | Tecolote Canyon Trunk Sewer Improvement | S15020 | Public Utilities | Design Bid Build | $12,847,000 | $17,130,000 | FY22 | Q1 | FY22 | Q3 |
15 | Fire Station 48 | S15015 | Fire-Rescue | Design Build | $12,402,500 | $15,091,000 | FY21 | Q3 | FY22 | Q1 |
16 | Maple Canyon Restoration - Phases 1 & 2 | B12040 | Transportation & Storm Water | Design Bid Build | $11,191,018 | $14,704,858 | FY22 | Q1 | FY22 | Q2 |
17 | PWP NCWRP Flow Equalization Basin | B21059 | Public Utilities | Design Bid Build | $10,590,000 | $13,767,000 | FY21 | Q4 | FY22 | Q2 |
18 | Miramar Reservoir Pump Station Improveme | B17190 | Public Utilities | Design Bid Build | $9,018,450 | $11,873,598 | FY22 | Q2 | FY22 | Q4 |
19 | Asphalt Overlay Group 2111 | B21090 | Transportation & Storm Water | Design Bid Build | $9,016,800 | $10,876,300 | FY22 | Q3 | FY22 | Q4 |
20 | AC Water & Sewer Group 1056 (W) | B18181 | Public Utilities | Design Bid Build | $8,535,300 | $11,045,700 | FY21 | Q3 | FY22 | Q1 |
21 | Hickman Fields Athletic Area | S00751 | Parks & Recreation | Design Bid Build | $8,200,001 | $10,566,319 | FY21 | Q3 | FY22 | Q1 |
22 | Street Reconstruction Group 1801 | B17188 | Transportation & Storm Water | Design Bid Build | $8,200,000 | $12,710,000 | FY22 | Q2 | FY22 | Q4 |
23 | Asphalt Overlay Group 2110 | B21089 | Transportation & Storm Water | Design Bid Build | $7,300,000 | $9,000,000 | FY22 | Q2 | FY22 | Q4 |
24 | South Mission Beach GI | B18118 | Transportation & Storm Water | Design Bid Build | $7,020,626 | $7,737,821 | FY22 | Q2 | FY22 | Q4 |
25 | Sewer & AC Water Group 1034 (W) | B18064 | Public Utilities | Design Bid Build | $6,959,100 | $9,201,600 | FY21 | Q3 | FY22 | Q1 |
26 | Sewer & AC Water Group 765A (S) | B18073 | Public Utilities | Design Bid Build | $6,907,708 | $9,121,708 | FY22 | Q1 | FY22 | Q3 |
27 | RIVIERA DEL SOL NEIGHBORHOOD PARK | S00999 | Parks & Recreation | Design Bid Build | $6,055,474 | $9,570,838 | FY22 | Q1 | FY22 | Q3 |
28 | Sewer & AC Water Group 794 (S) | B00395 | Public Utilities | Design Bid Build | $6,054,930 | $7,616,454 | FY22 | Q1 | FY22 | Q2 |
29 | University Ave Complete Street Phase 1 | S18001 | Transportation & Storm Water | Design Bid Build | $5,700,000 | $9,427,153 | FY21 | Q3 | FY22 | Q2 |
30 | Block 8R UUP | 21003599 | Transportation & Storm Water | Design Bid Build | $5,682,685 | $7,387,491 | FY22 | Q3 | FY22 | Q4 |
31 | Sewer & AC Water Group 765A (W) | B18071 | Public Utilities | Design Bid Build | $5,580,142 | $7,395,142 | FY22 | Q1 | FY22 | Q3 |
32 | Sewer and AC Water Group 793 (S) | B00394 | Public Utilities | Design Bid Build | $5,305,291 | $6,624,611 | FY21 | Q3 | FY22 | Q1 |
33 | Water Group Job 952 | B11048 | Public Utilities | Design Bid Build | $5,300,000 | $7,393,194 | FY21 | Q4 | FY22 | Q2 |
34 | AC Water & Sewer Group 1048 (S) | B18095 | Public Utilities | Design Bid Build | $5,142,900 | $6,655,500 | FY21 | Q4 | FY22 | Q2 |
35 | AC Water & Sewer Group 1050 (W) | B18090 | Public Utilities | Design Bid Build | $5,121,200 | $7,511,200 | FY21 | Q3 | FY22 | Q1 |
36 | AC Water & Sewer Group 1040 (W) | B18068 | Public Utilities | Design Bid Build | $5,050,700 | $7,539,300 | FY22 | Q2 | FY22 | Q4 |
37 | Sewer & AC Water Group 1034 (S) | B18063 | Public Utilities | Design Bid Build | $4,968,400 | $6,806,400 | FY21 | Q3 | FY22 | Q1 |
38 | MBGC Clubhouse Demo/Prtbl Building Instl | S01090 | Parks & Recreation | Design Bid Build | $4,770,578 | $7,400,000 | FY21 | Q3 | FY22 | Q1 |
39 | AC Water & Sewer Group 1052 (W) | B18092 | Public Utilities | Design Bid Build | $4,695,000 | $6,573,000 | FY21 | Q4 | FY22 | Q2 |
40 | Scripps miramar Ranch library | S00811 | Library | Design Bid Build | $4,208,097 | $6,253,376 | FY22 | Q1 | FY22 | Q3 |
41 | Clairemont Mesa E Improv 1 (S) | B18202 | Public Utilities | Design Bid Build | $4,017,500 | $5,327,700 | FY21 | Q4 | FY22 | Q2 |
42 | University City Improv 1 (W) | B19086 | Public Utilities | Design Bid Build | $3,982,800 | $5,256,400 | FY22 | Q2 | FY22 | Q4 |
43 | University City Improv 1 (S) | B19087 | Public Utilities | Design Bid Build | $3,793,000 | $5,007,100 | FY22 | Q2 | FY22 | Q4 |
44 | Pressure Reducing Stations Upgrades Phs1 | B16017 | Public Utilities | Design Bid Build | $3,740,000 | $6,290,000 | FY22 | Q2 | FY22 | Q3 |
45 | AC Water & Sewer Group 1052 (S) | B18096 | Public Utilities | Design Bid Build | $3,547,000 | $4,965,800 | FY21 | Q4 | FY22 | Q2 |
46 | Bannock Ave Streetscape Enhancements | B10027 | Transportation & Storm Water | Design Bid Build | $3,528,225 | $4,901,787 | FY22 | Q1 | FY22 | Q2 |
47 | Downtown Complete St Impl Phase 3A1 | B19144 | Transportation & Storm Water | Design Bid Build | $3,500,000 | $4,800,000 | FY22 | Q2 | FY22 | Q4 |
48 | Carmel Valley CP - Turf Upgrades | S16029 | Parks & Recreation | Design Bid Build | $3,468,542 | $4,774,121 | FY22 | Q3 | FY22 | Q4 |
49 | Chollas Large Car Washes | L14002.3 | Fleet Services | Design Bid Build | $3,325,000 | $4,423,370 | FY22 | Q1 | FY22 | Q2 |
50 | Egger/South Bay Comm Pk ADA Improvements | S15031 | Parks & Recreation | Design Bid Build | $3,119,000 | $4,534,000 | FY22 | Q2 | FY22 | Q4 |
51 | Miramar Place CNG Facility Upgrades | AFA00001 | Environmental Services | Sole Source | $3,100,000 | $3,700,000 | FY22 | Q3 | FY22 | Q3 |
52 | Southcrest Green Infrastructure (GI) | B16112 | Transportation & Storm Water | Design Bid Build | $3,055,400 | $4,600,000 | FY22 | Q1 | FY22 | Q2 |
53 | Sidewalk Replacement Group 1902-Clmnt Mesa & LaJolla | B19013 | Transportation & Storm Water | Design Bid Build | $3,000,000 | $3,700,000 | FY22 | Q2 | FY22 | Q3 |
54 | San Diego NC-MBC Improvements | B17006 | Public Utilities | Design Bid Build | $2,899,148 | $10,038,088 | FY21 | Q3 | FY22 | Q1 |
55 | Bay Ho Improv 3 (W) | B19134 | Public Utilities | Design Bid Build | $2,820,200 | $3,869,500 | FY22 | Q4 | FY22 | Q4 |
56 | MBGC Irrigation & Electrical Upgrades | S11010 | Parks & Recreation | Design Bid Build | $2,807,051 | $4,460,000 | FY21 | Q3 | FY22 | Q1 |
57 | Accelerated Sewer Referral Group 851 | B19063 | Public Utilities | Design Bid Build | $2,742,900 | $4,023,000 | FY22 | Q1 | FY22 | Q2 |
58 | Miramar Reservoir PS New Generator & Upg | B19099 | Public Utilities | Design Bid Build | $2,660,874 | $4,266,874 | FY22 | Q2 | FY22 | Q4 |
59 | College Areas Swr & AC Wtr Main Repl (S) | B16025 | Public Utilities | Design Bid Build | $2,645,302 | $3,707,427 | FY21 | Q4 | FY22 | Q2 |
60 | STORM WATER DIVERSION AT THE SBWRP | B20002 | Public Utilities | Design Bid Build | $2,537,900 | $3,908,100 | FY22 | Q1 | FY22 | Q3 |
61 | Tierrasanta Improv 1 (s) | B21003 | Public Utilities | Design Bid Build | $2,505,000 | $3,590,000 | FY22 | Q2 | FY22 | Q4 |
62 | AC Water & Sewer Group 1050 (S) | B18094 | Public Utilities | Design Bid Build | $2,346,300 | $3,441,200 | FY21 | Q3 | FY22 | Q1 |
63 | Scripps Ranch Improv 1 (W) | B18208 | Public Utilities | Design Bid Build | $2,313,800 | $3,517,000 | FY22 | Q2 | FY22 | Q4 |
64 | Olive Grove Community Park ADA Improveme | S15028 | Parks & Recreation | Design Bid Build | $2,298,814 | $3,721,866 | FY21 | Q3 | FY22 | Q1 |
65 | STORM DRAIN DIVERSION AT THE MBC | B19197 | Public Utilities | Design Bid Build | $2,260,800 | $3,481,800 | FY22 | Q1 | FY22 | Q3 |
66 | PD Substation Small Carwashes | L14002.6 | Fleet Services | Design Bid Build | $2,200,000 | $3,488,516 | FY22 | Q1 | FY22 | Q3 |
67 | Penasquitos Pump Stn Oxygenation System | B21001 | Public Utilities | Design Bid Build | $2,200,000 | $2,900,000 | FY22 | Q2 | FY22 | Q4 |
68 | Clairemont Mesa E Improv 1 (W) | B18200 | Public Utilities | Design Bid Build | $2,194,500 | $2,927,200 | FY21 | Q4 | FY22 | Q2 |
69 | MISSION CTR CNYN A SMR | B00431 | Public Utilities | Design Bid Build | $2,164,500 | $3,188,600 | FY22 | Q2 | FY22 | Q4 |
70 | EMTS Boat Dock Esplanade | S00319 | Public Utilities | Design Bid Build | $2,160,380 | $3,430,851 | FY21 | Q3 | FY22 | Q1 |
71 | Crown Point Drive Roundabouts | B18009 | Transportation & Storm Water | Design Bid Build | $2,130,000 | $3,663,300 | FY22 | Q2 | FY22 | Q4 |
72 | Citywide Street Lights 1950 | B19125 | Transportation & Storm Water | Job Order Contract | $2,050,000 | $2,558,347 | FY22 | Q1 | FY22 | Q1 |
73 | Scripps Ranch Improv 1 (S) | B18204 | Public Utilities | Design Bid Build | $2,035,300 | $3,052,500 | FY22 | Q2 | FY22 | Q4 |
74 | AC Water and Sewer Group 1023B (W) | B19205 | Public Utilities | Design Bid Build | $2,000,000 | $2,941,000 | FY21 | Q3 | FY22 | Q2 |
75 | Foothill Blvd & Loring St Roundabout | B18008 | Transportation & Storm Water | Design Bid Build | $1,984,050 | $3,009,700 | FY22 | Q1 | FY22 | Q3 |
76 | John F. Kennedy Neighborhood Park Improvements | B18005 | Parks & Recreation | Design Bid Build | $1,859,668 | $3,079,619 | FY22 | Q1 | FY22 | Q3 |
77 | North Park Mini Park Ped Improvements | B17102 | Transportation & Storm Water | Design Bid Build | $1,699,900 | $2,844,167 | FY22 | Q1 | FY22 | Q3 |
78 | Otay WTP-Basin #1 Concrete Restoration | B17092 | Public Utilities | Design Bid Build | $1,684,000 | $3,500,000 | FY22 | Q1 | FY22 | Q3 |
79 | Solana Highlands NP-Comfort Station | S16032 | Parks & Recreation | Design Bid Build | $1,667,000 | $2,191,000 | FY22 | Q1 | FY22 | Q3 |
80 | Block 1M (La Jolla 4) Rd Imp UU659_RP | B18155 | Transportation & Storm Water | Design Bid Build | $1,608,583 | $2,010,729 | FY22 | Q2 | FY22 | Q4 |
81 | AC Water & Sewer Group 1040 (S) | B18066 | Public Utilities | Design Bid Build | $1,568,500 | $2,278,800 | FY22 | Q2 | FY22 | Q4 |
82 | 5th and Brookes SD Upgrade | B19073 | Transportation & Storm Water | Design Bid Build | $1,559,400 | $2,184,300 | FY22 | Q3 | FY22 | Q4 |
83 | Torrey Pines Gf-Repr Storm Drain Outfall | B17152 | Parks & Recreation | Design Bid Build | $1,540,000 | $3,360,000 | FY21 | Q4 | FY22 | Q3 |
84 | Curb Ramp Improvement Group 1701 | B17114 | Transportation & Storm Water | Design Bid Build | $1,500,000 | $3,425,000 | FY22 | Q2 | FY22 | Q4 |
85 | Block 6DD1 (Clairemont Mesa)Rd Imp UU410 | B18142 | Transportation & Storm Water | Design Bid Build | $1,475,215 | $1,959,764 | FY22 | Q2 | FY22 | Q4 |
86 | AC Water & Sewer Group 1048 (W) | B18088 | Public Utilities | Design Bid Build | $1,395,900 | $1,806,500 | FY21 | Q4 | FY22 | Q2 |
87 | Santa Clara Playground Improvements | B19029 | Parks & Recreation | Design Bid Build | $1,377,009 | $1,960,000 | FY21 | Q4 | FY22 | Q1 |
88 | Miramar Place Repair Shop Upgrades | AFA00001 | Environmental Services | Design Bid Build | $1,286,000 | $1,500,000 | FY22 | Q3 | FY22 | Q4 |
89 | Carmel Grove NP-Comfort Station | S16038 | Parks & Recreation | Design Bid Build | $1,282,500 | $1,761,500 | FY22 | Q1 | FY22 | Q3 |
90 | Crown Point Playground Improvements | B19021 | Parks & Recreation | Design Bid Build | $1,264,516 | $1,960,000 | FY22 | Q3 | FY22 | Q4 |
91 | Sidewalk Replacement Group 1903-SE & CH | B19014 | Transportation & Storm Water | Design Bid Build | $1,200,000 | $1,499,997 | FY22 | Q1 | FY22 | Q2 |
92 | NCWRP - Chiller Replacement | B20148 | Public Utilities | Design Bid Build | $1,186,900 | $1,613,600 | FY22 | Q1 | FY22 | Q3 |
93 | Sewer & AC Water Group 794 (W) | B16041 | Public Utilities | Design Bid Build | $1,179,000 | $1,428,000 | FY22 | Q1 | FY22 | Q2 |
94 | Block 8R UUP - CIP | B15097 | Transportation & Storm Water | Design Bid Build | $1,114,000 | $1,439,000 | FY22 | Q3 | FY22 | Q4 |
95 | Green Infrastructure Group 1027 | B15103 | Transportation & Storm Water | Design Bid Build | $1,105,000 | $2,000,000 | FY22 | Q1 | FY22 | Q3 |
96 | Pacific Beach TS Interconnect Upgrade | B15065 | Transportation & Storm Water | Design Bid Build | $1,100,000 | $1,841,619 | FY22 | Q2 | FY22 | Q4 |
97 | Hard Court Improvements | AGF00007 | Parks & Recreation | To Be Determined | $1,070,000 | $1,070,000 | FY22 | Q2 | FY22 | Q3 |
98 | Ocean Air CP Comfort Station & Park Impr | S16031 | Parks & Recreation | Design Bid Build | $1,023,021 | $2,181,793 | FY22 | Q3 | FY22 | Q4 |
99 | Crown Point Parking Lot Improvements | B19022 | Parks & Recreation | Design Bid Build | $1,004,516 | $1,557,000 | FY22 | Q3 | FY22 | Q4 |
100 | North Cove Comfort Station Imp | B18234 | Parks & Recreation | Design Bid Build | $977,918 | $1,524,898 | FY22 | Q1 | FY22 | Q3 |
101 | Southeastern Mini Park Improvements- Clay Avenue Mini Park | L16000.5 | Parks & Recreation | Design Bid Build | $943,910 | $1,825,196 | FY20 | Q1 | FY22 | Q3 |
102 | AC Water Group 1027A | B21055 | Public Utilities | Design Bid Build | $900,000 | $1,200,000 | FY22 | Q1 | FY22 | Q3 |
103 | Miramar Trailer for new office space needs LF Ops | L17000.6 | Environmental Services | Design Build | $900,000 | $1,000,000 | FY22 | Q3 | FY22 | Q4 |
104 | College Areas Swr & AC Wtr Main Repl (W) | B16022 | Public Utilities | Design Bid Build | $896,284 | $1,414,184 | FY21 | Q4 | FY22 | Q2 |
105 | ADA Mid-City MS TSW-1 | B18054 | Transportation & Storm Water | Design Bid Build | $873,000 | $1,362,800 | FY22 | Q2 | FY22 | Q4 |
106 | MYF Electrical System Upgrade | B18034 | Airports | Design Bid Build | $864,846 | $1,270,062 | FY22 | Q1 | FY22 | Q3 |
107 | Carmel Knoll NP-Comfort Station | S16033 | Parks & Recreation | Design Bid Build | $852,000 | $1,178,700 | FY22 | Q1 | FY22 | Q3 |
108 | Carmel Mission NP Comfort Station Develo | S16039 | Parks & Recreation | Design Bid Build | $851,500 | $1,178,000 | FY22 | Q1 | FY22 | Q3 |
109 | Sage Canyon NP Concession Bldg-Develop | S16035 | Parks & Recreation | Design Bid Build | $767,500 | $1,310,500 | FY21 | Q4 | FY22 | Q3 |
110 | Mission Bl(Loring-Turquoise) Rd Imp UU30 | B18140 | Transportation & Storm Water | Design Bid Build | $750,989 | $976,286 | FY22 | Q2 | FY22 | Q4 |
111 | Plumosa Park Series Circuit Conversion | B17101 | Transportation & Storm Water | Design Bid Build | $721,000 | $1,450,000 | FY22 | Q1 | FY22 | Q3 |
112 | Sewer and AC Water Group 793 (W) | B15070 | Public Utilities | Design Bid Build | $677,900 | $964,700 | FY22 | Q2 | FY22 | Q4 |
113 | Damon Ave Water Main Extension & AC Repl | B18215 | Public Utilities | Design Bid Build | $662,000 | $1,340,200 | FY22 | Q1 | FY22 | Q2 |
114 | San Vicente PH I-II Rd Imp UU505-UU506 | B17098 | Transportation & Storm Water | Design Bid Build | $644,468 | $837,809 | FY22 | Q2 | FY22 | Q4 |
115 | El Cajon Bl-Highland-58th Improv | B17003 | Transportation & Storm Water | Design Bid Build | $627,199 | $1,370,184 | FY21 | Q4 | FY22 | Q2 |
116 | Adams Avenue (1620) Storm Drain Replacement | B13102 | Transportation & Storm Water | Design Bid Build | $616,000 | $1,298,933 | FY22 | Q1 | FY22 | Q2 |
117 | DeAnza North Parking Lot Improvements | B18220 | Parks & Recreation | Design Bid Build | $579,000 | $905,167 | FY22 | Q2 | FY22 | Q3 |
118 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation | Design Bid Build | $506,137 | $1,409,500 | FY21 | Q4 | FY22 | Q1 |
119 | Sunset Point Parking Lot Improvements | B19159 | Parks & Recreation | Design Bid Build | $502,582 | $732,582 | FY22 | Q2 | FY22 | Q3 |
120 | Mid-City & Eastern Area Signal Mods | B17128 | Transportation & Storm Water | Design Bid Build | $477,000 | $620,000 | FY22 | Q2 | FY22 | Q3 |
121 | Hilltop PH I(Boundary-Toyne)Rd Imp UU617 | B18153 | Transportation & Storm Water | Design Bid Build | $475,151 | $617,696 | FY22 | Q2 | FY22 | Q4 |
122 | Citywide Street Lights Group 1702 | B17051 | Transportation & Storm Water | Design Bid Build | $458,844 | $749,144 | FY21 | Q4 | FY22 | Q2 |
123 | Mountain View Improv 1 (S) | B20149 | Public Utilities | Job Order Contract | $453,800 | $713,800 | FY22 | Q2 | FY22 | Q3 |
124 | El Cajon & Kansas - Traffic Signal | B19060 | Transportation & Storm Water | Design Bid Build | $453,200 | $800,000 | FY22 | Q2 | FY22 | Q4 |
125 | Wightman (Chamoune -Euclid) Rd Imp UU388 | B18138 | Transportation & Storm Water | Design Bid Build | $420,849 | $547,104 | FY22 | Q2 | FY22 | Q4 |
126 | Citywide Street Lights Group 1701 | B17050 | Transportation & Storm Water | Design Bid Build | $419,500 | $705,600 | FY21 | Q4 | FY22 | Q2 |
127 | Howard Avenue- Village Pine to iris Avenue Sidewalk | B18019 | Transportation & Storm Water | Design Bid Build | $400,000 | $1,053,400 | FY22 | Q1 | FY22 | Q3 |
128 | Main at Vesta (Barrio Logan) | B13010 | Transportation & Storm Water | Design Bid Build | $359,600 | $499,000 | FY22 | Q1 | FY22 | Q3 |
129 | Division St & Osborn St Traffic Signal | B15047 | Transportation & Storm Water | Design Bid Build | $350,000 | $475,000 | FY22 | Q2 | FY22 | Q4 |
130 | Fire Station 12 Elevator Modernization | New | Real Estate Assets - Facilities | Design Build | $350,000 | $350,000 | FY22 | Q4 | ||
131 | Golfcrest(Jackson-Wandermere)Rd ImpUU584 | B18149 | Transportation & Storm Water | Design Bid Build | $335,328 | $435,926 | FY22 | Q2 | FY22 | Q4 |
132 | Kettner & Palm Pedestrian Hybrid Beacon | B18046 | Transportation & Storm Water | Design Bid Build | $330,100 | $481,400 | FY22 | Q2 | FY22 | Q4 |
133 | Kearny Mesa Pipeline Manway | B20072 | Public Utilities | Design Bid Build | $330,000 | $542,000 | FY21 | Q4 | FY22 | Q2 |
134 | Howard PHI-II(Park-Texas) Rd Imp UU71-72 | B18136 | Transportation & Storm Water | Design Bid Build | $311,452 | $404,888 | FY22 | Q2 | FY22 | Q4 |
135 | Governor Dr @ Lakewood St Traffic Signal | B17016 | Transportation & Storm Water | Design Bid Build | $306,925 | $590,000 | FY21 | Q4 | FY22 | Q2 |
136 | Scripps Ranch Library Fire Suppression System | New | Real Estate Assets - Facilities | Design Build | $300,000 | $330,000 | FY22 | Q4 | ||
137 | Miramar Valves Replacement | B20015 | Public Utilities | Design Bid Build | $275,000 | $529,500 | FY22 | Q1 | FY22 | Q2 |
138 | 73rd St-El Cajon Bl to Saranac-Sidewalk | B18017 | Transportation & Storm Water | Design Bid Build | $275,000 | $651,750 | FY22 | Q2 | FY22 | Q4 |
139 | El Cuervo Adobe Improvements | S14006 | Parks & Recreation | Design Bid Build | $273,480 | $606,000 | FY22 | Q1 | FY22 | Q4 |
140 | Reo Drive New Streetlights | B19079 | Transportation & Storm Water | Design Bid Build | $261,700 | $402,500 | FY22 | Q1 | FY22 | Q3 |
141 | El Cajon Blvd (Highland Ave - Chamoune Ave) streetlights | B21065 | Transportation & Storm Water | Design Bid Build | $250,000 | $300,000 | FY21 | Q4 | FY22 | Q1 |
142 | Tecolote Cyn GC Water Conn | B15203 | Public Utilities | Design Bid Build | $229,000 | $278,000 | FY22 | Q1 | FY22 | Q3 |
143 | Fanuel St III (Grand-PB Dr) Rd Imp UU188 | B17071 | Transportation & Storm Water | Design Bid Build | $217,325 | $282,523 | FY22 | Q2 | FY22 | Q4 |
144 | Morena Bl & W. Bernardo Medians | B15015 | Transportation & Storm Water | Multiple | $213,500 | $433,261 | FY22 | Q1 | FY22 | Q3 |
145 | Marlesta/Beagle (Gen-B/M-Ashf) SL UU465 | B18127 | Transportation & Storm Water | Job Order Contract | $210,000 | $350,000 | FY22 | Q1 | FY22 | Q2 |
146 | ADA Torrey Pines APS PROW-S25 | B18061 | Transportation & Storm Water | Design Bid Build | $209,400 | $352,400 | FY22 | Q2 | FY22 | Q4 |
147 | AC Water and Sewer Group 1023B (S) | B19204 | Public Utilities | Design Bid Build | $200,000 | $326,000 | FY21 | Q3 | FY22 | Q2 |
148 | Miramar Landfill Fee Booth Truck Scale #3 Replacement | AFA00001 | Environmental Services | Sole Source | $190,000 | $220,000 | FY22 | Q1 | FY22 | Q1 |
149 | Miramar Landfill Outbound Scale #5 Replacement | AFA00001 | Environmental Services | Sole Source | $190,000 | $220,000 | FY22 | Q1 | FY22 | Q1 |
150 | AC Water & Sewer Group 1056 (S) | B18182 | Public Utilities | Design Bid Build | $181,800 | $241,700 | FY21 | Q3 | FY22 | Q1 |
151 | Linda Vista Skate Park Phase 2 | B19062 | Parks & Recreation | Job Order Contract | $168,700 | $429,930 | FY21 | Q4 | FY22 | Q1 |
152 | Talmadge Traffic Calming Infrastructure | S17001 | Transportation & Storm Water | Design Bid Build | $167,100 | $330,000 | FY21 | Q3 | FY22 | Q1 |
153 | Crown Point SD Replacement | B19089 | Transportation & Storm Water | Design Bid Build | $145,500 | $250,300 | FY22 | Q2 | FY22 | Q4 |
154 | Citywide Street Lights 1901 | B19052 | Transportation & Storm Water | Design Bid Build | $124,310 | $185,461 | FY22 | Q3 | FY22 | Q4 |
155 | Mt Acadia (Mt Alifan-Mt Burnham)SL UU621 | B17012 | Transportation & Storm Water | Job Order Contract | $110,000 | $298,000 | FY21 | Q4 | FY22 | Q2 |
156 | Balboa Park Golf Course - Bathroom Remod | B20064 | Parks & Recreation | Job Order Contract | $62,000 | $129,000 | FY21 | Q4 | FY22 | Q1 |
157 | Cchavez Pkwy (I5-Comml) UU27 | B21092 | Transportation & Storm Water | Job Order Contract | $60,000 | $150,000 | FY21 | Q4 | FY22 | Q3 |
158 | Kellogg Comfort Station Improvements | B20120 | Real Estate Assets - Facilities | Job Order Contract | $52,000 | $126,000 | FY21 | Q4 | FY22 | Q2 |
159 | Redwood St (Pershing-Boundary) SL UU611 | B20095 | Transportation & Storm Water | Job Order Contract | $30,000 | $252,000 | FY21 | Q4 | FY22 | Q3 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Transportation & Storm Water | $143,806,372 | $197,638,089 |
Library | $4,208,097 | $6,253,376 |
Public Utilities | $444,651,139 | $597,136,573 |
Fleet Services | $5,525,000 | $7,911,886 |
Environmental Services | $5,666,000 | $6,640,000 |
Real Estate Assets - Facilities | $702,000 | $806,000 |
Fire-Rescue | $30,617,265 | $37,418,794 |
Parks & Recreation | $76,564,108 | $118,668,236 |
Citywide | $13,214,699 | $14,772,123 |
Airports | $864,846 | $1,270,062 |
FY 2022 Total | $725,819,526 | $988,515,140 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015