Data Date: Oct 1, 2020
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | Block 8R UUP | 21003599 | Transportation & Storm Water | Design Bid Build | $7,930,000 | $10,705,500 | FY20 | Q2 | FY21 | Q1 |
2 | Rancho Penasquitos Paving Group 1 | B20138 | Transportation & Storm Water | Job Order Contract | $3,286,393 | $3,779,352 | FY20 | Q4 | FY21 | Q1 |
3 | PHR Pump Track Fence | B20031 | Parks & Recreation | Emergency (As-needed) | $274,903 | $274,903 | FY21 | Q1 | FY21 | Q1 |
4 | Sewer & AC Water Group 763 (S) | B00374 | Public Utilities | Design Bid Build | $8,986,036 | $10,611,813 | FY21 | Q1 | FY21 | Q4 |
5 | Sewer and AC Water Group 812 (S) | B00426 | Public Utilities | Design Bid Build | $3,047,000 | $5,304,266 | FY21 | Q1 | FY21 | Q3 |
6 | Rolando Improv 1 (W) | B20126 | Public Utilities | Design Bid Build | $4,336,300 | $6,201,100 | FY21 | Q2 | FY21 | Q3 |
7 | High Purity Oxygen Addition System PQPS | B21001 | Public Utilities | Design Bid Build | $1,933,000 | $2,416,250 | FY21 | Q2 | FY21 | Q4 |
8 | AC Overlay Group 2012 MM/RP | TBD | Transportation & Storm Water | Design Bid Build | $3,992,691 | $4,697,284 | FY21 | Q3 | FY21 | Q3 |
9 | AC Overlay Group 2016 Navajo G2 | TBD | Transportation & Storm Water | Design Bid Build | $4,707,300 | $5,538,000 | FY21 | Q3 | FY21 | Q3 |
10 | AC Overlay Group 2014 Southwest | TBD | Transportation & Storm Water | Design Bid Build | $8,884,200 | $10,452,000 | FY21 | Q3 | FY21 | Q4 |
11 | AC Overlay Group 2015 Southeast | TBD | Transportation & Storm Water | Design Bid Build | $7,094,100 | $8,346,000 | FY21 | Q3 | FY21 | Q4 |
12 | Sidewalk Replacement Group 2030 | TBD | Transportation & Storm Water | Design Bid Build | $1,500,000 | $1,800,000 | FY21 | Q3 | FY21 | Q4 |
13 | Palm Ave Storm Drain | B17163 | Transportation & Storm Water | Job Order Contract | $288,700 | $393,815 | FY20 | Q4 | FY21 | Q2 |
14 | Cardinal Road Emergency SD Replacement | B19090 | Transportation & Storm Water | Sole Source Emergency | $106,700 | $5,150,000 | FY19 | Q2 | FY21 | Q1 |
15 | Market Street-47th to Euclid-Complete Street | S16061 | Transportation & Storm Water | Design Bid Build | $6,110,157 | $9,719,909 | FY19 | Q4 | FY21 | Q1 |
16 | ADA S/W Group 4E College | B16107 | Transportation & Storm Water | Design Bid Build | $360,000 | $862,081 | FY20 | Q3 | FY21 | Q1 |
17 | 5865 Cozzens Street SD Emergency | B20068 | Transportation & Storm Water | Emergency (As-needed) | $40,629 | $750,000 | FY20 | Q2 | FY21 | Q1 |
18 | MBGC Clubhouse Demo/Prtbl Building Instl | S01090 | Parks & Recreation | Design Bid Build | $4,770,578 | $7,400,000 | FY20 | Q2 | FY21 | Q3 |
19 | MBGC Irrigation & Electrical Upgrades | S11010 | Parks & Recreation | Design Bid Build | $2,807,051 | $4,460,000 | FY20 | Q2 | FY21 | Q3 |
20 | SEWER GJ 798C | B00409 | Public Utilities | Design Bid Build | $212,420 | $590,885 | FY20 | Q4 | FY21 | Q2 |
21 | District 1 Block 1-J UUD | B00836 | Transportation & Storm Water | Job Order Contract | $422,809 | $971,809 | FY20 | Q3 | FY21 | Q3 |
22 | Block 8R UUP - CIP | B15097 | Transportation & Storm Water | Design Bid Build | $1,114,000 | $1,464,000 | FY20 | Q2 | FY21 | Q2 |
23 | Nimitz Bridge at NTC Rehabilitation | B15198 | Transportation & Storm Water | Design Bid Build | $344,666 | $930,000 | FY20 | Q4 | FY21 | Q1 |
24 | Sewer Group 776A | B16034 | Public Utilities | Design Bid Build | $4,194,279 | $5,780,974 | FY20 | Q3 | FY21 | Q2 |
25 | ADA Curb Ramp Winder & McKee | B16108 | Transportation & Storm Water | Design Bid Build | $346,000 | $910,800 | FY20 | Q4 | FY21 | Q2 |
26 | Market Street Water Pipe Replacement | B17052 | Public Utilities | Design Bid Build | $1,528,878 | $1,926,448 | FY20 | Q1 | FY21 | Q1 |
27 | Market Street Sewer Pipe Replacement | B17054 | Public Utilities | Design Bid Build | $342,555 | $486,973 | FY20 | Q1 | FY21 | Q1 |
28 | Sewer and AC Water Group 1032 (S) | B17104 | Public Utilities | Design Bid Build | $6,389,000 | $8,518,000 | FY20 | Q3 | FY21 | Q2 |
29 | Sewer and AC Water Group 1032 (W) | B17105 | Public Utilities | Design Bid Build | $7,071,000 | $9,428,000 | FY20 | Q3 | FY21 | Q2 |
30 | Mission Beach Water & Sewer Repl (W) | B17169 | Public Utilities | Design Bid Build | $13,035,280 | $15,336,196 | FY20 | Q3 | FY21 | Q3 |
31 | Mission Beach Water & Sewer Repl (S) | B17170 | Public Utilities | Design Bid Build | $2,194,515 | $2,641,715 | FY20 | Q3 | FY21 | Q3 |
32 | Intelligent Cities Outdoor Lightng Proj2 | B18036 | Sustainability | Design Bid Build | $9,000,000 | $30,000,000 | FY20 | Q2 | FY21 | Q1 |
33 | Center City - New Traffic Signals | B18083 | Transportation & Storm Water | Design Bid Build | $1,345,350 | $2,152,800 | FY20 | Q3 | FY21 | Q1 |
34 | Alvarado TS Water Main Relocations | B18104 | Public Utilities | Design Bid Build | $10,000,000 | $10,438,400 | FY20 | Q3 | FY21 | Q2 |
35 | Accelerated Pipeline Rehab Ref Group 846 | B18185 | Public Utilities | Design Bid Build | $1,005,500 | $1,177,588 | FY20 | Q4 | FY21 | Q3 |
36 | ADA APS Group 1E - Broadway PH 2 | B18213 | Transportation & Storm Water | Design Bid Build | $80,500 | $150,000 | FY20 | Q3 | FY21 | Q3 |
37 | OB Dog Beach Accessibility Improvements | B19000 | Parks & Recreation | Job Order Contract | $759,806 | $1,143,306 | FY20 | Q4 | FY21 | Q2 |
38 | Miramar Ranch North Paving G1 | B19007 | Transportation & Storm Water | Design Bid Build | $3,925,870 | $5,080,555 | FY20 | Q3 | FY21 | Q1 |
39 | SBWRP Variable Frequency Drive Repl | B19066 | Public Utilities | Design Bid Build | $550,000 | $955,500 | FY20 | Q4 | FY21 | Q4 |
40 | Mingei Museum Dome Waterproofing | B19067 | Parks & Recreation | Minor Contract | $295,150 | $360,150 | FY20 | Q1 | FY21 | Q1 |
41 | City Heights Pool Reconstruction | B19068 | Parks & Recreation | Design Bid Build | $5,502,229 | $6,781,682 | FY20 | Q1 | FY21 | Q2 |
42 | Downtown Complete St Impl Phase 2 | B19143 | Transportation & Storm Water | Design Bid Build | $1,792,937 | $3,461,637 | FY20 | Q2 | FY21 | Q1 |
43 | Tierrasanta Pool Stairway Replacement | B20115 | Real Estate Assets | Job Order Contract | $222,271 | $248,416 | FY20 | Q3 | FY21 | Q2 |
44 | Island Ave Mini Park Improvements | L16000.2 | Parks & Recreation | Design Bid Build | $2,162,000 | $3,227,650 | FY20 | Q2 | FY21 | Q3 |
45 | J Street Mini Park Improvement | L16000.6 | Parks & Recreation | Design Bid Build | $847,913 | $1,525,000 | FY20 | Q1 | FY21 | Q1 |
46 | Dennery Ranch Neighborhood Park | S00636 | Parks & Recreation | Agency/ Developer Managed Built - City Paid | $5,070,000 | $15,100,000 | FY20 | Q1 | FY21 | Q3 |
47 | FAIRBROO K NEIGHBORHOOD PARK - DEVELOPMEN | S01083 | Parks & Recreation | Design Bid Build | $3,535,354 | $6,011,281 | FY20 | Q4 | FY21 | Q1 |
48 | La Jolla Village/I-805 Landscape Maint | S15017 | Transportation & Storm Water | Design Bid Build | $438,069 | $610,000 | FY20 | Q4 | FY21 | Q1 |
49 | Alvarado Trunk Sewer Phase IV | S15019 | Public Utilities | Design Bid Build | $55,000,000 | $67,000,000 | FY20 | Q3 | FY21 | Q2 |
50 | Fire-Rescue Air Ops Facility - PH II | S18007 | Fire-Rescue | Design Build | $1,000,000 | $22,481,000 | FY20 | Q2 | FY21 | Q2 |
51 | Pomerado Park Reservoir Upgrade | B00156 | Public Utilities | Design Bid Build | $4,875,000 | $6,235,000 | FY21 | Q2 | FY21 | Q4 |
52 | North City Pure Water Facility | B15139 | Public Utilities | Design Bid Build | $416,828,625 | $498,601,841 | FY21 | Q1 | FY21 | Q3 |
53 | Mid-City & Eastern Area Signal Mods | B17128 | Transportation & Storm Water | Job Order Contract | $389,086 | $1,090,000 | FY22 | Q2 | FY21 | Q1 |
54 | Highland & Monroe Aves Storm Drain Repl | B12096 | Transportation & Storm Water | Design Bid Build | $1,586,000 | $2,168,871 | FY21 | Q2 | FY21 | Q3 |
55 | North City Pure Water Pump Station | B15140 | Public Utilities | Design Bid Build | $13,350,922 | $17,617,145 | FY21 | Q1 | FY21 | Q3 |
56 | Storm Drain Group 968 | B15028 | Transportation & Storm Water | Design Bid Build | $131,000 | $3,810,047 | FY21 | Q2 | FY21 | Q2 |
57 | Block 1M1 UUP (La Jolla) | B15084 | Transportation & Storm Water | Job Order Contract | $252,450 | $397,000 | FY21 | Q2 | FY21 | Q2 |
58 | Block 6H UUP | B15086 | Transportation & Storm Water | Job Order Contract | $350,000 | $523,000 | FY21 | Q2 | FY21 | Q3 |
59 | 7649 Shorewood Dr SD Repl Emergency | B20143 | Transportation & Storm Water | Emergency (As-needed) | $450,000 | $750,000 | FY20 | Q4 | FY21 | Q1 |
60 | 836 Gage Drive SD Replacement Emergency | B20109 | Transportation & Storm Water | Emergency (As-needed) | $600,000 | $750,000 | FY20 | Q3 | FY21 | Q1 |
61 | Morena Pump Station (Package A) | B15141 | Public Utilities | Design Bid Build | $93,975,000 | $342,027,972 | FY21 | Q1 | FY21 | Q3 |
62 | Morena Pipelines - North (Package B3) | B15141 | Public Utilities | Design Bid Build | $86,345,000 | $103,626,000 | FY21 | Q1 | FY21 | Q3 |
63 | ADA S/W Group 3E W Point Loma | B16100 | Transportation & Storm Water | Design Bid Build | $538,000 | $1,140,200 | FY21 | Q1 | FY21 | Q3 |
64 | Fanuel St III (Grand-PB Dr) Rd Imp UU188 | B17071 | Transportation & Storm Water | Design Bid Build | $137,121 | $221,565 | FY21 | Q1 | FY21 | Q2 |
65 | El Cajon Bl-Highland-58th Improv | B17003 | Transportation & Storm Water | Design Bid Build | $643,000 | $1,105,000 | FY21 | Q2 | FY21 | Q4 |
66 | San Vicente PH I-II Rd Imp UU505-UU506 | B17098 | Transportation & Storm Water | Design Bid Build | $359,483 | $961,628 | FY21 | Q1 | FY21 | Q2 |
67 | Howard PHI-II(Park-Texas) Rd Imp UU71-72 | B18136 | Transportation & Storm Water | Design Bid Build | $190,910 | $389,315 | FY21 | Q1 | FY21 | Q2 |
68 | Curb Ramp Improvement Group 1701 | B17114 | Transportation & Storm Water | Design Bid Build | $1,130,000 | $1,830,000 | FY21 | Q2 | FY21 | Q3 |
69 | Sewer and AC Water Group 812 (W) | B17115 | Public Utilities | Design Bid Build | $1,916,000 | $4,960,266 | FY21 | Q1 | FY21 | Q3 |
70 | Sewer and AC Water Group 763 (W) | B17116 | Public Utilities | Design Bid Build | $1,972,545 | $2,305,318 | FY21 | Q1 | FY21 | Q4 |
71 | Wightman (Chamoune -Euclid) Rd Imp UU388 | B18138 | Transportation & Storm Water | Design Bid Build | $123,367 | $517,830 | FY21 | Q1 | FY21 | Q2 |
72 | Torrey Pines Gf-Repr Storm Drain Outfall | B17152 | Transportation & Storm Water | Design Bid Build | $2,135,000 | $3,360,000 | FY21 | Q1 | FY21 | Q3 |
73 | Sewer Group 843 | B17189 | Public Utilities | Design Bid Build | $6,127,389 | $8,022,289 | FY21 | Q2 | FY21 | Q2 |
74 | Asphalt Resurfacing Group 1901 | B18134 | Transportation & Storm Water | Design Bid Build | $9,746,100 | $10,486,046 | FY21 | Q2 | FY21 | Q2 |
75 | Mission Bl(Loring-Turquoise) Rd Imp UU30 | B18140 | Transportation & Storm Water | Design Bid Build | $170,777 | $1,212,544 | FY21 | Q1 | FY21 | Q2 |
76 | Golfcrest(Jackson-Wandermere)Rd ImpUU584 | B18149 | Transportation & Storm Water | Design Bid Build | $221,988 | $428,009 | FY21 | Q1 | FY21 | Q2 |
77 | Hilltop PH I(Boundary-Toyne)Rd Imp UU617 | B18153 | Transportation & Storm Water | Design Bid Build | $235,392 | $622,463 | FY21 | Q1 | FY21 | Q2 |
78 | Concrete Street Panel Repl - Coast Bl | B20046 | Transportation & Storm Water | Design Bid Build | $829,591 | $1,400,656 | FY21 | Q1 | FY21 | Q3 |
79 | Coast Cave SD Accelerated Replacement | B20076 | Transportation & Storm Water | Design Bid Build | $223,095 | $313,423 | FY21 | Q1 | FY21 | Q2 |
80 | Olive St Park Acquisition and Develpment | S10051 | Parks & Recreation | Design Bid Build | $1,983,000 | $5,171,585 | FY21 | Q1 | FY21 | Q3 |
81 | Adult Fitness Course East Shore | B18223 | Parks & Recreation | Design Bid Build | $1,060,000 | $1,954,000 | FY21 | Q2 | FY21 | Q2 |
82 | Tecolote North Playground Improvements | B18232 | Parks & Recreation | Design Bid Build | $1,469,984 | $2,964,000 | FY21 | Q2 | FY21 | Q2 |
83 | Tecolote North Comfort Station Imp | B18233 | Parks & Recreation | Design Bid Build | $1,639,422 | $1,963,000 | FY21 | Q2 | FY21 | Q2 |
84 | AC Overlay Group 2010 Peninsula | TBD | Transportation & Storm Water | Design Bid Build | $6,871,844 | $8,084,523 | FY21 | Q1 | FY21 | Q2 |
85 | Tecolote South Comfort Station Imp | B19015 | Parks & Recreation | Design Bid Build | $1,608,085 | $1,931,000 | FY21 | Q2 | FY21 | Q2 |
86 | Tecolote South Playground Improvements | B19016 | Parks & Recreation | Design Bid Build | $2,537,976 | $3,027,000 | FY21 | Q2 | FY21 | Q2 |
87 | Tecolote South Parking Lot Improvements | B19017 | Parks & Recreation | Design Bid Build | $419,282 | $528,000 | FY21 | Q2 | FY21 | Q2 |
88 | Bay Ho Improv 1 (S) | B19088 | Public Utilities | Design Bid Build | $5,208,400 | $7,024,800 | FY21 | Q2 | FY21 | Q3 |
89 | AC Overlay Group 2011 Rancho Bernardo | TBD | Transportation & Storm Water | Design Bid Build | $6,972,676 | $8,203,148 | FY21 | Q1 | FY21 | Q2 |
90 | AC Overlay Group 2013 La Jolla Pkwy | TBD | Transportation & Storm Water | Design Bid Build | $3,778,773 | $4,445,616 | FY21 | Q1 | FY21 | Q2 |
91 | Chollas Crane Replacement | L14002.4 | Fleet Operations | Design Bid Build | $300,000 | $555,000 | FY21 | Q2 | FY21 | Q3 |
92 | Chollas Paint Booth | L14002.5 | Fleet Operations | Design Bid Build | $303,000 | $666,000 | FY21 | Q2 | FY21 | Q3 |
93 | EMTS Boat Dock Esplanade | S00319 | Public Utilities | Design Bid Build | $2,160,380 | $3,333,000 | FY21 | Q2 | FY21 | Q3 |
94 | University Ave Mobility Plan | S00915 | Transportation & Storm Water | Design Bid Build | $5,974,533 | $9,553,350 | FY21 | Q2 | FY21 | Q4 |
95 | La Paz Mini Park | S11103 | Parks & Recreation | Design Bid Build | $1,502,338 | $2,602,840 | FY21 | Q2 | FY21 | Q4 |
96 | Convention Center Phase III Expansion | S12022 | Citywide | Construction Manager at Risk | $- | $- | FY21 | Q2 | FY21 | Q2 |
97 | Salk Neighborhood Park & Joint Use Devel | S14007 | Parks & Recreation | Design Bid Build | $5,576,686 | $7,237,278 | FY21 | Q2 | FY21 | Q3 |
98 | Water Group 968 | B14099 | Public Utilities | Design Bid Build | $2,152,300 | $5,064,806 | FY21 | Q1 | FY21 | Q4 |
99 | Olive Grove Community Park ADA Improveme | S15028 | Parks & Recreation | Design Bid Build | $2,386,895 | $3,437,268 | FY21 | Q2 | FY21 | Q3 |
100 | Harbor Drive Trunk Sewer Replacement | S18006 | Public Utilities | Design Bid Build | $14,700,000 | $21,045,000 | FY21 | Q2 | FY21 | Q2 |
101 | Sewer and AC Water Group 793 (S) | B00394 | Public Utilities | Design Bid Build | $5,305,291 | $6,624,611 | FY21 | Q2 | FY21 | Q4 |
102 | Fanuel St PI Archer to Tourmaline UUD | B00721 | Transportation & Storm Water | Job Order Contract | $90,344 | $142,047 | FY20 | Q3 | FY21 | Q1 |
103 | Water & Sewer Group 965 (S) | B12048 | Public Utilities | Design Bid Build | $1,855,400 | $2,932,600 | FY21 | Q2 | FY21 | Q4 |
104 | Water & Sewer Group 965 (W) | B12057 | Public Utilities | Design Bid Build | $1,769,500 | $2,934,600 | FY21 | Q2 | FY21 | Q4 |
105 | Adams Ave (1620) Storm Drain Replacement | B13102 | Transportation & Storm Water | Design Bid Build | $500,000 | $1,060,000 | FY21 | Q2 | FY21 | Q4 |
106 | Navajo Storm Drains | B15029 | Transportation & Storm Water | Design Bid Build | $2,100,400 | $3,266,409 | FY21 | Q2 | FY21 | Q4 |
107 | Logan Heights LID (South) | B15051 | Transportation & Storm Water | Design Bid Build | $3,705,000 | $5,316,000 | FY21 | Q2 | FY21 | Q4 |
108 | NCWRP Expansion | B15142 | Public Utilities | Design Bid Build | $123,741,148 | $159,419,446 | FY21 | Q2 | FY21 | Q4 |
109 | Pressure Reducing Stations Upgrades Phs1 | B16017 | Public Utilities | Design Bid Build | $3,740,000 | $6,290,000 | FY21 | Q2 | FY21 | Q3 |
110 | North City Pure Water Pipeline | B16035 | Public Utilities | Design Bid Build | $87,680,000 | $102,239,039 | FY21 | Q2 | FY21 | Q4 |
111 | North City Pure Water Subaqueous Pipeline | B16035 | Public Utilities | Design Bid Build | $5,270,000 | $7,000,000 | FY21 | Q2 | FY21 | Q4 |
112 | Southcrest Green Infrastructure (GI) | B16112 | Transportation & Storm Water | Design Bid Build | $3,055,400 | $4,600,000 | FY21 | Q2 | FY21 | Q4 |
113 | NCPWF Influent Pump Station and Pipeline | B16140 | Public Utilities | Design Bid Build | $29,218,851 | $38,413,734 | FY21 | Q2 | FY21 | Q4 |
114 | Asphalt Resurfacing Group 1902 | B18135 | Transportation & Storm Water | Design Bid Build | $2,552,801 | $3,003,295 | FY21 | Q1 | FY21 | Q2 |
115 | Governor Dr @ Lakewood St Traffic Signal | B17016 | Transportation & Storm Water | Design Bid Build | $275,700 | $460,000 | FY21 | Q3 | FY21 | Q4 |
116 | Clairemont Mesa Sewer Pipe Replacement | B17087 | Public Utilities | Design Bid Build | $186,000 | $346,100 | FY21 | Q2 | FY21 | Q4 |
117 | Balboa Park Pipeline Repl Ph II (S) | B17133 | Public Utilities | Design Bid Build | $1,852,000 | $1,730,069 | FY21 | Q2 | FY21 | Q4 |
118 | Balboa Park Pipeline Repl Ph II (W) | B17140 | Public Utilities | Design Bid Build | $3,790,000 | $8,041,636 | FY21 | Q2 | FY21 | Q4 |
119 | AC Water Group 1038 | B17153 | Public Utilities | Design Bid Build | $22,286,634 | $29,568,478 | FY21 | Q2 | FY21 | Q4 |
120 | Street Reconstruction Group 1801 | B17188 | Transportation & Storm Water | Design Bid Build | $8,200,000 | $12,710,000 | FY21 | Q2 | FY21 | Q3 |
121 | Sherman Height Community Center Playground | B18006 | Parks & Recreation | Design Bid Build | $350,000 | $697,471 | FY21 | Q2 | FY21 | Q4 |
122 | Convert Bldg 619 @ NTC into Rec Center | B18087 | Parks & Recreation | Design Bid Build | $3,579,000 | $6,228,000 | FY21 | Q2 | FY21 | Q4 |
123 | AC Water & Sewer Group 1051 (W) | B18091 | Public Utilities | Design Bid Build | $776,300 | $1,004,600 | FY21 | Q2 | FY21 | Q4 |
124 | AC Water & Sewer Group 1051 (S) | B18098 | Public Utilities | Design Bid Build | $3,136,600 | $4,059,100 | FY21 | Q2 | FY21 | Q4 |
125 | AC Water & Sewer Group 1036 (W) | B18121 | Public Utilities | Design Bid Build | $3,322,800 | $4,300,100 | FY21 | Q2 | FY21 | Q4 |
126 | Coronado SB (27th SB-Madden)Rd Imp UU193 | B18137 | Transportation & Storm Water | Design Bid Build | $268,213 | $337,203 | FY21 | Q2 | FY21 | Q4 |
127 | 32nd St PHII (Market-Imp.) Rd Imp UU17 | B18141 | Transportation & Storm Water | Design Bid Build | $268,213 | $350,089 | FY21 | Q2 | FY21 | Q4 |
128 | Block 6DD1 (Clairemont Mesa)Rd Imp UU410 | B18142 | Transportation & Storm Water | Design Bid Build | $1,473,215 | $1,959,764 | FY21 | Q2 | FY21 | Q4 |
129 | 32nd St PH I (Market-F St) Rd Imp UU386 | B18144 | Transportation & Storm Water | Design Bid Build | $124,122 | $159,998 | FY21 | Q2 | FY21 | Q4 |
130 | 31st Street (Market-L ST) Rd Imp UU11 | B18147 | Transportation & Storm Water | Design Bid Build | $286,745 | $366,702 | FY21 | Q2 | FY21 | Q4 |
131 | Cass (Grand-Pacific Bch Dr) Rd Imp UU143 | B18148 | Transportation & Storm Water | Design Bid Build | $109,924 | $172,019 | FY21 | Q2 | FY21 | Q4 |
132 | 25th (SB) (Coronado-Grove) Rd Imp UU995 | B18150 | Transportation & Storm Water | Design Bid Build | $88,173 | $131,599 | FY21 | Q2 | FY21 | Q4 |
133 | Hughes St (58th St-Jodi St) Rd Imp UU101 | B18151 | Transportation & Storm Water | Design Bid Build | $208,247 | $276,935 | FY21 | Q2 | FY21 | Q4 |
134 | Block 1M (La Jolla 4) Rd Imp UU659 | B18155 | Transportation & Storm Water | Design Bid Build | $817,563 | $1,135,146 | FY21 | Q3 | FY21 | Q4 |
135 | ADACA Woodman St-Cielo to Pagel PL Sidwl | B18159 | Transportation & Storm Water | Design Bid Build | $525,261 | $1,001,421 | FY21 | Q2 | FY21 | Q4 |
136 | Talmadge AC Water Main Replacement | B18197 | Public Utilities | Design Bid Build | $814,100 | $2,138,081 | FY21 | Q2 | FY21 | Q4 |
137 | DeAnza North Parking Lot Improvements | B18220 | Parks & Recreation | Design Bid Build | $579,000 | $870,167 | FY21 | Q3 | FY21 | Q3 |
138 | Tecolote North Parking Lot Improvements | B18231 | Parks & Recreation | Design Bid Build | $706,160 | $869,000 | FY21 | Q2 | FY21 | Q2 |
139 | Santa Clara Playground Improvements | B19029 | Parks & Recreation | Design Bid Build | $1,377,009 | $1,960,000 | FY21 | Q2 | FY21 | Q4 |
140 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation | Design Bid Build | $506,137 | $750,000 | FY21 | Q2 | FY21 | Q4 |
141 | Linda Vista Skate Park Phase 2 | B19062 | Parks & Recreation | Job Order Contract | $168,700 | $348,900 | FY21 | Q2 | FY21 | Q4 |
142 | Accelerated MH Referral Group 1 | B19097 | Public Utilities | Design Bid Build | $515,000 | $741,980 | FY21 | Q2 | FY21 | Q4 |
143 | Citywide Street Lights 1950 | B19125 | Transportation & Storm Water | Job Order Contract | $1,350,000 | $1,490,000 | FY21 | Q2 | FY21 | Q2 |
144 | Sewer Rehab 1051A | B19145 | Public Utilities | Design Bid Build | $126,200 | $178,200 | FY21 | Q2 | FY21 | Q4 |
145 | AC Water and Sewer Group 1052A (W) | B19166 | Public Utilities | Multiple Award Construction Contract | $3,502,400 | $5,182,900 | FY21 | Q2 | FY21 | Q4 |
146 | AC Water & Sewer Group 1052A (S) | B19169 | Public Utilities | Multiple Award Construction Contract | $1,923,000 | $2,814,100 | FY21 | Q2 | FY21 | Q4 |
147 | Point Loma Library Chiller Replacement | B19203 | Library | Job Order Contract | $166,000 | $280,000 | FY21 | Q2 | FY21 | Q3 |
148 | Balboa Park Golf Course - Bathroom Remod | B20064 | Parks & Recreation | Job Order Contract | $62,000 | $129,000 | FY21 | Q2 | FY21 | Q4 |
149 | Miramar Landfill Trailer Replacements | L17000.6 | Environmental Services | Design Build | $300,000 | $400,000 | FY21 | Q2 | FY21 | Q3 |
150 | Chollas Lake Electrical Upgrade | L18001.1 | Parks & Recreation | Design Bid Build | $424,000 | $850,000 | FY21 | Q2 | FY21 | Q4 |
151 | Miramar Landfill Storm Water Basin Improvements | L18002.3 | Environmental Services | Design Bid Build | $6,000,000 | $8,000,000 | FY21 | Q2 | FY21 | Q3 |
152 | Hickman Fields Athletic Area | S00751 | Parks & Recreation | Design Bid Build | $7,200,000 | $9,566,318 | FY21 | Q2 | FY21 | Q3 |
153 | El Monte Pipeline No. 2 | S10008 | Public Utilities | Design Bid Build | $17,900,000 | $24,500,000 | FY21 | Q2 | FY21 | Q4 |
154 | Cielo & Woodman Pump Station | S12012 | Public Utilities | Design Bid Build | $4,678,000 | $6,678,000 | FY21 | Q2 | FY21 | Q4 |
155 | Alvarado 2nd Extension Pipeline | S12013 | Public Utilities | Design Bid Build | $65,210,000 | $102,648,545 | FY21 | Q2 | FY21 | Q4 |
156 | Wangenheim Joint Use Facility | S15007 | Parks & Recreation | Design Bid Build | $6,386,396 | $9,517,667 | FY21 | Q2 | FY21 | Q3 |
157 | Fire Station 48 | S15015 | Fire-Rescue | Design Build | $11,137,500 | $15,091,000 | FY21 | Q2 | FY21 | Q4 |
158 | Carmel Del Mar NP Comfort Station - Dev | S16034 | Parks & Recreation | Design Bid Build | $1,519,564 | $2,330,564 | FY21 | Q3 | FY21 | Q4 |
159 | Talmadge Traffic Calming Infrastructure | S17001 | Parks & Recreation | Design Bid Build | $173,938 | $310,000 | FY21 | Q2 | FY21 | Q4 |
160 | Kearny Mesa Pipeline Manway | B20072 | Public Utilities | Design Bid Build | $330,000 | $492,700 | FY21 | Q3 | FY21 | Q4 |
161 | Water Group Job 952 | B11048 | Public Utilities | Design Bid Build | $5,300,000 | $7,393,194 | FY21 | Q3 | FY21 | Q4 |
162 | Pipeline Rehabilitation AY-1 | B18212 | Public Utilities | Design Bid Build | $6,561,800 | $7,841,500 | FY21 | Q2 | FY21 | Q3 |
163 | Citywide Street Lights Group 1702 | B17051 | Transportation & Storm Water | Job Order Contract | $441,200 | $749,144 | FY21 | Q2 | FY21 | Q4 |
164 | Plumosa Park Series Circuit Conversion | B17101 | Transportation & Storm Water | Job Order Contract | $765,000 | $1,450,000 | FY21 | Q3 | FY21 | Q4 |
165 | Ingulf St (Morena Bl-Erie St) SL UU123 | B18126 | Transportation & Storm Water | Job Order Contract | $24,200 | $78,000 | FY20 | Q3 | FY21 | Q1 |
166 | Orange Av PH3 Central-Fairmont SL UU24 | B18130 | Transportation & Storm Water | Job Order Contract | $53,200 | $207,600 | FY20 | Q3 | FY21 | Q2 |
167 | Thermal Ave - Donax Ave to Palm Ave Sidewalk | B18157 | Transportation & Storm Water | Design Bid Build | $1,270,300 | $1,609,100 | FY21 | Q3 | FY21 | Q4 |
168 | Sidewalk Replacement Group 1903-SE & CH | B19014 | Transportation & Storm Water | Design Bid Build | $1,000,000 | $1,649,007 | FY21 | Q3 | FY21 | Q4 |
169 | Downtown Complete St Impl Phase 3A | B19144 | Transportation & Storm Water | Design Bid Build | $4,230,000 | $7,000,000 | FY21 | Q3 | FY21 | Q4 |
170 | Rose Marie Starns Parking Lot Imprvemts | B19163 | Parks & Recreation | Design Bid Build | $1,922,000 | $2,870,000 | FY21 | Q3 | FY21 | Q4 |
171 | Chollas Large Car Washes | L14002.3 | Fleet Operations | Design Bid Build | $1,650,000 | $2,748,370 | FY21 | Q3 | FY21 | Q4 |
172 | PD Substation Small Carwashes | L14002.6 | Fleet Operations | Design Bid Build | $2,200,000 | $3,488,516 | FY21 | Q3 | FY21 | Q4 |
173 | SCRIPPS MIRAMAR RANCH LIB | S00811 | Library | Design Bid Build | $4,270,000 | $6,076,377 | FY21 | Q3 | FY21 | Q4 |
174 | Canon Street Pocket Park | S16047 | Parks & Recreation | Design Bid Build | $1,224,350 | $2,567,315 | FY21 | Q3 | FY21 | Q4 |
175 | University Ave Complete Street | S18001 | Transportation & Storm Water | Design Bid Build | $4,838,300 | $7,229,400 | FY21 | Q3 | FY21 | Q4 |
176 | AC Water & Sewer Group 1056 (W) | B18181 | Public Utilities | Design Bid Build | $8,535,300 | $11,045,700 | FY21 | Q2 | FY21 | Q4 |
177 | AC Water & Sewer Group 1056 (S) | B18182 | Public Utilities | Design Bid Build | $181,800 | $241,700 | FY21 | Q2 | FY21 | Q4 |
178 | Torrey Highlands NP Upgrades | S16036 | Parks & Recreation | Design Bid Build | $660,000 | $1,027,937 | FY21 | Q2 | FY21 | Q2 |
179 | Mountain View Sports Courts | B18192 | Parks & Recreation | Job Order Contract | $542,000 | $1,252,000 | FY21 | Q1 | FY21 | Q2 |
180 | Balboa Park Pipeline Repl Ph III (W) | B17141 | Public Utilities | Design Bid Build | $3,010,000 | $5,004,135 | FY20 | Q3 | FY21 | Q4 |
181 | Balboa Park Pipeline Repl Ph III (S) | B17134 | Public Utilities | Design Bid Build | $1,213,000 | $1,998,500 | FY21 | Q3 | FY21 | Q4 |
182 | MLK Rec Center Moisture Intrusion | B19001 | Parks & Recreation | Design Bid Build | $1,020,093 | $2,439,820 | FY21 | Q1 | FY21 | Q3 |
183 | San Diego Av (Old Town-McKee) SL UU598 | B20045 | Transportation & Storm Water | Job Order Contract | $82,200 | $333,600 | FY20 | Q3 | FY21 | Q2 |
184 | Pacific Highlands Ranch Branch Library | S14023 | Library | Design Bid Build | $17,443,915 | $26,164,178 | FY21 | Q1 | FY21 | Q3 |
185 | Seminole PH2 (El Cajon-Stanley) SL UU630 | B17013 | Transportation & Storm Water | Job Order Contract | $108,000 | $270,000 | FY21 | Q1 | FY21 | Q1 |
186 | Citywide Street Lights Group 1801 | B18012 | Transportation & Storm Water | Design Bid Build | $120,000 | $207,238 | FY21 | Q2 | FY21 | Q3 |
187 | Block 3DD (Adams North) SL UU908 | B20050 | Transportation & Storm Water | To Be Determined | $279,400 | $844,000 | FY21 | Q3 | FY21 | Q3 |
188 | University of SD FH/FS Reconnection | B20136 | Public Utilities | Job Order Contract | $209,480 | $234,480 | FY21 | Q1 | FY21 | Q2 |
189 | Civita Franklin Ridge | 240033323 | Parks & Recreation | Agency/ Developer Managed Built Paid | $71,000 | $223,184 | FY21 | Q2 | FY21 | Q4 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Transportation & Storm Water | $86,371,600 | $141,416,273 |
Library | $21,879,915 | $32,520,555 |
Public Utilities | $93,878,000 | $113,534,950 |
Transportation & Storm Water | $50,990,779 | $59,839,218 |
Parks & Recreation | $74,679,998 | $121,907,286 |
Public Utilities | $1,089,499,927 | $1,609,180,421 |
Sustainability | $9,000,000 | $30,000,000 |
Real Estate Assets | $222,271 | $248,416 |
Fire-Rescue | $12,137,500 | $37,572,000 |
Fleet Operations | $4,453,000 | $7,457,886 |
Citywide | $0 | $0 |
Environmental Services | $6,300,000 | $8,400,000 |
FY 2021 Total | $1,449,412,990 | $2,162,077,005 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015