Data Date: April 1, 2021

To create the print version set the font-size:0.5em on both tables. Save as PDF in Chrome; More Settings - Margins:None and Scale:85. Also change link on https://www.sandiego.gov/cip/reports to match the year if starting with quarter 1.

This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.

PDF icon PRINT - Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)

File DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)

Asummary by asset-managing departmentsis listed at the bottom of this page.

*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.

Line
Number
Project
Name
Project
Number
Asset Managing
Department
Contract
Type
Estimated
Contract
Cost ($)
Estimated
Total Project
Cost ($)
Fiscal Year
Advertising
Quarter
Advertising
Fiscal Year
Awarding
Quarter
Awarding
1North City Pure Water Pump StationB15140Public UtilitiesDesign Bid Build$11,707,700$23,708,919FY19Q3FY21Q3
2North City Pure Water PipelineB16035Public UtilitiesDesign Bid Build$99,826,181$133,561,405FY19Q4FY21Q4
3City Heights Pool ReconstructionB19068Parks & RecreationDesign Bid Build$4,352,130$5,768,807FY20Q1FY21Q3
4AC Water & Sewer Group 1052A (S)B19169Public UtilitiesMultiple Award Construction Contract$2,946,100$4,000,000FY21Q3FY21Q4
5SBWRP Variable Frequency Drive ReplB19066Public UtilitiesDesign Bid Build$508,292$1,359,792FY20Q4FY21Q3
6AC Water and Sewer Group 1052A (W)B19166Public UtilitiesMultiple Award Construction Contract$5,500,000$7,000,000FY21Q3FY21Q4
7Market Street Sewer Pipe ReplacementB17054Public UtilitiesDesign Bid Build$337,555$486,973FY20Q1FY21Q1
8Market St-47th St to Euclid Complete StS16061Transportation & Storm WaterDesign Bid Build$6,710,300$9,805,084FY20Q1FY21Q1
9University Avenue MobilityS00915Transportation & Storm WaterDesign Bid Build$4,987,003$9,557,310FY21Q2FY21Q4
10ADA S/W Group 3E W Point LomaB16100Transportation & Storm WaterDesign Bid Build$553,231$1,339,502FY21Q1FY21Q3
11ADA Curb Ramp Winder & McKeeB16108Transportation & Storm WaterDesign Bid Build$310,567$918,617FY20Q4FY21Q3
12Hillside Dr (SD Install/Resurf) ImprovB20151Transportation & Storm WaterDesign Build$465,000$850,000FY21Q1FY21Q4
13Market Street Water Pipe ReplacementB17052Public UtilitiesDesign Bid Build$1,762,584$2,355,513FY20Q1FY21Q1
14Sewer and AC Water Group 812 (S)B00426Public UtilitiesDesign Bid Build$8,025,664$10,953,041FY21Q1FY21Q3
15Sewer and AC Water Group 812 (W)B17115Public UtilitiesDesign Bid Build$3,863,196$5,480,222FY21Q1FY21Q3
16AC Water Group 1038B17153Public UtilitiesDesign Bid Build$21,926,632$26,280,377FY21Q4FY21Q4
17AC Water & Sewer Group 1051 (W)B18091Public UtilitiesDesign Bid Build$1,140,590$1,368,890FY21Q2FY21Q4
18AC Water & Sewer Group 1051 (S)B18098Public UtilitiesDesign Bid Build$3,136,600$4,059,100FY21Q2FY21Q4
19AC Water & Sewer Group 1056 (W)B18181Public UtilitiesDesign Bid Build$8,535,300$11,045,700FY21Q3FY21Q4
20AC Water & Sewer Group 1056 (S)B18182Public UtilitiesDesign Bid Build$181,800$241,700FY21Q3FY21Q4
21Clairemont Mesa E Improv 1 (W)B18200Public UtilitiesDesign Bid Build$2,194,500$2,927,200FY21Q4FY21Q4
22Clairemont Mesa E Improv 1 (S)B18202Public UtilitiesDesign Bid Build$4,017,500$5,327,700FY21Q4FY21Q4
23Pipeline Rehabilitation AY-1B18212Public UtilitiesDesign Bid Build$6,561,800$7,841,500FY21Q2FY21Q3
24Sewer Rehab 1051AB19145Public UtilitiesDesign Bid Build$787,724$839,724FY21Q2FY21Q4
25Pipeline Rehabilitation BB-1B19201Public UtilitiesDesign Bid Build$6,871,000$8,600,000FY21Q3FY21Q4
26Pipeline Rehabilitation BA-1B20014Public UtilitiesDesign Bid Build$5,137,000$6,788,300FY21Q3FY21Q4
27Rolando Improv 1 (W)B20126Public UtilitiesJob Order Contract$3,765,110$5,506,477FY21Q2FY21Q2
28Trench Paving Sewer & AC Water Grp 697AB21015Transportation & Storm WaterDesign Bid Build$385,000$385,000FY19Q1FY21Q4
29Talmadge AC Water Main ReplacementB18197Public UtilitiesDesign Bid Build$1,494,592$2,138,081FY21Q3FY21Q4
30AC Water Group 1018 (P)B21087Transportation & Storm WaterDesign Bid Build$191,811$191,811FY18Q3FY21Q4
31Mingei Museum Dome WaterproofingB19067Parks & RecreationMinor Contract$445,066$635,000FY20Q1FY21Q1
32PHR Pump Track FenceB20031Parks & RecreationMinor Contract$274,903$400,000FY21Q1FY21Q1
33Buchanan Canyon SM Rpr/Repl EmergencyB21080Public UtilitiesEmergency (As-needed)$300,000$500,000FY21Q2FY21Q2
34Otay WTP Raw Wtr PS Rpr/Repl EmergencyB21025Public UtilitiesEmergency (As-needed)$100,000$200,000FY21Q1FY21Q1
35NCWRP Improvements to 30 MGDS17012Public UtilitiesDesign Bid Build$26,449,499$32,998,711FY19Q4FY21Q4
36Chollas Crane ReplacementL14002.4Fleet ServicesDesign Bid Build$421,270$705,000FY21Q2FY21Q4
37Point Loma Library Chiller ReplacementB19203LibraryJob Order Contract$175,172$430,000FY21Q3FY21Q4
38Citywide Street Lights 1950B19125Transportation & Storm WaterJob Order Contract$414,000$558,000FY21Q4FY21Q4
39Sewer & AC Water Group 763 (S)B00374Public UtilitiesDesign Bid Build$8,971,276$10,611,813FY21Q1FY21Q4
40Sewer and AC Water Group 1032 (S)B17104Public UtilitiesDesign Bid Build$5,440,946$8,518,000FY20Q3FY21Q2
41Sewer Group 843B17189Public UtilitiesDesign Bid Build$5,808,342$8,000,000FY21Q3FY21Q4
42Sewer Group 776AB16034Public UtilitiesDesign Bid Build$3,348,012$5,335,936FY20Q3FY21Q3
43Bay Ho Improv 1 (S)B19088Public UtilitiesDesign Bid Build$2,832,345$5,250,000FY21Q2FY21Q4
44Sewer and AC Water Group 1032 (W)B17105Public UtilitiesDesign Bid Build$7,913,003$10,348,685FY20Q3FY21Q2
45Sewer and AC Water Group 763 (W)B17116Public UtilitiesDesign Bid Build$1,969,305$2,305,318FY21Q1FY21Q4
46Miramar Ranch North Paving G1B19007Transportation & Storm WaterDesign Bid Build$4,239,292$5,105,000FY20Q3FY21Q1
47Chollas Lake Electrical UpgradeL18001.1Parks & RecreationDesign Bid Build$424,000$850,000FY21Q4FY21Q4
48Morena Improv 3 (S)B21064Public UtilitiesDesign Build$620,000$868,000FY21Q4FY21Q4
49Maple Canyon Restoration - Phase 1 (JOC)B17057Transportation & Storm WaterJob Order Contract$459,557$683,842FY21Q2FY21Q3
50Mt Albertine Ave CMP SD EmergencyB21006Transportation & Storm WaterEmergency (As-needed)$211,000$283,000FY21Q2FY21Q2
511st Ave CMP Storm Drain EmergencyB21005Transportation & Storm WaterDesign Bid Build$121,000$211,000FY21Q1FY21Q1
52Morena Improv 3 (W)B21056Public UtilitiesDesign Build$820,000$1,148,000FY21Q4FY21Q4
53Sherman Heights Com Center PlaygroundB18006Parks & RecreationDesign Bid Build$366,700$697,471FY21Q3FY21Q4
54Morena Conveyance NorthernB15141.2Public UtilitiesDesign Bid Build$95,243,645$118,452,448FY19Q3FY21Q4
55PWP North City Water Rec Plant ExpansionB21060Public UtilitiesDesign Bid Build$148,491,498$195,829,212FY19Q4FY21Q4
56PWP Morena Wastewater Pump StationB21061Public UtilitiesDesign Bid Build$112,386,346$146,885,953FY21Q2FY21Q4
57MBC Equipment UpgradesS17013Public UtilitiesDesign Bid Build$35,400,000$45,503,972FY21Q3FY21Q4
58NCPWF Influent Pump Station and PipelineB16140Public UtilitiesDesign Bid Build$19,127,010$30,891,790FY19Q4FY21Q4
59San Diego NC-MBC ImprovementsB17006Public UtilitiesDesign Bid Build$2,484,300$9,599,422FY21Q3FY21Q4
60PWP North City Pure Water Facility Pkg 2B21058Public UtilitiesDesign Bid Build$345,974,226$452,233,288FY20Q1FY21Q3
61Nimitz Bridge at NTC RehabilitationB15198Transportation & Storm WaterDesign Bid Build$344,666$930,000FY20Q4FY21Q1
62ADA S/W Group 4E CollegeB16107Transportation & Storm WaterDesign Bid Build$249,526$751,607FY20Q3FY21Q1
63Adult Fitness Course East ShoreB18223Parks & RecreationDesign Bid Build$501,000$1,954,000FY21Q2FY21Q4
64FAIRBROOK NEIGHBORHOOD PARK - DEVELOPMENS01083Parks & RecreationDesign Bid Build$3,185,354$6,011,280FY20Q4FY21Q1
65Tecolote South Playground ImprovementsB19016Parks & RecreationDesign Bid Build$2,482,838$3,027,000FY21Q3FY21Q4
66Tecolote North Playground ImprovementsB18232Parks & RecreationDesign Bid Build$2,411,252$2,964,000FY21Q2FY21Q4
67Tecolote North Comfort Station ImpB18233Parks & RecreationDesign Bid Build$1,200,000$1,963,000FY21Q2FY21Q4
68Tecolote South Comfort Station ImpB19015Parks & RecreationDesign Bid Build$1,350,000$1,931,000FY21Q2FY21Q4
69Torrey Highlands Neighborhood Park UpgraS16036Parks & RecreationJob Order Contract$690,000$1,057,937FY20Q2FY21Q4
70Tecolote North Parking Lot ImprovementsB18231Parks & RecreationDesign Bid Build$400,000$869,000FY21Q1FY21Q4
71Tecolote South Parking Lot ImprovementsB19017Parks & RecreationDesign Bid Build$250,000$528,000FY21Q2FY21Q4
72Mission Beach Water & Sewer Repl (S)B17170Public UtilitiesDesign Bid Build$2,408,258$3,124,042FY20Q3FY21Q2
73Accelerated Pipeline Rehab Ref Group 846B18185Public UtilitiesDesign Bid Build$966,888$1,177,588FY20Q4FY21Q2
74AC Water & Sewer Group 1036 (S)B18123Public UtilitiesDesign Bid Build$525,900$652,800FY21Q4FY21Q4
75SEWER GJ 798CB00409Public UtilitiesDesign Bid Build$318,925$590,885FY20Q4FY21Q2
76Mission Beach Water & Sewer Repl (W)B17169Public UtilitiesDesign Bid Build$10,794,707$14,317,814FY20Q3FY21Q2
77Water Group 968B14099Public UtilitiesDesign Bid Build$3,730,595$4,760,795FY21Q1FY21Q3
78AC Water & Sewer Group 1036 (W)B18121Public UtilitiesDesign Bid Build$3,322,800$4,300,100FY21Q4FY21Q4
79OB Dog Beach Accessibility ImprovementsB19000Parks & RecreationJob Order Contract$442,526$1,143,306FY20Q4FY21Q2
80Concrete Street Panel Repl - Coast BlB20046Transportation & Storm WaterDesign Bid Build$702,685$1,723,480FY21Q1FY21Q3
81La Jolla Village/I-805 Landscape MaintS15017Transportation & Storm WaterDesign Bid Build$438,070$553,870FY15FY21Q1
82Coast Cave SD Accelerated ReplacementB20076Transportation & Storm WaterDesign Bid Build$290,767$389,200FY21Q1FY21Q3
83Island Ave Mini Park ImprovementsL16000.2Parks & RecreationDesign Bid Build$1,897,205$3,170,000FY20Q2FY21Q2
84La Paz Mini ParkS11103Parks & RecreationDesign Bid Build$1,283,284$2,602,840FY21Q2FY21Q3
85J Street Mini Park ImprovementL16000.6Parks & RecreationDesign Bid Build$844,490$1,536,095FY20Q1FY21Q1
86Balboa Park Pipeline Repl Ph III (S)B17134Public UtilitiesDesign Bid Build$942,476$1,822,975FY20Q3FY21Q3
87Balboa Park Pipeline Repl Ph II (S)B17133Public UtilitiesDesign Bid Build$960,935$1,552,245FY21Q4FY21Q4
88Balboa Park Pipeline Repl Phase II (W)B17140Public UtilitiesDesign Bid Build$4,197,462$6,775,153FY21Q4FY21Q4
89Balboa Park Pipeline Repl Ph III (W)B17141Public UtilitiesDesign Bid Build$2,856,853$4,850,988FY20Q3FY21Q3
90University of SD FH/FS ReconnectionB20136Public UtilitiesJob Order Contract$183,116$208,116FY21Q1FY21Q4
91Downtown Complete St Impl Phase 2B19143Transportation & Storm WaterDesign Bid Build$2,392,937$3,941,565FY20Q2FY21Q1
92Center City - New Traffic SignalsB18083Transportation & Storm WaterDesign Bid Build$1,345,317$2,152,767FY20Q2FY21Q1
93District 1 Block 1-J UUDB00836Transportation & Storm WaterJob Order Contract$695,618$1,044,618FY20Q3FY21Q4
94San Diego Av (Old Town-McKee) SL UU598B20045Transportation & Storm WaterJob Order Contract$124,422$337,022FY20Q3FY21Q2
95Orange Av PH3 Central-Fairmount SL UU24B18130Transportation & Storm WaterJob Order Contract$112,456$266,856FY20Q3FY21Q2
96Ingulf St (Morena Bl-Erie St) SL UU123B18126Transportation & Storm WaterJob Order Contract$96,673$144,473FY20Q3FY21Q1
97Fanuel St PI Archer to Tourmaline UUDB00721Transportation & Storm WaterJob Order Contract$90,344$142,047FY20Q3FY21Q1
98Seminole PH2 (El Cajon-Stanley) SL UU630B17013Transportation & Storm WaterJob Order Contract$83,264$120,000FY21Q1FY21Q1

Summary By Asset-Managing Departments

Asset-Managing DepartmentEstimated Construction Contract AwardEstimated Total Project Cost
Library$175,172$430,000
Parks & Recreation$22,800,747$37,108,735
Public Utilities$1,055,116,086$1,401,484,662
Transportation & Storm Water$26,014,504$42,385,670
Fleet Services$421,270$705,000
FY 2021 Total$1,104,527,779$1,482,114,067

*Estimated Advertise and Award Dates for Pure Water projects are to be determined

Archive of Anticipated CIP Projects