Data Date: February 1, 2020
This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.
PRINT - Forecast of Projects to be Awarded Fiscal Year 2021 (Proposed Budget)
DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Asummary by asset-managing departmentsis listed at the bottom of this page.
*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.
Line Number | Project Name | Project Number | Asset Managing Department | Contract Type | Estimated Contract Cost ($) | Estimated Total Project Cost ($) | Fiscal Year Advertising | Quarter Advertising | Fiscal Year Awarding | Quarter Awarding |
---|---|---|---|---|---|---|---|---|---|---|
1 | Pomerado Park Reservoir Upgrade | B00156 | PUD Water | Design Bid Build | $4,875,000 | $6,888,000 | FY21 | Q1 | FY21 | Q3 |
2 | Sewer & AC Water Group 763 (S) | B00374 | PUD Water | Design Bid Build | $4,080,280 | $5,720,817 | FY20 | Q4 | FY21 | Q2 |
3 | Sewer and AC Water Group 793 (S) | B00394 | PUD Sewer | Design Bid Build | $5,305,291 | $6,624,611 | FY21 | Q2 | FY21 | Q3 |
4 | Sewer and AC Water Group 812 (S) | B00426 | PUD Water | Design Bid Build | $3,047,000 | $4,030,000 | FY21 | Q1 | FY21 | Q3 |
5 | MISSION CTR CNYN A SMR | B00431 | PUD Sewer | Design Bid Build | $2,164,500 | $3,188,600 | FY20 | Q4 | FY21 | Q2 |
6 | SEWER GROUP 828 | B00434 | PUD Sewer | Design Bid Build | $4,807,950 | $6,744,100 | FY21 | Q2 | FY21 | Q4 |
7 | Stlight Design & Install 30th St - Ocean | B12001 | TSW | Job Order Contract | $107,100 | $126,000 | FY20 | Q4 | FY21 | Q1 |
8 | Water & Sewer Group 965 (S) | B12048 | PUD Sewer | Design Bid Build | $1,855,400 | $2,932,600 | FY21 | Q2 | FY21 | Q4 |
9 | Water & Sewer Group 965 (W) | B12057 | PUD Water | Design Bid Build | $1,769,500 | $2,934,600 | FY21 | Q2 | FY21 | Q4 |
10 | Signal Mods in Barrio Logan | B13010 | TSW | Design Bid Build | $190,900 | $300,000 | FY20 | Q3 | FY21 | Q1 |
11 | Adams Ave (1620) Storm Drain Replacement | B13102 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $500,000 | $868,000 | FY21 | Q1 | FY21 | Q3 |
12 | Division St & Osborn St Traffic Signal | B15047 | TSW | Design Bid Build | $212,200 | $275,000 | FY21 | Q3 | FY21 | Q4 |
13 | Pacific Beach TS Interconnect Upgrade | B15065 | Transportation and Storm Water Department - Street Division | Job Order Contract | $933,030 | $1,841,619 | FY20 | Q3 | FY21 | Q1 |
14 | Sewer and AC Water Group 793 (W) | B15070 | PUD Water | Design Bid Build | $677,900 | $964,700 | FY21 | Q2 | FY21 | Q3 |
15 | Block 1M1 UUP (La Jolla) | B15084 | TSW | Job Order Contract | $252,450 | $297,000 | FY20 | Q4 | FY21 | Q1 |
16 | Hancock Street UUP (Witherby to Tourquoi | B15096 | TSW | Job Order Contract | $53,550 | $63,000 | FY20 | Q4 | FY21 | Q1 |
17 | Block 2S2 UUP | B15098 | TSW | Job Order Contract | $260,100 | $306,000 | FY20 | Q4 | FY21 | Q1 |
18 | North City Pure Water Facility | B15139 | Public Utilities | Design Bid Build | $388,927,000 | $493,083,000 | FY21 | Q1 | FY21 | Q3 |
19 | North City Pure Water Pump Station | B15140 | PUD Water | Design Bid Build | $12,709,200 | $19,997,559 | FY21 | Q1 | FY21 | Q3 |
20 | NC Morena Blvd Pump Stations & Pipelines | B15141 | PUD Water | Design Bid Build | $90,000,000 | $100,000,000 | FY21 | Q1 | FY21 | Q3 |
21 | Morena Conveyance Northern Segment - B3 | B15141 | PUD Water | Design Bid Build | $98,047,703 | $122,559,629 | FY21 | Q1 | FY21 | Q3 |
22 | NCWRP Expansion (Pkg. 2) | B15142 | Public Utilities | Design Bid Build | $148,300,000 | $192,790,000 | FY21 | Q2 | FY21 | Q4 |
23 | Tecolote Cyn GC Water Conn | B15203 | PUD Water | Design Bid Build | $229,000 | $278,000 | FY21 | Q2 | FY21 | Q4 |
24 | Pressure Reducing Stations Upgrades Phs1 | B16017 | PUD Water | Design Bid Build | $3,740,000 | $6,290,000 | FY21 | Q2 | FY21 | Q3 |
25 | North City Pure Water Pipeline | B16035 | PUD Water | Design Bid Build | $80,421,961 | $121,995,876 | FY21 | Q2 | FY21 | Q4 |
26 | ADA S/W Group 3E W Point Loma | B16100 | Development Services Department | Design Bid Build | $538,000 | $1,139,502 | FY20 | Q4 | FY21 | Q2 |
27 | Southcrest Green Infrastructure (GI) | B16112 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $3,007,000 | $4,500,000 | FY21 | Q1 | FY21 | Q3 |
28 | NCPWF Influent Pump Station and Pipeline | B16140 | Public Utilities | Design Bid Build | $27,400,000 | $39,000,000 | FY21 | Q2 | FY21 | Q4 |
29 | Storm Drain Group 828 | B16155 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $1,840,150 | $3,000,000 | FY21 | Q2 | FY21 | Q4 |
30 | Otay 2nd Pipeline Phase 3 | B16158 | PUD Water | Design Bid Build | $10,116,000 | $12,636,000 | FY21 | Q1 | FY21 | Q3 |
31 | El Cajon Bl-Highland-58th Improv | B17003 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $643,000 | $1,215,050 | FY20 | Q4 | FY21 | Q2 |
32 | Murphy Canyon Trunk Sewer Repair/Rehab | B17005 | PUD Sewer | Design Bid Build | $12,378,317 | $16,393,110 | FY21 | Q2 | FY21 | Q3 |
33 | San Diego NC-MBC Improvements | B17006 | Public Utilities | Design Bid Build | $2,410,800 | $3,262,000 | FY21 | Q2 | FY21 | Q4 |
34 | Mt Acadia (Mt Alifan-Mt Burnham)SL UU621 | B17012 | TSW | Job Order Contract | $205,200 | $228,000 | FY21 | Q1 | FY21 | Q1 |
35 | Seminole PH2 (El Cajon-Stanley) SL UU630 | B17013 | TSW | Job Order Contract | $108,000 | $120,000 | FY21 | Q1 | FY21 | Q1 |
36 | Citywide Street Lights Group 1701 | B17050 | TSW | Design Bid Build | $419,500 | $700,600 | FY20 | Q4 | FY21 | Q3 |
37 | Citywide Street Lights Group 1702 | B17051 | TSW | Design Bid Build | $441,200 | $731,500 | FY20 | Q4 | FY21 | Q3 |
38 | Clairemont Mesa Sewer Pipe Replacement | B17087 | PUD Sewer | Design Bid Build | $153,800 | $228,400 | FY21 | Q1 | FY21 | Q2 |
39 | Curb Ramp Improvement Group 1701 | B17114 | Transportation and Storm Water Department - Street Division | Design Bid Build | $3,138,800 | $4,137,600 | FY20 | Q4 | FY21 | Q1 |
40 | Sewer and AC Water Group 812 (W) | B17115 | PUD Water | Design Bid Build | $1,916,000 | $2,555,000 | FY21 | Q1 | FY21 | Q3 |
41 | Sewer and AC Water Group 763 (W) | B17116 | PUD Water | Design Bid Build | $1,350,000 | $1,686,013 | FY20 | Q4 | FY21 | Q2 |
42 | Mid-City & Eastern Area Signal Mods | B17128 | TSW | Design Bid Build | $389,086 | $629,860 | FY21 | Q3 | FY21 | Q4 |
43 | Balboa Park Pipeline Repl Ph II (S) | B17133 | PUD Sewer | Design Bid Build | $1,852,000 | $3,043,651 | FY21 | Q2 | FY21 | Q4 |
44 | Balboa Park Pipeline Repl Ph II (W) | B17140 | PUD Water | Design Bid Build | $3,790,000 | $6,319,547 | FY21 | Q2 | FY21 | Q4 |
45 | Torrey Pines Gf-Repr Storm Drain Outfall | B17152 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $2,135,000 | $3,360,000 | FY21 | Q1 | FY21 | Q2 |
46 | Palm Ave Storm Drain | B17163 | Transportation and Storm Water Department - Storm Water Division | Job Order Contract | $288,700 | $502,700 | FY20 | Q4 | FY21 | Q1 |
47 | Street Reconstruction Group 1801 | B17188 | Street Division | Design Bid Build | $8,200,000 | $12,710,000 | FY21 | Q2 | FY21 | Q4 |
48 | Sewer Group 843 | B17189 | PUD Sewer | Design Bid Build | $4,224,400 | $5,719,300 | FY21 | Q1 | FY21 | Q2 |
49 | John F Kennedy Neighborhood Park Improve | B18005 | Parks & Recreation Department | Design Bid Build | $1,859,668 | $3,079,619 | FY20 | Q3 | FY21 | Q1 |
50 | Intelligent Cities Outdoor Lightng Proj2 | B18036 | Sustainability Department | Design Bid Build | $9,000,000 | $30,000,000 | FY20 | Q2 | FY21 | Q1 |
51 | Sewer & AC Water Group 1034 (S) | B18063 | PUD Sewer | Design Bid Build | $4,968,400 | $6,806,400 | FY21 | Q2 | FY21 | Q3 |
52 | Sewer & AC Water Group 1034 (W) | B18064 | PUD Water | Design Bid Build | $6,959,100 | $9,201,600 | FY21 | Q2 | FY21 | Q4 |
53 | Convert Bldg 619 @ NTC into Rec Center | B18087 | Parks & Recreation Department | Design Bid Build | $3,579,000 | $6,228,000 | FY21 | Q1 | FY21 | Q3 |
54 | AC Water & Sewer Group 1051 (W) | B18091 | PUD Sewer | Design Bid Build | $776,300 | $1,004,600 | FY21 | Q2 | FY21 | Q4 |
55 | AC Water & Sewer Group 1051 (S) | B18098 | PUD Sewer | Design Bid Build | $3,136,600 | $4,059,100 | FY21 | Q2 | FY21 | Q4 |
56 | AC Water & Sewer Group 1036 (W) | B18121 | PUD Sewer | Design Bid Build | $3,322,800 | $4,300,100 | FY21 | Q2 | FY21 | Q4 |
57 | AC Water & Sewer Group 1036 (S) | B18123 | PUD Sewer | Design Bid Build | $525,900 | $652,800 | FY21 | Q2 | FY21 | Q4 |
58 | Coronado SB (27th SB-Madden)Rd Imp UU193 | B18137 | TSW | Design Bid Build | $268,213 | $337,203 | FY21 | Q1 | FY21 | Q3 |
59 | 32nd St PHII (Market-Imp.) Rd Imp UU17 | B18141 | TSW | Design Bid Build | $268,213 | $337,203 | FY21 | Q1 | FY21 | Q3 |
60 | Block 6DD1 (Clairemont Mesa)Rd Imp UU410 | B18142 | TSW | Design Bid Build | $1,473,215 | $1,884,016 | FY21 | Q1 | FY21 | Q3 |
61 | 32nd St PH I (Market-F St) Rd Imp UU386 | B18144 | TSW | Design Bid Build | $124,122 | $154,689 | FY21 | Q1 | FY21 | Q3 |
62 | 31st Street (Market-L ST) Rd Imp UU11 | B18147 | TSW | Design Bid Build | $286,745 | $366,702 | FY21 | Q1 | FY21 | Q3 |
63 | Cass (Grand-Pacific Bch Dr) Rd Imp UU143 | B18148 | TSW | Design Bid Build | $109,924 | $140,575 | FY21 | Q1 | FY21 | Q3 |
64 | 25th (SB) (Coronado-Grove) Rd Imp UU995 | B18150 | TSW | Design Bid Build | $88,173 | $112,761 | FY21 | Q1 | FY21 | Q3 |
65 | Hughes St (58th St-Jodi St) Rd Imp UU101 | B18151 | TSW | Design Bid Build | $208,247 | $266,317 | FY21 | Q1 | FY21 | Q3 |
66 | Block 1M (La Jolla 4) Rd Imp UU659 | B18155 | TSW | Design Bid Build | $817,563 | $1,087,358 | FY21 | Q1 | FY21 | Q3 |
67 | 54th-Market to Santa margarita Sidwlk | B18158 | Transportation and Storm Water Department - Street Division | Design Bid Build | $394,900 | $694,100 | FY21 | Q1 | FY21 | Q3 |
68 | ADACA Woodman St-Cielo to Pagel Pl Sidwl | B18159 | Transportation and Storm Water Department - Storm Water Division | Design Bid Build | $525,261 | $926,800 | FY21 | Q2 | FY21 | Q4 |
69 | Talmadge AC Water Main Replacement | B18197 | PUD Water | Design Bid Build | $814,100 | $1,194,100 | FY21 | Q2 | FY21 | Q4 |
70 | Clairemont Mesa E Improv 1 (W) | B18200 | PUD Water | Design Bid Build | $2,194,500 | $2,927,200 | FY21 | Q3 | FY21 | Q4 |
71 | Clairemont Mesa E Improv 1 (S) | B18202 | PUD Sewer | Design Bid Build | $4,017,500 | $5,327,700 | FY21 | Q3 | FY21 | Q4 |
72 | Pipeline Rehabilitation AY-1 | B18212 | PUD Sewer | Design Bid Build | $6,561,800 | $7,841,500 | FY20 | Q4 | FY21 | Q2 |
73 | Adult Fitness Course East Shore | B18223 | Parks & Recreation Department | Design Bid Build | $1,060,000 | $1,954,000 | FY20 | Q4 | FY21 | Q1 |
74 | Tecolote North Parking Lot Improvements | B18231 | Parks & Recreation Department | Design Bid Build | $444,000 | $869,000 | FY20 | Q4 | FY21 | Q1 |
75 | Tecolote North Playground Improvements | B18232 | Parks & Recreation Department | Design Bid Build | $1,269,010 | $1,780,000 | FY20 | Q4 | FY21 | Q1 |
76 | Tecolote North Comfort Station Imp | B18233 | Parks & Recreation Department | Design Bid Build | $1,032,300 | $1,963,000 | FY20 | Q4 | FY21 | Q1 |
77 | OB Dog Beach Accessibility Improvements | B19000 | Parks & Recreation Department | Job Order Contract | $759,806 | $1,143,306 | FY20 | Q4 | FY21 | Q1 |
78 | Sidewalk Replacement Group 1902-CM & LJ | B19013 | TSW | Design Bid Build | $2,500,000 | $3,000,000 | FY20 | Q4 | FY21 | Q1 |
79 | Sidewalk Replacement Group 1903-SE & CH | B19014 | TSW | Design Bid Build | $1,000,000 | $1,400,000 | FY20 | Q4 | FY21 | Q1 |
80 | Tecolote South Comfort Station Imp | B19015 | Parks & Recreation Department | Design Bid Build | $1,012,320 | $1,931,000 | FY20 | Q4 | FY21 | Q1 |
81 | Tecolote South Parking Lot Improvements | B19017 | Parks & Recreation Department | Design Bid Build | $263,625 | $528,000 | FY20 | Q4 | FY21 | Q1 |
82 | Crown Point Playground Improvements | B19021 | Parks & Recreation Department | Design Bid Build | $1,077,924 | $1,960,000 | FY21 | Q1 | FY21 | Q3 |
83 | Crown Point Parking Lot Improvements | B19022 | Parks & Recreation Department | Design Bid Build | $907,500 | $1,557,000 | FY21 | Q1 | FY21 | Q3 |
84 | Santa Clara Playground Improvements | B19029 | Parks & Recreation Department | Design Bid Build | $1,377,009 | $1,960,000 | FY20 | Q4 | FY21 | Q2 |
85 | Santa Clara Comfort Station Improvements | B19032 | Parks & Recreation Department | Design Bid Build | $506,137 | $750,000 | FY20 | Q4 | FY21 | Q2 |
86 | SBWRP Variable Frequency Drive Repl | B19066 | PUD Sewer | Design Bid Build | $104,000 | $955,500 | FY20 | Q4 | FY21 | Q3 |
87 | Bay Ho Improv 1 (S) | B19088 | PUD Sewer | Design Bid Build | $5,068,300 | $8,465,000 | FY20 | Q4 | FY21 | Q2 |
88 | Accelerated MH Referral Group 1 | B19097 | PUD Sewer | Design Bid Build | $690,745 | $913,548 | FY21 | Q1 | FY21 | Q2 |
89 | Sewer Rehab 1051A | B19145 | PUD Sewer | Design Bid Build | $126,200 | $178,200 | FY21 | Q2 | FY21 | Q4 |
90 | Sunset Point Parking Lot Improvements | B19159 | Parks & Recreation Department | Job Order Contract | $250,000 | $450,000 | FY21 | Q3 | FY21 | Q4 |
91 | AC Water and Sewer Group 1052A (W) | B19166 | PUD Water | Multiple Award Construction Contract | $3,502,400 | $5,182,900 | FY21 | Q2 | FY21 | Q4 |
92 | AC Water & Sewer Group 1052A (S) | B19169 | PUD Sewer | Multiple Award Construction Contract | $1,923,000 | $2,814,100 | FY21 | Q2 | FY21 | Q4 |
93 | Storm Drain at MBC | B19197 | PUD Sewer | Design Bid Build | $2,260,800 | $3,481,800 | FY21 | Q3 | FY21 | Q4 |
94 | AC Water & Sewer Group 1023B | B19204 | PUD Water | Design Bid Build | $200,000 | $326,000 | FY20 | Q3 | FY21 | Q1 |
95 | AC Water & Sewer Group 1023B | B19205 | PUD Water | Design Bid Build | $2,000,000 | $2,941,000 | FY20 | Q3 | FY21 | Q1 |
96 | Concrete Street Panel Repl - Coast Bl | B20046 | Transportation and Storm Water Department - Street Division | Design Bid Build | $1,052,686 | $1,437,264 | FY20 | Q4 | FY21 | Q1 |
97 | Coast Cave SD Accelerated Replacement | B20076 | Transportation and Storm Water Department - Street Division | Design Bid Build | $223,095 | $313,423 | FY20 | Q4 | FY21 | Q1 |
98 | Chollas Large Car Washes | L14002.3 | Fleet Services | Design Bid Build | $1,650,000 | $2,748,370 | FY21 | Q2 | FY21 | Q3 |
99 | Chollas Crane Replacement | L14002.4 | Fleet Services | Design Bid Build | $300,000 | $555,000 | FY21 | Q1 | FY21 | Q1 |
100 | Chollas Paint Booth | L14002.5 | Fleet Services | Design Bid Build | $303,000 | $666,000 | FY21 | Q1 | FY21 | Q3 |
101 | PD Substation Small Carwashes | L14002.6 | Fleet Services | Design Bid Build | $2,200,000 | $3,488,516 | FY21 | Q2 | FY21 | Q3 |
102 | Clay Street Mini Park Improvement | L16000.5 | Parks & Recreation Department | Design Bid Build | $663,000 | $1,228,930 | FY20 | Q3 | FY21 | Q1 |
103 | Miramar Landfill Trailer Replacements | L17000.6 | Environmental Services | Sole Source | $1,500,000 | $2,000,000 | FY21 | Q2 | FY21 | Q2 |
104 | Miramar Landfill Storm Water Basin Improvements | L18002.3 | Environmental Services | Design Bid Build | $6,000,000 | $8,000,000 | FY21 | Q1 | FY21 | Q3 |
105 | EMTS Boat Dock Esplanade | S00319 | PUD Sewer | Design Bid Build | $2,160,380 | $3,333,000 | FY20 | Q4 | FY21 | Q2 |
106 | Hickman Fields Athletic Area | S00751 | Parks & Recreation Department | Design Bid Build | $6,690,000 | $8,928,714 | FY20 | Q3 | FY21 | Q1 |
107 | SCRIPPS MIRAMAR RANCH LIB | S00811 | Library Department | Design Bid Build | $4,270,000 | $6,076,377 | FY21 | Q2 | FY21 | Q4 |
108 | University Ave Mobility Plan | S00915 | Transportation and Storm Water Department - Street Division | Design Bid Build | $5,751,376 | $9,533,349 | FY20 | Q4 | FY21 | Q2 |
109 | Coastal Rail Trail | S00951 | TSW | Design Bid Build | $15,284,458 | $24,467,998 | FY21 | Q1 | FY21 | Q3 |
110 | FAIRBROO K NEIGHBORHOOD PARK - DEVELOPMEN | S01083 | Parks & Recreation Department | Design Bid Build | $4,366,673 | $6,045,539 | FY20 | Q4 | FY21 | Q1 |
111 | MBGC Clubhouse Demo/Prtbl Building Instl | S01090 | Parks & Recreation Department | Design Bid Build | $4,770,578 | $6,463,816 | FY20 | Q3 | FY21 | Q1 |
112 | El Monte Pipeline No. 2 | S10008 | PUD Water | Design Bid Build | $17,900,000 | $24,500,000 | FY21 | Q1 | FY21 | Q3 |
113 | Olive St Park Acquisition and Develpment | S10051 | Parks & Recreation Department | Design Bid Build | $1,659,494 | $3,271,585 | FY21 | Q4 | FY21 | Q4 |
114 | MBGC Irrigation & Electrical Upgrades | S11010 | Parks & Recreation Department | Design Bid Build | $2,807,051 | $4,460,000 | FY20 | Q3 | FY21 | Q1 |
115 | La Paz Mini Park | S11103 | Parks & Recreation Department | Design Bid Build | $1,502,338 | $2,603,754 | FY20 | Q3 | FY21 | Q1 |
116 | Cielo & Woodman Pump Station | S12012 | PUD Water | Design Bid Build | $4,678,000 | $6,678,000 | FY20 | Q3 | FY21 | Q1 |
117 | Alvarado 2nd Extension Pipeline | S12013 | PUD Water | Design Bid Build | $65,210,000 | $80,498,531 | FY21 | Q2 | FY21 | Q4 |
118 | El Cuervo Adobe Improvements | S14006 | Parks & Recreation Department | Job Order Contract | $273,480 | $606,000 | FY21 | Q2 | FY21 | Q4 |
119 | Salk Neighborhood Park & Joint Use Devel | S14007 | Parks & Recreation Department | Design Bid Build | $4,376,686 | $6,036,686 | FY20 | Q4 | FY21 | Q2 |
120 | Pacific Highlands Ranch Branch Library | S14023 | Library Department | Design Bid Build | $17,443,915 | $26,164,178 | FY20 | Q4 | FY21 | Q2 |
121 | Wangenheim Joint Use Facility | S15007 | Parks & Recreation Department | Design Bid Build | $6,386,396 | $9,190,353 | FY20 | Q4 | FY21 | Q2 |
122 | Tecolote Canyon Trunk Sewer Improvement | S15020 | PUD Sewer | Design Bid Build | $32,826,000 | $35,555,000 | FY21 | Q1 | FY21 | Q3 |
123 | Olive Grove Community Park ADA Improveme | S15028 | Parks & Recreation Department | Design Bid Build | $1,050,000 | $1,617,849 | FY20 | Q4 | FY21 | Q1 |
124 | Egger/South Bay Comm Pk ADA Improvements | S15031 | Parks & Recreation Department | Design Bid Build | $1,969,145 | $2,730,145 | FY21 | Q2 | FY21 | Q4 |
125 | Carmel Valley CP - Turf Upgrades | S16029 | Parks & Recreation Department | Design Bid Build | $2,505,000 | $4,274,121 | FY21 | Q1 | FY21 | Q3 |
126 | Ocean Air CP Comfort Station & Park Impr | S16031 | Parks & Recreation Department | Design Bid Build | $1,067,000 | $1,881,793 | FY21 | Q1 | FY21 | Q3 |
127 | Carmel Del Mar NP Comfort Station - Dev | S16034 | Parks & Recreation Department | Design Bid Build | $1,519,564 | $2,330,564 | FY20 | Q4 | FY21 | Q2 |
128 | Sage Canyon NP Concession Bldg-Develop | S16035 | Parks & Recreation Department | Job Order Contract | $767,500 | $1,310,500 | FY21 | Q1 | FY21 | Q3 |
129 | Canon Street Pocket Park | S16047 | Parks & Recreation Department | Design Bid Build | $1,224,350 | $2,567,315 | FY20 | Q4 | FY21 | Q1 |
130 | Talmadge Traffic Calming Infrastructure | S17001 | Parks & Recreation Department | Design Bid Build | $173,938 | $309,957 | FY21 | Q2 | FY21 | Q4 |
131 | North City Water Reclamation Plant Electrical Upgrades | S17012 | Public Utilities | Design Bid Build | $26,500,000 | $34,450,000 | FY21 | Q2 | FY21 | Q4 |
132 | MBC Equipment Upgrades | S17013 | Public Utilities | Design Bid Build | $30,109,800 | $39,956,000 | FY21 | Q2 | FY21 | Q4 |
133 | University Ave Complete Street | S18001 | Transportation and Storm Water Department - Street Division | Design Bid Build | $4,330,300 | $6,718,400 | FY21 | Q3 | FY21 | Q4 |
134 | Harbor Drive Trunk Sewer Replacement | S18006 | PUD Sewer | Design Bid Build | $14,700,000 | $21,045,000 | FY21 | Q1 | FY21 | Q2 |
135 | Fire-Rescue Air Ops Facility - PH II | S18007 | Fire-Rescue Department (FS) | Design Bid Build | $13,000,000 | $15,000,000 | FY20 | Q2 | FY21 | Q2 |
Summary By Asset-Managing Departments
Asset-Managing Department | Estimated Construction Contract Award | Estimated Total Project Cost |
---|---|---|
Development Services Department | $538,000 | $1,139,502 |
Library Department | $21,713,915 | $32,240,555 |
Parks & Recreation Department | $59,170,491 | $92,010,545 |
PUD Water | $420,227,644 | $548,305,071 |
PUD Sewer | $115,910,383 | $151,607,720 |
TSW | $25,068,159 | $37,331,782 |
Transportation and Storm Water Department - Storm Water Division | $8,939,111 | $14,372,550 |
Transportation and Storm Water Department - Street Division | $15,824,187 | $24,675,755 |
Public Utilities | $623,647,600 | $802,541,000 |
Street Division | $8,200,000 | $12,710,000 |
Sustainability Department | $9,000,000 | $30,000,000 |
Fleet Services | $4,453,000 | $7,457,886 |
Environmental Services | $7,500,000 | $10,000,000 |
Fire-Rescue Department (FS) | $13,000,000 | $15,000,000 |
FY 2021 Total | $1,333,192,490 | $1,779,392,366 |
*Estimated Advertise and Award Dates for Pure Water projects are to be determined
Archive of Anticipated CIP Projects
Forecast of Projects to be Awarded in Fiscal Year 2024
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2024 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2023
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2023 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2022
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2022 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2021
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Third Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Mid-Year Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (First Quarter Update)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Adopted Budget)
- Forecast of Projects to be Awarded in Fiscal Year 2021 (Proposed Budget)
Forecast of Projects to be Awarded in Fiscal Year 2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Third Quarter Update) as of 4/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (Second Quarter Update) as of 1/1/2016
- Forecast of Projects to be Awarded in Fiscal Year 2016 (First Quarter Update) as of 10/1/2015
- Forecast of Projects to be Awarded in Fiscal Year 2016 as of 07/1/2015