To comply with the requirements of Proposition A and the San Diego Sunshine Act, the contracts listed here are being made available to help ensure that the public has access to government information and policymaking information. These resources provide, in a searchable format, the text of all A&E and other consultant contracts entered into by the City valued at more than $25,000, from July 1, 2014 through June 30, 2015.
To view a contract, click on the Contract Number for the desired project.
Contract Number | Contract Name | Award Date | Award Amount | Contractor | Number of Firms Interviewed | Contact |
---|---|---|---|---|---|---|
H146219 | Design of Cielo & Woodman Pump Station | 6/17/2015 | $850,000.00 | AECOM Technical Services | 4 | Kyle Nguyen |
H156314 | Mission Hills/Hillcrest Branch Library Public Art Project | 6/15/2015 | $280,000.00 | Janet Zweig, LLC | 50 | Kyle Nguyen |
H146218 | Otay 2nd Pipeline - Phase 1 | 6/15/2015 | $550,000.00 | AECOM Technical Services | 4 | Kyle Nguyen |
H146292 | As-Needed Engineering Consultant Services | 6/3/2015 | $5,000,000.00 | Kleinfelder/Simon Wong Engineering | 12 | Kyle Nguyen |
H156462 | Desert View Drive Storm Drain Outfall | 5/28/2015 | $1,199,967.00 | Leighton & Associates | Sole Source | Kyle Nguyen |
H146279 | Landfill Gas to Energy Project | 5/27/2015 | $250,000.00 | HDR Engineering, Inc. | Sole Source | Kyle Nguyen |
H156344 | As-Needed Planning Services | 5/26/2015 | $2,125,000.00 | AECOM Technical Services | 15 | Kyle Nguyen |
H156343 | As-Needed Planning Services | 5/26/2015 | $2,125,000.00 | RRM Design Group | 15 | Kyle Nguyen |
H156342 | As-Needed Planning Services | 5/26/2015 | $2,125,000.00 | Dyett & Bhatia | 15 | Kyle Nguyen |
H146184 | 2015 Urban Water Management Plan (UWMP) | 5/21/2015 | $278,949.00 | CDM Smith, Inc. | 3 | Kyle Nguyen |
H156386 | San Diego Convention Center Assessment of Phase III Expansion Options | 4/13/2015 | $45,000.00 | CB Urban Development | Sole Source | Kyle Nguyen |
H156336 | As-Needed Traffic Engineering Services | 4/9/2015 | $1,050,000.00 | Kimley-Horn and Associates | 8 | Kyle Nguyen |
H156333 | As-Needed Traffic Engineering Services | 4/3/2015 | $1,050,000.00 | Chen Ryan Associates, Inc. | 8 | Kyle Nguyen |
H156485 | MOU R14MU350035 Between City of SD and The Bureau of Reclamation | 4/2/2015 | $300,000.00 | U.S. Department of the Interior, Bureau of Reclamation | Memorandum of Understanding | Kyle Nguyen |
H156539 | Participation Agreement - Otay 2nd Pipeline Relocation | 3/25/2015 | $1,634,092.00 | Baldwin & Sons, LLC | Participation Agreement | Kyle Nguyen |
H146201 | Bridging Documents for North University City Fire Station 50 | 3/25/2015 | $450,065.35 | Safdie Rabines Architects | 5 | Kyle Nguyen |
H146278 | Construction Support Services for Juan Street Concrete Replacement Project | 3/06/2015 | $139,560.00 | Atkins North America, Inc. | Sole Source | Kyle Nguyen |
H146197 | Programmatic Water Transmission Pipelines Condition Assessment | 3/02/2015 | $7,997,857.00 | Black & Veatch | 6 | Kyle Nguyen |
H146239 | Morena Boulevard Station Area Specific Plan | 2/06/2015 | $375,000.00 | PlaceWorks, Inc | 7 | Kyle Nguyen |
H146240 | Complete Boulevard Planning Study | 1/22/2015 | $216,539.00 | Wilson & Company, Inc. Engineers & Architects | 5 | Kyle Nguyen |
H146241 | Palm Avenue Revitalization Plan | 1/20/2015 | $229,680.00 | Chen Ryan Associates, Inc. | 6 | Kyle Nguyen |
H156315 | Environmental Impact Report for the Climate Action Plan (CAP) | 1/16/2015 | $150,000.00 | Environmental Science Associates | 4 | Kyle Nguyen |
H156303 | As-Needed Technical Services Consultant for Pure Water San Diego Program | 1/5/2015 | $30,000,000.00 | MHW Americas | 5 | Kyle Nguyen |
H146293 | As Needed Review Services Groundwater Wellfield & Plant Expansion | 12/19/2014 | $250,000.00 | Lee & Ro, Inc. | 5 | Kyle Nguyen |
H146098 | As Needed Mechanical Engineering Service | 12/10/2014 | $250,000.00 | Eskinder Berhanu & Associates | 6 | Kyle Nguyen |
H136030 | Arc Flash Hazard Analysis/Short-Circuit Coordination Study | 11/25/2014 | $749,750.00 | Black & Veatch | 5 | Frank Romero |
H146173 | As-Needed Architectural Design Services | 11/10/2014 | $1,000,000.00 | Architects Mosher Drew | 9 | Frank Romero |
H146172 | As-Needed Landscape Architectural Design Services | 11/7/2014 | $1,000,000.00 | KTU+A | 9 | Frank Romero |
H146169 | As-Needed Traffic Control Design Services | 11/7/2014 | $250,000.00 | Linscott, Law and Greenspan, Engineers | 9 | Frank Romero |
H146178 | Improvements for Fire Station Numbers 3, 8 and 15 | 11/6/2014 | $310,000.00 | Kitchell CEM, Inc. | 5 | Frank Romero |
H135849 | Balboa Park Golf Course-Clubhouse and Parking Lot - Phase II | 11/3/2014 | $240,660.00 | Roesling Nakamura Terada Architects, Inc. | 4 | Frank Romero |
H146171 | As-Needed Landscape Architectural Design Services | 10/23/2014 | $1,000,000.00 | Schmidt Design Group | 9 | Frank Romero |
H146246 | Skyline Hills Branch Library Public Art Project | 10/22/2014 | $140,000.00 | Actual Size Art Works, LLC | 5 | Frank Romero |
H146170 | As-Needed Traffic Control Design Services | 10/17/2014 | $250,000.00 | Wilson & Company, Inc., Engineers & Architects | 9 | Frank Romero |
H146174 | As-Needed Architectural Design Services | 10/16/2014 | $1,000,000.00 | Davy Architecture | 9 | Frank Romero |
H146114 | As-Needed Environmental Consultant Services | 10/13/2014 | $75,000.00 | Rincon Consultants, Inc. | 5 | Frank Romero |
H156358 | San Diego River Groundwater Model Project | 10/1/2014 | $249,000.00 | The Bureau of Reclamation | N/A | Frank Romero |
H146118 | Design of Rose Canyon Trunk Sewer Joint Repair | 09/24/2014 | $597,745.00 | GHD Inc. | 5 | Frank Romero |
H146223 | Evaluation of Anthropogenic Impacts on the San Diego Coastal Kelp Forest Ecosystem (2014-2019) | 8/25/2014 | $2,662,178.00 | UCSD | Sole Source | Cindy Crocker |
H146222 | Update of Construction Documents for Del Mar Mesa Neighborhood Park Phase II | 7/29/2014 | $68,620.00 | Neri Landscape Architecture | Sole Source | Cindy Crocker |
H146206 | Point Loma Ocean Outfall Discharge Study | 7/11/2014 | $234,885.00 | UCSD | Sole Source | Cindy Crocker |
H146059 | Design of 69th and Mohawk Pump Station | 7/1/2014 | $992,094.00 | RBF Consulting | 6 | Cindy Crocker |
H135855 | As-Needed Electrical Engineering/Control Systems Engineering Services | 7/1/2014 | $1,000,000.00 | Lee & Ro, Inc. | 6 | Cindy Crocker |