Fee Schedule for Mechanical, Electrical, Plumbing/Gas Permits

This information bulletin explains the process and fees associated with Mechanical, Electrical, and Plumbing (MEP) permits. Separate building and MEP permits are required for all non-residential and Multi-Dwelling Unit (MDU) construction. Each building must have its own MEP permit. Electrical permits are required for all electrical work except as exempted in San Diego Municipal Code (SDMC) §129.0303 of the Land Development Code. Mechanical and plumbing permits are required for all mechanical and plumbing work except as exempted in SDMC §129.0403 and §129.0404 of the Land Development Code.

Plumbing and Mechanical equipment, including water heaters, washing machines, air conditioner units and pool equipment, shall not be installed in required side or rear yards of Residential Zones unless they comply with SDMC §131.0461(a)(5).

I. Required Documents and Outside Reviews

  1. Project Contact Forms
    The Project Contacts Information Form (DS-345) must be submitted at the time of permit issuance for all other permits.
  2. Owner-Builder Form
    If the property owner is doing the work or is hiring different contractors, a separate Owner-Builder Verification Form (DS-3042) must be signed by the owner before the permit can be issued.
  3. Circuit Card
    A completed and signed City of San Diego Electrical Circuit Card (DS-1779) is required at the time of inspection of any electrical components or systems added to a single dwelling unit or duplex unless electrical plans, calculations or single-line drawings are included in the approved plans.
  4. Home Energy Rating System (HERS) Rating
    A HERS evaluation is required to meet the state’s Title 24 energy efficiency standards and to obtain final inspection approval, applying to:
    • New residential construction.
    • Major HVAC system changes or replacements.
    • Home additions exceeding 1,000 square feet.
    • Certain renovations to existing homes.
    • Installation of more than 40 feet of new ductwork.

A certified HERS rater—an independent third party—conducts on-site inspections and diagnostic testing to verify that the building meets energy performance requirements, issuing a certificate to the homeowner or contractor. View the directory of City-certified HERS Raters.

  1. Historical Review
    If your site contains a designated historical resource or is located in a historic district, plans will be required for review. Refer to Information Bulletin 581, Designated Historical Resource Review.
  2. Address Review
    If an address has not been assigned, a site plan and an addressing review will be required. An additional $98.86 fee may be assessed for assigning an address.
  3. Food Establishment Wastewater Discharge (FEWD) Review
    All new or replacement Grease Traps/Interceptors require approval from the Public Utilities Department. Refer to the Public Utilities website.
  4. Building Permit and/or Building Construction Plans Required
    Building Construction Plans are required to be submitted, and a Building Permit is required when one or more of the following conditions are present:
    • The supporting floor, roof and platform structure require alterations to accommodate support and anchorage of the equipment.
    • When special inspections are required for reasons other than due to the installation of post-installed anchors.
    • Equipment is supported on a new pad on grade, and that is located on the exterior of a building's footprint or has an operating weight in excess of 2,500 lb.
  5. Structural Calculations
    Structural Calculations are required to determine the anchorage of the equipment to the supporting ground, floor, roof and platform and to verify the adequacy of the supporting structural framing elements when one or more of the following conditions are present:
    • Equipment weight exceeds 400 pounds.
    • The center of gravity (mass) of the equipment exceeds four feet above the supporting base.

II. Options for Service

  1. Simple Permits - MEP
    Items listed in the following tables that qualify for Simple Permits-MEP do not require a plan review and can be applied for through the online portal by selecting 'Simple Permits'. Note that historical designated resources and projects in historic districts do not qualify for Simple Permits-MEP and must be submitted as a Standalone MEP permit with plans. If a project scope includes items that need plan review along with items that qualify for Simple Permits-MEP, the project does not qualify for Simple Permits–MEP and all items must be included in the permit scope to be plan reviewed.
  2. Standalone MEP with Plans
    MEP permits that require plans and MEP permits related to a Building Permit must be submitted through the online portal. Select the specific permit type for requested standalone MEPs - Electrical, Mechanical or Plumbing Permits.
  3. Building Permits with MEP
    Building Permits that contain MEP work must be submitted through the online portal by selecting Building Permit.

III. Fees

  1. Mapping Fee
    This fee is collected to fund automation efforts and online GIS data and mapping for Development Services. It is charged when there are plans, drawings, maps or other geographical documents utilized for project review.

    Mapping Fee......................................................... $12.16

  2. Plan Check/Inspection Fee
    Items identified on the fee schedules, as requiring plans for non-residential and MDU construction (three or more units), will be reviewed prior to the issuance of a permit. In most cases, the plan review occurs as part of a building permit application, and the inspection fees are assessed at that time. If a plan review is required, and one was not conducted as part of a building permit application, plans will be required, and a plan review fee will be charged per Information Bulletin 501, in addition to the inspection fees per the fee schedule.

Plan check, inspection, and records fees are non-refundable. To learn more, see the Refund Policy noted within the Refund Application Form (DS-721).

Table 1A: Mechanical Fee Schedule (per Building Use)

The following fees are for mechanical systems that serve the specified use (for example, the hotel fee includes all mechanical systems serving hotel rooms). Mechanical systems serving mixed uses shall be charged based upon each fee listed in Table 1A or Table 1B, as applicable.

TABLE 1A: MECHANICAL FEE SCHEDULE (PER BUILDING USE)
Qualifies for Simple Permit—MEPUseUnit

First Unit

Each Add'l Unit

NoHotel New MechPer Guest Room

$353.13

$87.68

NoMultiple Dwelling Unit (MDU) - New MechanicalFirst 3 Units

$353.13

Not applicable

Next 4 -50 Units

Not applicable

$87.68

Addl 10 Units over 50

Not applicable

$529.71

NoMDU Remodel- New MechanicalEach Unit

$264.25

$43.84

NoNon-Residential Shell 1Per Floor

$440.82

Not applicable

NoNon-Residential Tenant Improvement—MechanicalEach 5,000 sf

$176.57

Not applicable

NoExhaust System (Garage)Each System

$299.54

$87.68

Table 1B: Mechanical Fee Schedule (per Item)

The following fees are for standalone permits or items not serving the building uses listed in Table 1A.

TABLE 1B: MECHANICAL FEE SCHEDULE (PER ITEM)
Qualifies for Simple Permit—MEPItem 3, 4Unit

First Unit

Each Add'l Unit

Single Family, Duplex, TownhouseNon-Residential or MDU
NewRepair/Replace in Kind
YesNoYesAir Handler, Mini-Split, HumidifierEach

$176.57

$52.39

YesYesYesAppliance Vent/ChimneyEach

$87.68

$35.29

YesNoYesBoilerEach

$176.57

$52.39

YesNoNoChillerEach

$264.25

$52.39

YesNoYesCondensing Unit for HVAC 2Each

$131.52

Not applicable

YesNoNoCooling TowerEach

$264.25

$52.39

YesNoNoDryer VentEach

$105.98

$52.39

YesNoYesEvaporative Cooler - Makeup Air UnitEach

$105.98

$52.39

YesYesYesExhaust FanEach

$105.98

$35.29

YesNoYesFan Coil UnitEach

$176.57

$52.39

YesNoYesFurnace/(FAU)2Each

$176.57

$52.39

YesNoYesGas System Leak RepairEach 5 Outlets

$264.25

$87.68

YesNoYesGas System/MeterEach 5 Outlets

$264.25

$87.68

YesNoYesHeat Pump-Package UnitEach

$176.57

$52.39

YesNoYesHeater-Unit/RadiantEach

$105.98

$52.39

N/ANoNoHood Type I and/or DuctEach

$264.25

$70.58

N/ANoNoHood Type II and/or DuctEach

$141.28

$52.39

NoNoNoVariable Air Volume BoxEach

$141.28

Not applicable

Add'l 5 Units

Not applicable

$52.39

YesNoNoWalk-In Cooler/CondenserEach

$141.28

$52.39

Table 1A Footnote 1: Non-residential shell fee shall be used when the shell building includes the heating/cooling systems. For shell buildings that do not include the heating/cooling system, each individual system shall be charged per Table 1B.

Table 1B Footnote 2: Replacement of these systems requires a HERS rating when more than 40 feet of duct is in unconditioned space. See Section I(C) for details.

Table 1B Footnote 3: A separate Building Permit is required when scope of work includes drywall, wood framing or replacing/installing new finishes in MDU or non-residential building.

Table 1B Footnote 4: A separate Electrical Permit is required if electrical circuits/devices are installed/modified in a MDU or non-residential building.

Table 2: Electrical Fee Schedule (per Building)

TABLE 2: ELECTRICAL FEE SCHEDULE (PER BUILDING)
Qualifies for Simple Permit-MEPSystemUnit

First Unit

Each Add'l Unit

Single Family, Duplex, TownhouseNon-Residential or MDU
Not applicableNoElectrical Service New MDU 1Dwelling Unit

$1,412.54

$87.68

YesYesCircuits 15-45 AmpsFirst 5 Circuits

$176.57

Not applicable

YesYesCircuits 15-45 Amps6-10 Circuits

Not applicable

$52.39

YesYesCircuits 15-45 AmpsEach additional 10 circuits over 10, up to 50

Not applicable

$52.39

YesYesCircuits 15-45 AmpsEach additional 50 circuits over 50

Not applicable

$141.28

YesYesCircuits 50-200 AmpsEach 3 Circuits

$353.13

Not applicable

YesYesPanel Replace/Upgrade up to 200 ampEach

$176.57

Not applicable

YesYesCircuits 225-400 AmpsEach 2 Circuits

$353.13

Not applicable

NoNoCircuits 450-1,000 AmpsEach

$440.82

Not applicable

NoNoCircuits 1,200 Amps or LargerEach

$440.82

Not applicable

YesYesConduit and J Box OnlyEach

$176.57

Not applicable

Yes (Private Garage Only)NoElectrical Vehicle Charging Systems in Private Garages. See Information Bulletin 187 for detailed information, including fees.
NoNoGenerator Only 2Each

$176.57

Not applicable

NoNoSolar Photovoltaic. See Information Bulletin 301 for detailed information, including fees.
N/ANoSpecialized Occupancy (e.g., healthcare, hazardous location) 3Each

$529.71

Not applicable

YesYesTemp Pole (Construction Power) 4Each

$176.57

Not applicable

Table 2 Footnote 1: In addition to this fee, use “Circuits” fees for common area distribution circuits in an MDU building.

Table 2 Footnote 2: A Hazardous Materials permit from SDFD (see Information Bulletin 116) and a separate plumbing, building, and/or mechanical permit may also be required.

Table 2 Footnote 3: This fee is in addition to the electrical circuit fees and is required for specialized occupancies as identified in Chapter 5 of the California Electrical Code.

Table 2 Footnote 4: Temporary power qualifies for Simple Permits up to 400amps. Services over 400amps must be submitted with plans.

Table 3A: Plumbing Fee Schedule (per Building Use)

The following fees are for plumbing systems that serve the specified use (for example, the hotel fee includes all plumbing systems serving hotel rooms). Plumbing systems serving mixed uses shall be charged based upon each fee listed in Table 3A or Table 3B, as applicable.

TABLE 3A: PLUMBING FEE SCHEDULE (PER BUILDING USE)
Qualifies for Simple Permit—MEPUseUnit

First Unit

Each Add'l Unit

NoHotels New-PlumbingPer Guest Room

$264.25

$52.39

NoLaboratory w/out restroomsEach 5 Fixtures

$264.25

$52.39

NoMultiple Dwelling Unit Building (MDU - New)Each Dwelling Unit

$264.25

$176.57

NoMDU Building - RemodelEach Dwelling Unit

$264.25

$52.39

NoNon-Residential KitchenEach 5 Fixtures

$353.13

$122.97

NoNon-Residential RestroomsEach 5 Fixtures

$264.25

$70.58

NoNon-Residential Shell (not including restrooms)Each Floor

$264.25

$122.97

NoNon-Residential Plumbing Tenant Improvement (not including restrooms or kitchen)Each Floor

$264.25

$122.97

NoParking Garages- PlumbingPer Floor

$264.25

$52.39

YesResidential buildings (Group R-2 or R-3 occupancy only) – existing Kitchen/Bathroom Remodel with no changes to structural elements, wall framing or exterior walls and no added plumbing fixtures/gas appliances. (Information Bulletin 203) 1Per Dwelling Unit

$440.82

Not applicable

Table 3B: Plumbing Fee Schedule (per Item)

The following fees are for standalone permits (plumbing only) or for items that are not serving building uses listed in Table 3A.

TABLE 3B: PLUMBING FEE SCHEDULE (PER ITEM)
Qualifies for Simple Permit - MEPItems 2, 3Unit

First Unit

Each Add'l Unit

Single Family, Duplex, TownhouseNon-Residential or MDU
NewRepair/Replace in Kind
YesNoYesBackflow Preventer-DomesticEach

$87.68

$52.39

YesYesYesBuilding DrainPer Floor

$52.39

Not applicable

YesNoYesGas System Leak RepairEach 5 Outlets

$264.25

$87.68

YesNoYesGas System/MeterEach 5 Outlets

$264.25

$87.68

NoNoNoReclaim Water SystemEach

$87.68

Not applicable

NoNoNoGray Water SystemsEach

$176.57

Not applicable

N/ANoYesGrease Trap / Interceptor 4Each

$264.25

$87.68

NoNoNoPrivate Utilities- Water/Sewer (Information Bulletin 182)First 100 LF

$264.25

Not applicable

Each Add'l 10 LF

Not applicable

$52.39

YesNoYesSewage EjectorEach

$264.25

$87.68

NoNoYesSolar Water Heating SystemEach

$176.57

Not applicable

YesNoYesWater Heater 5Each

$122.97

Not applicable

YesNoYesWater SoftenerEach

$87.68

$52.39

YesNoYesWater SubmeterEach 4 Submeters

$87.68

$35.29

N/AYesYesWater/Waste Pipe Repair/Replacement – Non-ResidentialPer Floor

$264.25

$122.97

YesN/AYesWater/Waste Pipe Repair/Replacement - ResidentialPer Dwelling Unit

$264.25

$87.68

Table 3A Footnote 1: This fee includes the cost of a no-plan combination permit for all plumbing, mechanical, and electrical work. Plans will be required if the scope of work includes any framing.

Table 3B Footnote 2: A separate Building Permit is required when the scope of work includes drywall, wood framing or replacing/installing new finishes in MDU or non-residential building.

Table 3B Footnote 3: A separate Electrical Permit is required if electrical circuits/devices are installed/modified in an MDU or non-residential building.

Table 3B Footnote 4: The FEWD "Plan Check List" must be provided at the time of inspection. See Item (G) for details.

Table 3B Footnote 5: For non-residential or MDU buildings, replacing a water heater with a tankless water heater requires plans and plan review.