Miramar Treatment Plant Project Schedule
Contract Name | Construction Timeframe |
Early Start Improvements Phase I | Apr. 2001 - Jan. 2003 |
Early Start Improvements Phase II | Sept. 2002 - Feb. 2005 |
Contract A | Aug. 2003 - Dec. 2007 |
Contact B | Nov. 2007 - Dec. 2009 |
Contract C | May 2008 - Mar. 2010 |
Contract D | Late 2011 ? Mid 2012 |