Gold Coast Drive and Parkdale Avenue
Streets Impacted:
- Gold Coast Drive (East of Camino Ruiz, West of Thanksgiving Lane): 1.2 linear miles
- Parkdale Avenue: 0.9 linear miles
- Gold Coast Way: cul de sac
- Gold Coast Court: cul de sac
- Lipscomb Drive: 0.2 linear miles
Project Cost:
- $12.7 million
Project Timeline:
- Design Phase: July 2020 Completion
- Construction contract award: August 2020
Project awaiting commercial paper (CP) funding allocation
Construction timeframe: 12 months upon allocation of funding
Advocacy:
June 27, 2018: Informational Update in Mira Mesa
November 5, 2018: Informational Update in Mira Mesa
April 30, 2020: Budget Review Committee
November 17, 2020: City Council
June 24, 2021: Infrastructure Committee
August 2, 2021: City Council