How to Obtain a Permit for Private Utilities
INFORMATION BULLETIN
182
July 2024
This Information Bulletin describes the procedure for obtaining a permit to install private underground for domestic water and sewer. A separate plumbing permit is required for installation of all private underground domestic water and sewer when proposing to serve more than one building, not a part of a Public Right-of-Way permit. Single buildings connected to a public main do not require a separate plumbing permit. For Private Fire Service and Hydrants, see Information Bulletin 181, Private Underground Fire Service and Hydrants.
Definitions
Terms used in this Information Bulletin:
- Private Water is a privately maintained water system between the public water meter and building (s).
- Private Sewer is a privately maintained sewer system between building (s) and the Public Right of Way clean out.
- Private Fire Hydrant or Service is a privately maintained water system serving a private fire system between the backflow and building (s).
Submittal Requirements
The following plans and documents shall be provided when applying for a private water or sewer system Plumbing permit.
- Forms
The Project Contact form (DS-345) must be completed and submitted. - Plans
Provide and submit the construction plans, including the following information:- Associated building or grading permit number.
- Detailed scope of work (i.e.: Installation of private underground water service serving 12 single dwelling units). Include all buildings being served by the underground utility.
- Limit of work.
- Property line dimensions and any easements.
- Identify which portions of the system were designed in accordance with Water Design Guide (for water), Sewer Design Guide (for sewer) or California Plumbing Code (for water and sewer).
- Clearly define existing and proposed public and private utilities applied for under this permit or separate permit.
- Location, pipe sizes, slope, connection(s) and material of piping.
- Calculation for sizing of water and sewer piping.
- Depth of cover.
- Sewer clean-out size and locations.
- Sewer manhole locations.
- Cross section(s) and elevation(s).
- If the plan is intended to be professionally certified, then the title of the project must include the language, “Professional Certification of Private Utilities”. See Section IIA below for more information about Professional Certification.
- Professional certification plans must be signed and stamped by the responsible design professional, either a registered Civil or Mechanical Engineer. The registered design professional must provide a signed statement with the following language on the first sheet of the plans in order to qualify for Professional Certification:
- I hereby acknowledge that I am the responsible design professional for this project and that I am accountable for compliance with the governing policies, regulations, and code requirements applicable to this installation.
- I hereby acknowledge that the maintenance of my Professional Certification privilege requires accurate plans and installations on a consistent basis. I hereby certify that all work will occur within private property without easements and the City assumes no liability.
- With this submittal, I confirm that the plans and documents submitted for approval comply with the governing policies, regulations and code requirements that are applicable to the proposed installation.
- I understand that, if the installation deviates from requirements, a construction change may be required, and final approval will be delayed. I also understand that submitting inaccurate plans and installations may result in the revocation of my Professional Certification privilege.
Options for Service
Professional Certification
Plan review for private water and sewer systems is not required when the plans have been professionally certified. Items 13 –14 listed in Section I must appear on the first sheet of the plans in order to be considered as professional certification, along with all other applicable items in Section I. Projects that are professionally certified still require inspections as described in Section V.
- Plan review
Projects that are not professionally certified as specified in Section IIIA will be plan reviewed. - Submittal of Plans
Private Utilities Permits must be submitted through the online portal by selecting Plumbing/Gas Permit.
Other Requirements
- Connection to the City’s water or sewer mains requires a separate right-of-way permit. See Information Bulletin 166, “How to Obtain a Permit for Water, Sewer or Fire Service”.
- The installation of a cross-connection control device on all water services must be in accordance with Information Bulletin 113, “How to Obtain Approval for Cross-Connection Controls”.
Fees
References
- Project Contacts Form (DS-345)
- Project Submittal Manual, Section 3
- Information Bulletin 113, Cross-Connection Control
- Information Bulletin 120, Project Inspection
- Information Bulletin 166, Water, Sewer & Fire Service
- Information Bulletin 181, Private Underground Fire Service & Hydrants
- Information Bulletin 501, Fee Schedule for Construction Permits—Structures